33 05 05.41 - Air Testing.pdf

PDF 217 KB Posted

Attached to
2027 Sewer System Improvements Project
Solicitation number
Not on record
Issued by
Dauphin County, Harveys Lake Borough, Pennsylvania

About this file

This is a technical specification document for air testing procedures in gravity sewer piping systems, applicable to the 2027 Sewer System Improvements Project managed by Capital Region Water (CRW) in Harrisburg, Pennsylvania. The specification outlines comprehensive requirements for low-pressure air testing of gravity sewer pipes between adjacent manholes and individual joint testing to verify system integrity and identify leaks. Testing procedures must be submitted by contractors prior to work commencement, along with equipment certifications, test schedules, and disposal plans for test water. The contractor must conduct all testing in the presence of the Engineer, with testing authorized only when ambient air temperatures reach 35°F or higher. Testing duration varies by pipe diameter, ranging from 3 minutes 46 seconds per 100 feet for 4-inch pipe to 51 minutes 17 seconds for 36-inch pipe, with acceptance criteria requiring pressure drops not exceeding 1.0 psi during the specified testing period for line acceptance tests or 1.0 psi in 15 seconds for joint acceptance tests.

Equipment specifications require a complete air testing system with pneumatically expanded packers (hydraulic or mechanical expansion devices are prohibited), calibrated pressure gauges accurate to 0.1 psi, compressed air systems with approved pressure regulators, and remote monitoring equipment allowing simultaneous observation of test conditions by the Engineer. Contractors must furnish laboratory-calibrated test gauges and demonstrate equipment capability through a demonstration test using a test cylinder with a simulated leak prior to commencing work, with readiness tests required before testing each sewer section. Lateral connection testing requires isolation of the connection and first joint, with passage criteria met if pressure drops from 4 psi to 3 psi within more than 15 seconds. All failed sections must be repaired and retested until specifications are met. Test records must document sewer section identification, test pressures, joint locations, pass/fail results, achieved pressures, equipment calibration data, and ambient temperature at time of testing. Final system acceptance occurs only upon written approval by CRW ownership following successful Engineer inspection, with warranty periods commencing upon such acceptance.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 41 26-B - City of Harrisburg Notice of Construction Cover Sheet.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 05 05.41 - AIR TESTING

1.0 General

1.1 Summary

A. Section Includes: Low-pressure air testing of gravity sewer piping.

B. Related Requirements:

1. Section 33 31 11 – Public Sanitary Sewerage Gravity Piping: Pipe materials, manholes, and accessories normally encountered with gravity sewerage piping.

1.2 Submittals

A. Section 01 33 00 – Submittal Procedures: Requirements for submittals.

B. Submit following items prior to start of testing:

1. Testing procedures.

2. List of test equipment.

3. Testing sequence schedule.

4. Provisions for disposal of flushing and test water.

5. Certification of test gage calibration.

C. Test and Evaluation Reports: The Contractor shall indicate results of piping tests.

D. Qualifications Statement:

1. Submit qualifications for applicator.

2.0 Products

2.1 Air Testing

A. Equipment: The Contractor shall provide a complete air testing system specifically designed and constructed for internal air pressure tightness integrity testing of sewer piping joints. The equipment shall be constructed in such a way as to provide means for introducing air, under pressure, into the void area created by the expanded ends of the joint-testing packer and a means for continuously measuring the actual static pressure of the air within the void area only. The system shall include, but not be limited to, the following items and features:

1. Packer: Open end, cylindrical casing of a size less than the pipe diameter, remote controlled for forward and backward movement within the sewer mains:

1. Air-inflatable sleeves (or diaphragms) mounted at each end of the casing exterior with the ends of sleeves fastened to the casing. Devices that have sleeves which may require extreme pressures to “seat” against the inside periphery of the sewer main pipe are not permitted.

2. Regulate expansion of air-inflatable sleeves by precise pressure gauges and controls. Under no conditions will hydraulically or mechanically expanded devices be allowed.

3. Pass conduits leading from the surface though one end of the packer casing adapted to supply air, under pressure, to the space at the center of the casing.

2. Compressed Air System: Compressed air system shall include compressed air source, piping, valves and pressure gauges to control the rate of air flow to the packer sleeves and test section:

1. To prevent loading the test section with the full pressure of the compressor, the test equipment shall be provided with an approved pressure regulating device.

2. Pressure gauges shall be calibrated to 0.1 psi.

3. Test Monitoring Equipment: Provide test monitoring equipment to transmit the value of the void air pressure to a remote test pressure monitoring gauge or readout:

a. Test pressure monitoring gauge or readout shall be located to allow for simultaneous and continuous observation of the television monitor and test monitoring equipment by the Engineer.

