01 29 00 - Payment Procedures.pdf

PDF 102 KB Posted

Attached to
2027 Sewer System Improvements Project
Solicitation number
Not on record
Issued by
Dauphin County, Harveys Lake Borough, Pennsylvania

About this file

This is a payment procedures document related to Capital Region Water's (CRW) 2027 Sewer System Improvements Project, a general construction contract in Pennsylvania. The project encompasses sewer system improvements including material, equipment, labor, and associated work as detailed in contract documents. Bids will be received via the online PennBid Bonfire Program until October 27, 2026, at 10:00 a.m. EST, at which time bids will be opened online. All bid documents are available at no cost through the PennBid Bonfire Hub website at https://pennbid.bonfirehub.com/portal. Bids shall be submitted on a unit price basis. CRW intends to award the contract to the overall lowest responsible bidder as determined by CRW's Board of Directors in the best interest of the organization. No mandatory pre-bid meeting is specified in the available documentation, though interested parties may request site visits or further information through the PennBid platform.

CRW has adopted a Minority Women and Disadvantaged Business Enterprise Plan to ensure equal opportunity for minority, women, and disadvantaged business enterprises in the award and administration of contracts. Bidders are required to submit MWDBE documentation in compliance with contract requirements. The procurement allows bidders to utilize existing Commonwealth of Pennsylvania contracts and other competitively sourced cooperative purchasing agreements. Performance bonds, payment bonds, and anti-collusion affidavits may be required in accordance with specific contract documents. No incumbent vendor information or specific budget range is disclosed in the solicitation materials. Assistance is available through PennBid Representatives at 610-693-4769.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
01 41 26-B - City of Harrisburg Notice of Construction Cover Sheet.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 29 00 – PAYMENT PROCEDURES

1.0 General

1.1 SECTION INCLUDES

A. Scope of Payment.

B. Schedule of Values.

C. Application for Payment.

D. Defect Assessment.

1.2 SCOPE OF PAYMENT

A. Contractor will receive and accept compensation provided for in the Contract as full payment for furnishing all materials, labor, tools, and equipment and for performing all Work in a complete and acceptable manner and for all risk, loss, damage, or expense of whatever character arising out of the nature of the Work or the prosecution thereof.

B. Contractor shall furnish all labor, materials, equipment, machinery, apparatus, and tools and perform all operations necessary to install, equip, adjust, and put into satisfactory operation the Work, and shall connect the various items or sections of the Work as to form a complete and properly operating whole. Any miscellaneous labor, materials, equipment, or apparatus not specifically mentioned herein, or shown on the drawings, which may be found necessary to complete or perfect any portion of the Work in a substantial manner and in compliance with the requirements stated or implied by the Contract Documents, shall be furnished by the Contractor without additional compensation. This includes the cost of material disposal, water for testing and all testing costs including laboratory fees.

1.3 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of

Contractor's Construction Schedule.

B. Submit printed or electronic file of schedule on Application for Payment Continuation

Sheets.

C. Submit Schedule of Values as electronic file within 10 days after date established in

Notice to Proceed.

D. Format:

1. Provide a Provide a breakdown of the Contract Price in enough detail to facilitate continued evaluation of Applications for Payment and progress reports.

2. Use Table of Contents of this Project Manual. Identify each line item with number and title of major Specification Section. Provide several line items for principal subcontract amounts, where appropriate.

3. Identify site mobilization and project management costs.

4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

E. Include in each line-item amount of allowances as specified. For unit cost allowances, identify quantities taken from Contract Documents multiplied by unit cost to achieve total for each item.

F. Include within each line item, direct proportional amount of Contractor's overhead and profit:

1. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of

Values or distributed as general overhead expense, at Contractor's option.

G. Revise schedule to list approved Change Orders with each Application for Payment.

1.4 APPLICATION FOR PAYMENT

A. Submit one (1) electronic copy of each Application for Payment on form(s) provided in Section 00 62 76 in accordance with requirements of the General Conditions:

1. Initial Application for Payment, Application for Payment at time of Substantial

Completion, and final Application for Payment involve additional requirements.

B. Content and Format: Use Schedule of Values for listing items in Application for

Payment:

1. Execute by a person authorized to sign legal documents on behalf of Contractor.

Engineer will return incomplete applications without action.

2. Include amounts of Change Orders issued before last day of construction period covered by application.

C. Submit copy of updated record drawing set.

D. Submit certified payrolls for Contractor and all sub-contractors through work period reflected on Application for Payment.

E. Submit updated construction schedule with each Application for Payment.

F. Payment Period: Submit at intervals stipulated in the Agreement.

G. Submit executed originals with transmittal letter to Engineer by method ensuring receipt within 24 hours.

H. Substantiating Data: When Engineer requires substantiating information, submit data justifying dollar amounts in question.

I. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Contractor’s Construction Schedule (preliminary if not final).

3. Products list.

4. Submittals Schedule (preliminary if not final).

5. Certificates of insurance and insurance policies.

J. Application for Payment at Substantial Completion: After issuance of the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete less the amounts certified by the Engineer as remaining:

1. Application for Payment at Substantial Completion: After issuance of the

Certificate of Substantial Completion, submit an Application for Payment showing

100 percent completion for portion of the Work claimed as substantially complete less the amounts certified by the Engineer as remaining:

a. Final Operation and Maintenance Manuals, as applicable.

b. Final test and field reports.

c. Draft Project Record Documents.

K. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following. Final Application will be prepared by the Engineer following completion of the final inspection per Section 01 77 00 – Closeout Procedures:

1. Evidence of completion of Project closeout requirements.

2. Final Project Record Documents.

3. Insurance certificates for products and completed operations and proof that taxes, fees, and similar obligations were paid.

4. Contractor's Affidavit: Submit on form provided by Engineer.

5. Consent of Surety to Final Payment: Submit on form provided by Engineer.

1.5 Defect Assessment

A. Replace the Work, or portions of the Work, not conforming to specified requirements.

B. If, in the opinion of Engineer it is not practical to remove and replace the Work, Engineer will direct appropriate remedy or adjust payment.

C. The defective Work may remain, but unit sum/price will be adjusted to new sum/price at discretion of Engineer and/or Owner.

D. Defective Work will be partially repaired according to instructions of Engineer and/or

Owner and unit sum/price will be adjusted to new price at discretion of Engineer and/or Owner.

E. Individual Specification Sections may modify these options or may identify specific formula or percentage sum/price reduction.

F. Authority of Engineer and/or Owner to assess defects and identify payment adjustments is final.

G. Nonpayment for Rejected Products: Payment will not be made for rejected products for any of the following reasons:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from transporting vehicle.

4. Products placed beyond lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected products.

2.0 Products - Not Used.

3.0 Execution – Not Used

END OF SECTION

a. Final Operation and Maintenance Manuals, as applicable.
b. Final test and field reports.
c. Draft Project Record Documents.