This Table of Contents document outlines the comprehensive bid package and contract specifications for the 2027 Sewer System Improvements Project administered by Capital Region Water (CRW) in Harrisburg, Pennsylvania. The project encompasses sewer system improvements including gravity piping installation, concrete manhole construction, hydrostatic testing, vacuum testing, air testing, mandrel testing, and related utility work. The contract is structured on a unit price basis with sealed bids to be received online through the PennBid Procurement Portal until October 27, 2026, at 10:00 a.m. EST, at which time bids will be opened. The work includes all materials, equipment, labor, and miscellaneous items necessary to complete the contract as detailed in the project documents. The project will take place in Harrisburg, Pennsylvania, with multiple CRW facilities potentially involved. No mandatory pre-bid meeting is specified in the available information, though bidders may request site visits to evaluate project conditions.
The bid package includes standard procurement and contracting requirements such as a Minority/Women/Disadvantaged Business Enterprise (MWDBE) Plan, wage rate requirements and wage determination schedules, performance and payment bonds, anti-pollution measures, and steel origin certifications. Capital Region Water intends to award the contract to the overall lowest responsible bidder as determined by its Board of Directors in the best interest of the organization. The contract documents encompass detailed specifications across multiple divisions covering general requirements, concrete work, earthwork, exterior improvements, and utility construction, with comprehensive quality requirements, submittal procedures, and closeout specifications. Performance bonds and payment bonds are required in accordance with contract documents, and all bid documents are available at no cost through the PennBid Procurement Portal.
View the file
Other files
Show 40 more
Latest 50 of 116 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2027 Sewer System Improvements Project
Table of Contents
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS DOCUMENT: PAGES
Procurement Requirements
ADVERTISEMENT FOR BIDS ..................................................................... 00 11 13: 1-2
INSTRUCTIONS TO BIDDERS .................................................................... 00 21 13: 1-13
A. MINORITY/WOMEN/DISADVANTAGED BUSINESS ENTERPRISE PLAN 00 21 13: 1-15
PERMIT APPLICATIONS ............................................................................ 00 31 43: 1
BID FORM SIGNATURE PAGES .................................................................. 00 41 16: 1-4
QUALIFICATION STATEMENT .................................................................... 00 41 20: 1-18
BID BOND (DAMAGES FORM) .................................................................. 00 43 13: 1-3
NON-COLLUSION AFFIDAVIT .................................................................... 00 45 19: 1-2
CERTIFICATION OF NON-SEGREGATED FACILITIES
& NON-EMPLOYMENT OF ILLEGAL ALIEN LABOR ............................... 00 45 33: 1
CERTIFICATION OF BIDDER REGARDING EQUAL EMPLOYMENT OPPORTUNITY 00 45 36: 1
PUBLIC WORKS EMPLOYMENT VERIFICATION FORM .................................... 00 45 46: 1
Contracting Requirements
STEEL ORIGIN CERTIFICATION ................................................................. 00 45 60: 1
NOTICE OF AWARD ................................................................................. 00 51 00: 2
AGREEMENT BETWEEN OWNER AND CONTRACTOR .................................... 00 52 00: 1-8
NOTICE TO PROCEED .............................................................................. 00 55 00: 1
PROJECT FORMS ..................................................................................... 00 60 00: 1
PERFORMANCE BOND .............................................................................. 00 61 13: 1-10
PAYMENT BOND ...................................................................................... 00 61 14: 1-4
WARRANTY BOND ................................................................................... 00 61 19: 1-3
APPLICATION FOR PAYMENT FORM ........................................................... 00 62 76: 1-4
REQUEST FOR INFORMATION/INTERPRETATION FORM ................................ 00 63 13: 1
FIELD ORDER FORM ................................................................................ 00 63 36: 1
CHANGE ORDER FORM ............................................................................ 00 63 63: 1-2
CERTIFICATE OF SUBSTANTIAL COMPLETION ............................................. 00 65 16: 1-2
AFFIDAVIT OF RELEASE OF LIENS ............................................................. 00 65 19.16: 1-2
CONSENT OF SURETY TO FINAL PAYMENT .................................................. 00 65 19.19: 1-2
NOTICE OF ACCEPTABILITY OF WORK ....................................................... 00 65 19.23: 1
GENERAL CONDITIONS ............................................................................ 00 72 00: 1-102
WAGE RATE REQUIREMENTS .................................................................... 00 73 43: 1-4
WAGE DETERMINATION SCHEDULE ........................................................... 00 73 46: 1-7
ANTI-POLLUTION MEASURES .................................................................... 00 73 53: 1
STATUTORY REQUIREMENTS .................................................................... 00 73 73: 1-5