3.0 Execution

3.1 Examination

A. Section 01 73 00 – Execution Requirements: Requirements for installation examination.

B. The Contractor shall verify that piping is ready for testing.

C. The Contractor shall verify that trenches are backfilled.

3.2 Installation

A. Section 01 73 00 – Execution Requirements: Requirements for preparation.

B. Plugs:

1. Plug outlets, wye branches, and laterals.

2. Brace plus to resist test pressures.

3.3 Field Quality Control

A. 01 40 00 – Quality Requirements: Requirements for inspecting and testing.

B. General Requirements: The Contractor shall conduct tests specified herein so that each pipeline installed in the Project is tested to the Engineer's satisfaction:

1. Provide tools, materials, apparatuses, and instruments necessary for pipeline testing.

2. Conduct tests in the presence of and to the satisfaction of the Engineer.

C. Cleaning Prior to Tests: Before tests are conducted, the Contractor shall clean piping including sewers, branches and service connections until free of dirt or silt or construction debris

D. Line Acceptance Test for Gravity Lines: (Leakage tests): After a section of sewer is constructed between adjacent manholes, backfilled and successfully cleaned and passes an alignment test, the Contractor shall perform a low-pressure air Line

Acceptance Test in accordance with ASTM F 1417 and the following:

1. Seal and brace sewer piping at upstream and downstream manholes and at all laterals. Test plug seal before actual use by testing plugs outside the trench in one length of pipe pressurized to maximum anticipated testing pressure. Plugs shall hold without bracing and show no movement. After plug is placed in pipe and sealed, brace or protect as insurance against blow out. Protect workers from potential plug blow out.

2. Introduce low pressure air slowly into sealed sewer section. The test shall be performed as follows:

a. Introduce air pressure slowly to approximately four (4) psig.

b. Determine ground water elevation above spring line of piping.

c. For every foot of ground water above spring line of piping, increase starting air test pressure by 0.43 psi.

d. Do not increase pressure above 10 psig.

e. Allow pressure to stabilize for at least five minutes. Add air only to maintain required test pressure.

f. After the stabilization period, adjust the test pressure to the required test pressure, and disconnect the air supply. Then measure drop in pressure during testing period

g. Minimum Testing Duration in Minutes Per 100 Feet (do not make allowance for laterals):

i. Pipe Size 4 Inches: 3:46

ii. Pipe Size 6 Inches: 5:40.

iii. Pipe Size 8 Inches: 7:34.

iv. Pipe Size 10 Inches: 9:26.

v. Pipe Size 12 Inches: 11:20.

vi. Pipe Size 15 Inches: 14:10.

vii. Pipe Size 18 Inches: 17:00.

viii. Pipe Size 21 Inches: 19:50.

ix. Pipe Size 24 Inches: 22:47.

x. Pipe Size 27 Inches: 28:51.

xi. Pipe Size 30 Inches: 35:37.

xii. Pipe Size 36 Inches: 51:17.

xiii. Pipe Size 42 Inches: 69:48.

h. If air pressure drops more than 1.0 psi during testing period, piping has failed.

i. If 1.0 psi air pressure drop has not occurred during testing period, piping is acceptable; discontinue testing.

j. If piping fails, test reach of piping in incremental stages until leaks are isolated, repair leaks, and retest entire reach between manholes.

k. If unsatisfactory testing results are achieved, make necessary repairs and retest until result meets criteria.

3. Repair visible leaks regardless of quantity of leakage.

4. After laterals are installed, re-test line in accordance with the above procedure if line is initially tested before the installation of laterals.

5. Where lines are live and carry flow, perform Joint Acceptance Test by testing one joint at a time as described in paragraph 3.3.C, below.

E. Joint Acceptance Test for Gravity Lines (Leakage Tests):

1. Joint Testing Equipment Control Test: A two-part control test shall be performed by the Contractor to ensure the accuracy, integrity, and performance capabilities of the testing equipment; testing as follows:

a. Demonstration Test: Prior to starting the air testing work, perform a demonstration test in the presence of the Engineer using a test cylinder, furnished by the Contractor, constructed so that a leak can be simulated. The demonstration test shall use the procedures specified in this Section.

i. The purpose of the demonstration test is to establish that the air testing system is capable of meeting the specified test criteria.

ii. If this test cannot be performed successfully, the Contractor shall repair or otherwise modify his equipment and repeat the test until the results are satisfactory to the Engineer.

iii. The Engineer may require that this test be repeated at any time during the joint testing work when, in the Engineer’s opinion, the testing results are suspect.

b. Readiness Test: Prior to commencing joint testing in each section of sewer main piping, perform a readiness test in the presence of the Engineer. Position the air testing packer on a section of sound sewer pipe between pipe joints and perform a test as specified.

i. The purpose of the test is to check that the piping is properly cleaned for air testing and the air testing equipment system is operating in accordance with the requirements of the Specifications.

ii. If this test cannot be performed successfully, the Contractor shall remove the air testing packer from the sewer section and repair or otherwise modify his equipment and repeat the test until the results are satisfactory to the

Engineer.

