01 32 16 - Construction Progress Schedule.pdf

PDF 104 KB Posted

Attached to
2027 Sewer System Improvements Project
Solicitation number
Not on record
Issued by
Dauphin County, Harveys Lake Borough, Pennsylvania

About this file

Construction Progress Schedule Specification Summary

This document is a technical specification section (01 32 16) for construction progress schedule requirements applicable to the 2027 Sewer System Improvements Project under Capital Region Water (CRW), a Pennsylvania water utility. The specification establishes mandatory requirements for the General Contractor to prepare, submit, and maintain a construction progress schedule using Microsoft Project software in Gantt chart format. The contractor must submit a preliminary schedule within seven days of contract award and revise it monthly or whenever actual schedule variance exceeds seven days from the proposed schedule. A weekly look-ahead schedule must be provided by noon every Wednesday throughout construction, identifying expected activities for the upcoming week. The schedule must identify all work items sequenced according to the project manual's table of contents, display accumulated completion percentages, show the critical path with original baseline, include a separate identifiable activity for foreseeable bad weather days allowance, and provide a submittal schedule showing shop drawing dates and engineer review requirements. The document requires distribution of computer-generated schedules to the engineer, owner, other contractors, subcontractors, and suppliers, with recipients instructed to promptly report anticipated problems in writing. The contractor must coordinate the work schedule with local business owners.

The specification mandates compliance with AGC's "Construction Planning & Scheduling" standards and requires the contractor to determine the appropriate number of weather delay days based on normal anticipated weather for the project location and work nature, subject to minimum requirements in the contract's General Conditions or Supplementary Conditions. Weather delays, when justified, are considered allowable but non-compensable costs. Revised schedules must be submitted with each application for payment and must include narrative reports defining problem areas, anticipated delays, schedule impacts, and corrective actions proposed or implemented. The schedule serves multiple purposes including communicating the contractor's execution plan, identifying critical work paths, evaluating mitigation strategies for unforeseen events, analyzing time impacts of changes, documenting actual progress, and facilitating timely project completion.

View the file

Other files

File Type Posted
00 41 20 Qualifications Statement (CRW).pdf PDF
00 00 00 Cover.pdf PDF
33 01 30 Operation and Maintenance of Sewer Utilities.pdf PDF
00 43 13 Bid Bond Damages Form.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
00 55 00 Notice to Proceed.pdf PDF
00 21 13 Instructions to Bidders.pdf PDF
00 61 19 - Warranty Bond.pdf PDF
01 41 26-C - Chlorinated Water Discharge - Incident Report Cover Sheet & Form.pdf PDF
00 73 53 - Anti-Pollution Measures.pdf PDF
01 10 00 - Summary.pdf PDF
00 63 36 - Field Order Form.pdf PDF
00 51 00 Notice of Award.pdf PDF
31 23 19 Dewatering.pdf PDF
01 22 00 - Unit Prices.pdf PDF
00 52 00 Agreement.pdf PDF
03 11 00 Concrete Forming.pdf PDF
00 45 36 EEO Certificate.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
33 05 05.31 - Hydrostatic Testing.pdf PDF
33 13 00 - Disinfection of Water Utility Distribution.pdf PDF
2026.09.29 Contract Drawings for Upload to PennBid.pdf PDF
01 25 00 - Substitution Procedures.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 73 46 - Wage Determination Schedule Cover.pdf PDF
01 31 19 - Project Meetings.pdf PDF
00 01 10 Table of Contents.pdf PDF
33 05 53 - Identification For Utilities Piping and Equipment.pdf PDF
01 35 15 - Notifications and Other Coordination.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
03 30 00 Cast-in-Place Concrete.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 31 13 - Project Coordination.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
32 13 13 - Concrete Paving.pdf PDF
00 21 13-1 Owner Minority, Women and Other DBE Forms.pdf PDF
01 77 00 - Closeout Procedures.pdf PDF
01 41 26-A - City of Harrisburg Street Closure Request Form.pdf PDF
33 14 17 - Site Water Service Utility Laterals.pdf PDF
00 65 16 Certificate of Substantial Completion.pdf PDF
03 60 00 Grouting.pdf PDF
00 45 33 Certification of Non-Segregated Facilities and Non-Employment of Illegal Alien Labor.pdf PDF
33 05 05.41 - Air Testing.pdf PDF
00 31 43 Permit Applications.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
01 78 36 - Warranties.pdf PDF
33 01 31 TV Inspection of Sewer Pipelines.pdf PDF
00 72 00 - General Conditions 2013.pdf PDF
33 14 13 - Public Water Utility Distribution Piping.pdf PDF
Show 40 more

Latest 50 of 116 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 32 16 – Construction Progress Schedule

1.0 General

1.1. Section Includes

A. This Section includes administrative and procedural requirements for the preparation, submittal, and maintenance of the progress schedule, reporting progress of the Work, and Contract Time adjustments, including the following:

1. Format.

2. Content.

3. Revisions to schedules.

4. Submittals.

5. Distribution.

B. Refer to the General Conditions and the Agreement for definitions and specific dates of Contract Time.

C. The above listed Project schedules shall be used for evaluating all issues related to time for this Contract. The Project schedules shall be updated in accordance with the requirements of this Section to reflect the actual progress of the Work and the

Contractor’s current plan for the timely completion of the Work. The Project schedules shall be used by the Owner and Contractor for the following purposes as well as any other purpose where the issue of time is relevant:

1. To communicate to the Owner the Contractor’s current plan for carrying out the

Work.

