00 43 13 Bid Bond Damages Form.pdf

PDF 126 KB Posted

Attached to
2027 Sewer System Improvements Project
Solicitation number
Not on record
Issued by
Dauphin County, Harveys Lake Borough, Pennsylvania

About this file

This is a Bid Bond (Damages Form) document for the 2027 Sewer System Improvements Project, Contract No. 2026-12, issued by Capital Region Water in Harrisburg, Pennsylvania. The bid bond establishes the financial guarantee required from bidders submitting sealed bids for general construction services related to sewer system improvements at Capital Region Water's facilities located at 3003 N. Front Street, Harrisburg, PA 17110. Sealed bids were to be received online through the PennBid Procurement Portal until October 27, 2026, at 10:00 a.m. EST, at which time bids would be opened. The contract is awarded on a unit price basis to the overall lowest responsible bidder as determined by Capital Region Water's Board of Directors. The work encompasses sewer main replacement and installation, service line replacement, surface restoration, and all other work identified in the contract documents, including all materials, equipment, labor, and miscellaneous items as contemplated by the specifications.

The bid bond form establishes the financial obligations and conditions binding both the bidder and surety. In the event of bidder default, the surety is jointly and severally liable for the difference between the bidder's bid amount and the next lowest responsible bid, or the full bond amount if no alternative bidder exists, whichever is less. Default occurs if the bidder fails to deliver the executed agreement and required performance and payment bonds within the time specified in the bidding documents. The bond obligation becomes null and void if the owner accepts the bid and the bidder delivers all required documents timely, if all bids are rejected, or if the owner fails to issue a Notice of Award within the specified timeframe. Payment under the bond is due within 30 calendar days of written default notice, and any legal action must commence no earlier than 30 days and no later than one year after the bid due date. Capital Region Water has adopted a Minority Women and Disadvantaged Business Enterprise Plan to ensure equal opportunity for participation in project-related construction contracts.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 41 26-B - City of Harrisburg Notice of Construction Cover Sheet.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

00 43 13 Bid Bond Damages Form

BID BOND (DAMAGES FORM)

Bidder Surety

Name: Name:

Address (principal place of business): Address (principal place of business):

Owner Bid

Name: Capital Region Water Project (name and location):

Address (principal place of business): 2027 Sewer System Improvements Project

Contract No. 2026-12: General

Construction

City of Harrisburg, PA

3003 N. Front Street

Harrisburg, PA 17110

Bid Due

Date:

Bond

Bond

Amount:

Date of Bond:

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth in this Bid

Bond, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

Bidder Surety

(Full formal name of Bidder) (Full formal name of Surety) (corporate seal)

By: By:

(Signature) (Signature) (Attach Power of

Attorney) Name: Name:

(Printed or typed) (Printed or typed)

Title: Title:

Attest

Attest:

(Signature) (Signature)

Name: Name:

(Printed or typed) (Printed or typed)

Title:

Title:

Notes: (1) Note: Addresses are to be used for giving any required notice. (2) Provide execution by any additional parties, such as joint venturers, if necessary.

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder any difference between the total amount of Bidder’s Bid and the total amount of the Bid of the next lowest, responsible Bidder that submitted a responsive Bid, as determined by Owner, for the work required by the Contract

Documents, provided that:

A. If there is no such next Bidder, and Owner does not abandon the Project, then Bidder and

Surety shall pay to Owner the bond amount set forth on the face of this Bond, and

B. In no event will Bidder’s and Surety’s obligation hereunder exceed the bond amount set forth on the face of this Bond.

C. Recovery under the terms of this Bond will be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder occurs upon the failure of Bidder to deliver within the time required by the

Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed

Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation will be null and void if:

A. Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding

Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the

Bidding Documents, or

B. All Bids are rejected by Owner, or

C. Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding

Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by Paragraph 5 hereof).

4. Payment under this Bond will be due and payable upon default of Bidder and within 30 calendar days after receipt by Bidder and Surety of written notice of default from Owner, which notice will be given with reasonable promptness, identifying this Bond and the Project and including a statement of the amount due.

5. Surety waives notice of any and all defenses based on or arising out of any time extension to issue Notice of Award agreed to in writing by Owner and Bidder, provided that the total time for issuing Notice of Award including extensions will not in the aggregate exceed 120 days from Bid due date without Surety’s written consent.

6. No suit or action will be commenced under this Bond prior to 30 calendar days after the notice of default required in Paragraph 4 above is received by Bidder and Surety, and in no case later than one year after the Bid due date.

7. Any suit or action under this Bond must be commenced only in a court of competent jurisdiction located in the state in which the Project is located.

8. Notices required hereunder must be in writing and sent to Bidder and Surety at their respective addresses shown on the face of this Bond. Such notices may be sent by personal delivery, commercial courier, or by United States Postal Service registered or certified mail, return receipt requested, postage pre-paid, and will be deemed to be effective upon receipt by the party concerned.

9. Surety shall cause to be attached to this Bond a current and effective Power of Attorney evidencing the authority of the officer, agent, or representative who executed this Bond on behalf of Surety to execute, seal, and deliver such Bond and bind the Surety thereby.

10. This Bond is intended to conform to all applicable statutory requirements. Any applicable requirement of any applicable statute that has been omitted from this Bond will be deemed to be included herein as if set forth at length. If any provision of this Bond conflicts with any applicable statute, then the provision of said statute governs and the remainder of this Bond that is not in conflict therewith continues in full force and effect.

11. The term “Bid” as used herein includes a Bid, offer, or proposal as applicable.

File details come from the government source that posted it. Updated .