2. The air testing packer end elements shall be expanded so as to isolate the joint from the remainder of the line and create a void area between the packer end elements and the pipe joint. The ends of the testing device shall be expanded against the pipe with sufficient inflation pressure to contain the air within the void without leakage past the expanded ends.

3. Contractor shall then introduce pressurized air into the isolated void created by the testing device. Pressure shall be applied until it is determined that the pressure cannot be built in the void or four (4) psi as recorded by the void pressure monitor.

When either of these conditions is reached, Contractor shall shut off the air supply.

4. If the required pressure cannot be developed, joint shall have failed the test. If the required test pressure in the void was increased to four (4) psi, rate of decay of this pressure shall not exceed one (1) psi in 15 seconds. The joint being tested will also have failed if the pressure drops more than one (1) psi in 15 seconds. The line shall then be repaired prior to the retest.

5. Test Records:

a. During joint acceptance testing, records shall be kept by the Contractor which include identification of the sewer section tested, test pressure used, location

(footage) of each joint tested, a statement indicating test results (passed or failed) for each joint tested, test pressure achieved and maintained for each joint passing air test, weekly equipment pressure test results, sewer section barrel test results, and air temperature at time of testing joints.

F. Construction Testing – Lateral Connections:

1. To determine if a lateral connection passes the air test, the packer and sealing bladder shall be inflated to isolate the area around the connection and the first joint of the lateral pipe.

2. Contractor shall then introduce an air pressure of four (4) psi into the isolated void and shut off the air supply. Contractor shall then measure and record the length of time for the pressure to drop from four (4) psi to three (3) psi.

3. The joint test for the lateral would consider to be passed if the time delay for the pressure drop exceeds 15 seconds.

G. Time for Making Test:

1. Engineer shall be present during the operating of valves required to fill mains for leakage test.

2. Contractor shall advise Engineer of any test at least 48 hours in advance. No testing will be authorized unless ambient air temperature is 35◦ F or higher.

3. All tests shall be witnessed by Engineer.

4. Contractor shall furnish laboratory calibrated test gauges and measuring devices for the leakage test.

H. Acceptance: Observation of successful testing of this Section by the Engineer does not constitute acceptance of the system or any portion thereof. Upon completion of any determined portion of a total system, and successful testing thereof, the Engineer may recommend final acceptance to the Owner. Only upon final inspection by the Owner or Engineer, and upon written acceptance for same, will the system or portion thereof be considered substantially completed. Upon such acceptance, the warranty period as specified for the manholes and sewers will commence.

1. If, during this final inspection, any irregularities are observed, the condition must be corrected at the Contractor's expense prior to acceptance.

END OF SECTION

1. Packer: Open end, cylindrical casing of a size less than the pipe diameter, remote controlled for forward and backward movement within the sewer mains:
1. Air-inflatable sleeves (or diaphragms) mounted at each end of the casing exterior with the ends of sleeves fastened to the casing. Devices that have sleeves which may require extreme pressures to “seat” against the inside periphery of the sewer mai...
2. Regulate expansion of air-inflatable sleeves by precise pressure gauges and controls. Under no conditions will hydraulically or mechanically expanded devices be allowed.
3. Pass conduits leading from the surface though one end of the packer casing adapted to supply air, under pressure, to the space at the center of the casing.
2. Compressed Air System: Compressed air system shall include compressed air source, piping, valves and pressure gauges to control the rate of air flow to the packer sleeves and test section:
1. To prevent loading the test section with the full pressure of the compressor, the test equipment shall be provided with an approved pressure regulating device.
2. Pressure gauges shall be calibrated to 0.1 psi.
3. Test Monitoring Equipment: Provide test monitoring equipment to transmit the value of the void air pressure to a remote test pressure monitoring gauge or readout:
1. To determine if a lateral connection passes the air test, the packer and sealing bladder shall be inflated to isolate the area around the connection and the first joint of the lateral pipe.
2. Contractor shall then introduce an air pressure of four (4) psi into the isolated void and shut off the air supply. Contractor shall then measure and record the length of time for the pressure to drop from four (4) psi to three (3) psi.
3. The joint test for the lateral would consider to be passed if the time delay for the pressure drop exceeds 15 seconds.
G. Time for Making Test: