About this file

This is a specification document for product warranties issued by Capital Region Water (CRW) in Pennsylvania for the 2027 Sewer System Improvements Project. The warranty section establishes comprehensive requirements for product warranties, manufacturer warranties, and special warranties that contractors must provide to the Owner. Contractors must submit warranty documentation to the Owner and Engineer within 10 days following the Date of Substantial Completion or Partial Utilization, and for items accepted after Substantial Completion, within 10 days following each individual acceptance. Warranty documents must be submitted electronically and prepared in a format ready for execution by required parties, including manufacturers, subcontractors, and suppliers as applicable. Warranties become valid and operative upon issuance of the Certificate of Substantial Completion.

The specification requires that written warranties made to the Owner are in addition to implied warranties and do not limit duties, obligations, rights, and remedies otherwise available under law. Manufacturer disclaimers and limitations do not relieve the Contractor of warranty obligations on work incorporating those products, nor do they relieve suppliers, manufacturers, and subcontractors required to countersign special warranties. When warranted work fails, the Contractor must correct defects through replacement or rebuilding at no additional cost to the Owner, including removal and replacement of other work damaged as a result of the failure or requiring removal for access. The Contractor is responsible for replacement costs regardless of whether the Owner has benefited from use of the work through a portion of its anticipated useful service life. Upon correction of failed work, the Contractor must reinstate the warranty by written endorsement, with the reinstated warranty equitable to the original warranty adjusted for depreciation.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 41 26-B - City of Harrisburg Notice of Construction Cover Sheet.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 78 36 – Warranties

1.0 General

1.1 Summary

A. Section Includes:

1. Product warranty manuals.

2. Warranty requirements.

B. Related Sections:

1. Section 01 77 00 – Closeout Procedures: General closeout procedures.

2. Individual Sections for specific requirements for Project Record Documents of the

Work in those Sections.

1.2 Product Warranties

A. Warranties specified in individual Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaimers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents. Warranties shall be written in Owner’s name:

1. Standard Product Warranties are preprinted written warranties published by individual manufacturers for particular products and are specifically endorsed by the manufacturer to Owner.

2. Special Warranties are written warranties required by or incorporated into Contract

Documents, either to extend time limits provided by standard warranties or to provide greater rights for Owner.

B. Submission requirements:

1. The Contractor shall submit documents to Owner and Engineer within 10 days following Date of Substantial Completion or Partial Utilization. For items accepted after Date of Substantial Completion, submit documents within 10 days following each individual acceptance:

a. When special warranty is required to be executed by Contractor, or Contractor and a subcontractor, supplier, or manufacturer, prepare a written document that contains appropriate terms and identification, ready for execution by required parties. Submit a draft to Owner.

2. The Contractor shall submit information electronically to Owner and Engineer.

1.3 Warranty Requirements

A. Written warranties made to Owner are in addition to implied warranties and shall not limit duties, obligations, right and remedies otherwise available under law, nor shall warranty periods be interpreted as limitations on time in which Owner can enforce such other duties, obligations, rights, or remedies.

01 78 36 – Warranties

B. Manufacturer's disclaimers and limitations on product warranties shall not relieve

Contractor of warranty on Work that incorporates products, nor shall it relieve suppliers, manufacturers, and Subcontractors required to countersign special warranties with Contractor.

C. Special Warranties: The Contractor shall prepare a written document that contains appropriate terms and identification, ready for execution. Submit a draft for approval before final execution:

1. Manufacturer's Standard Form: Modified to include Project-specific information and properly executed.

2. Specified Form: When specified forms are included with the Specifications, prepare a written document using appropriate form properly executed.

3. Refer to Sections for specific content requirements and particular requirements for submitting Special Warranties.

D. Warranties shall become valid and operative upon issuance of Certificate of Substantial

Completion.

E. For items of Work delayed beyond Date of Substantial Completion, the Contractor shall provide an updated schedule within 10 days after acceptance, listing date of acceptance as start of warranty.

F. Related Damages and Losses: When correcting warranted Work that has failed, the

Contractor shall remove, and replace other Work that has been damaged as a result of such failure or that needs to be removed and replaced to provide access for correction of warranted Work, at no additional cost to the Owner.

G. Reinstatement of Warranty: In event of Work covered by warranty has failed, the

Contractor shall correct by replacement or rebuilding. Reinstate warranty by written endorsement. Reinstated warranty shall be equal to original warranty with an equitable adjustment for depreciation.

H. Replacement Cost:

1. Upon determining that Work covered by a warranty has failed, the Contractor shall replace or rebuild Work to an acceptable condition in compliance with requirements of Contract Documents.

2. Contractor shall be responsible for cost of replacing or rebuilding defective Work regardless of whether Owner has benefited from use of Work through a portion of its anticipated useful service life.

2.0 Products - Not Used.

3.0 Execution - Not Used.

END OF SECTION