Specifications
DIVISION 01 - GENERAL REQUIREMENTS SECTION: PAGES
01 10 00 – SUMMARY .............................................................................. 01 10 00: 1-4
01 22 00 – UNIT PRICES .......................................................................... 01 22 00: 1-14
01 25 00 – SUBSTITUTION PROCEDURES .................................................. 01 25 00: 1-6
01 26 00 – CONTRACT MODIFICATION PROCEDURES .................................. 01 26 00: 1-3
01 26 13 – REQUESTS FOR INTERPRETATION ............................................ 01 26 13: 1-3
01 29 00 – PAYMENT PROCEDURES ........................................................... 01 29 00: 1-4
01 31 13 – PROJECT COORDINATION ........................................................ 01 31 13: 1-2
01 31 19 – PROJECT MEETINGS ................................................................ 01 31 19: 1-3
01 32 16 – CONSTRUCTION PROGRESS SCHEDULE ..................................... 01 32 16: 1-4
01 32 26 – CONSTRUCTION PROGRESS REPORTING ................................... 01 32 26: 1-2
01 32 33 – PHOTOGRAPHIC DOCUMENTATION ........................................... 01 32 33: 1-2
01 32 36 – VIDEO MONITORING AND DOCUMENTATION .............................. 01 32 36: 1-2
01 33 00 – SUBMITTAL PROCEDURES ........................................................ 01 33 00: 1-8
01 35 15 – NOTIFICATIONS AND OTHER COORDINATION ............................ 01 35 15: 1-3
01 40 00 – QUALITY REQUIREMENTS ........................................................ 01 40 00: 1-5
01 41 26 – PERMIT REQUIREMENTS .......................................................... 01 41 26: 1-5
A. CITY OF HARRISBURG STREET CLOSURE REQUEST FORM ......... 01 41 26A: 1-1
B. CITY OF HARRISBURG NOTICE OF CONSTRUCTION .................. 01 41 26B: 1-2
C. CHLORINATED WATER DISCHARGE – INCIDENT REPORT FORM . 01 41 26C: 1-2
01 42 00 – REFERENCES .......................................................................... 01 42 00: 1-7
01 50 00 – TEMPORARY FACILITIES AND CONTROLS................................... 01 50 00: 1-7
01 61 00 – PRODUCT REQUIREMENTS ....................................................... 01 61 00: 1-4
01 73 00 – EXECUTION REQUIREMENTS .................................................... 01 73 00: 1-6
01 74 19 – CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL ............... 01 74 19: 1-3
01 77 00 – CLOSEOUT PROCEDURES ......................................................... 01 77 00: 1-3
01 78 36 – WARRANTIES ......................................................................... 01 78 36: 1-2
01 78 39 – PROJECT RECORD DOCUMENTS ................................................ 01 78 39: 1-11
DIVISION 02 – EXISTING CONDITIONS SECTION: PAGES
02 41 16 – STRUCTURE DEMOLITION ........................................................ 02 41 16: 1-5
DIVISION 03 – CONCRETE SECTION: PAGES
03 11 00 – CONCRETE FORMING .............................................................. 03 11 00: 1-5
03 20 00 – CONCRETE REINFORCING ........................................................ 03 20 00: 1-3
03 30 00 – CAST-IN-PLACE CONCRETE ...................................................... 03 30 00: 1-10
03 39 00 – CONCRETE CURING ................................................................ 03 39 00: 1-3
03 60 00 – GROUTING ............................................................................. 03 60 00: 1-3
DIVISION 31 – EARTHWORK SECTION: PAGES
31 23 19 – DEWATERING ......................................................................... 31 23 19: 1-4
31 23 33 – TRENCHING AND BACKFILLING FOR UTILITIES .......................... 31 23 33: 1-13
31 25 00 – EROSION AND SEDIMENTATION CONTROLS .............................. 31 25 00: 1
31 40 00 – SHORING AND UNDERPINNING ................................................ 31 40 00: 1-2
DIVISION 32 – EXTERIOR IMPROVEMENTS SECTION: PAGES
32 12 16 – ASPHALT PAVING ................................................................... 32 12 16: 1-7
32 13 13 – CONCRETE PAVING ................................................................. 32 13 13: 1-4
32 92 00 – TURF AND GRASSES ............................................................... 32 92 00: 1-8
DIVISION 33 – UTILITIES SECTION: PAGES
33 01 30 – OPERATION AND MAINTENANCE OF SEWER UTILITIES ................ 33 01 10: 1-4
33 01 31 – TV INSPECTION OF SEWER PIPELINES ...................................... 33 01 31: 1-3
33 05 05.31 – HYDROSTATIC TESTING ...................................................... 33 05 05.31: 1-7
33 05 05.36 – VACUUM TESTING .............................................................. 33 05 05.36: 1-3
33 05 05.41 – AIR TESTING ..................................................................... 33 05 05.41: 1-5
33 05 05.43 – MANDREL TESTING ............................................................ 33 05 05.43: 1-2
33 05 53 – IDENTIFICATION FOR UTILITIES PIPING AND EQUIPMENT ........... 33 05 53: 1-2
33 05 61 – CONCRETE MANHOLES ............................................................ 33 05 61: 1-14
33 13 00 – DISINFECTION OF WATER UTILITY DISTRIBUTION ..................... 33 13 00: 1-16
33 14 13 – PUBLIC WATER UTILITY DISTRIBUTION PIPING .......................... 33 14 13: 1-9
33 14 17 – SITE WATER SERVICE UTILITY LATERALS .................................. 33 14 17: 1-7
33 14 19 – VALVES AND HYDRANTS FOR WATER UTILITY SERVICE ............... 33 14 19: 1-6
33 31 11 – PUBLIC SANITARY SEWERAGE GRAVITY PIPING ......................... 33 31 11: 1-9