2. To identify work paths that is critical to the timely completion of the Work.

3. To identify upcoming activities on the Critical Path(s).

4. To evaluate the best course of action for mitigating the impact of unforeseen events.

5. As the basis for analyzing the time impact of changes in the Work.

6. As a reference in determining the cost associated with increases or decreases in the Work.

7. To identify when submittals will be submitted.

8. To prioritize the review of submittals.

9. To document the actual progress of the Work.

10. To evaluate resource requirements of the Contractor and the Owner.

11. To integrate the Work with the operational requirements of the Owner’s facilities.

12. To facilitate efforts to complete the Work in a timely manner.

13. To document the history of the Work.

1.2. Related Sections

A. Section 01 10 00 – Summary.

B. Section 01 22 00 – Unit Prices.

C. Section 01 33 00 – Submittal Procedures.

D. Section 01 40 00 – Quality Requirements.

1.3. Definitions

A. Construction Schedule: A method of planning and scheduling a construction project utilizing a horizontal bar chart with a separate bar for each major portion of the Work or operation to make the schedule an effective tool for planning and monitoring the progress of the work.

B. Critical Path: The longest continuous chain of activities through the network at a given data date for the Schedule to a Contract Milestone or Contract Completion. Where the path to a specific Milestone has become negative, the Critical Path shall be the longest continuous chain of activities with the greatest amount of negative float.

C. Activity: A discrete part of a project that can be identified for planning, scheduling, monitoring, and controlling the construction project. Activities included in a construction schedule consume time and resources:

1. Critical activities are activities on the critical path.

2. Predecessor activity is an activity that must be completed before a given activity can be started.

D. Event: An event is the starting or ending point of an activity.

E. Milestone: A key or critical point in time for reference or measurement.

F. Weekly Look-Ahead Schedule: The Contractor shall provide a weekly look-ahead schedule by or before noon every Wednesday, throughout the duration of

Construction. This schedule shall be emailed to the Owner and Engineer. The

Contractor will prepare this schedule, and it will provide an indication of expected activities for the upcoming week.

1.4. Quality Assurance

A. Scheduling Software:

1. The Contractor shall use the latest version of Microsoft Project as the scheduling software system for use on this Project.

2. Standards: Comply with procedures contained in AGC's "Construction Planning &

Scheduling."

1.5. Preliminary Schedule

A. Preliminary Gantt schedule is to be prepared by the General Contractor and submitted to the Engineer within seven days of award of contract. This schedule is to cover all items of Work from the start of the Project up to the completion of the Project. This schedule must be revised when the actual schedule of significant items varies more than one week from the proposed schedule.

1.6. Construction Schedule Format

A. Format: Utilize a horizontal bar chart (Gantt) with a separate bar for each major portion of the Work or operation, identifying first workday of each week.

B. Program: Use Microsoft Project, latest version.

C. Sequence of Listings: Utilize the Table of Contents of this Project Manual and the chronological order of the start of each item of work.

D. Scale and Spacing: Provide space for notations and revisions.

E. Sheet Size: To be coordinated with Construction Administrator.

F. Foreseeable Bad Weather Days Allowance: The Contractor shall include a separate identifiable activity on the Critical Path labeled "Foreseeable Bad Weather Days:"

1. The Contractor shall be fully responsible for determining the number of weather delay days to be included in the Schedule. This determination shall be based on the normal anticipated weather for the project location and the nature of the project work. The Schedule shall be based on the Contractor’s determined weather delay allowance but must meet the minimum shown in the General Conditions or

Supplementary Conditions.

2. The Contractor shall insert an activity in the Schedule to reflect weather day occurrences when weather days are experienced. Identify this activity as a foreseeable weather delay.

3. The Contractor shall reduce duration of Foreseeable Bad Weather Days Allowance activity as weather delays are experienced and inserted into the Schedule.

Remaining days in Foreseeable Bad Weather Day Allowance at completion of the

Project is considered float. Weather delays, when justified, are considered allowable, non-compensable.

1.7. Content

A. Show complete sequence of construction by activity, with dates beginning and completion of each element of construction.

B. Identify each item by specification section numbers.

C. Identify Work of separate phases and other logically grouped activities.

D. Show accumulated percentages of completion of each item, and total percentage of

Work completed, as of the first day of each month.

E. Provide separate schedule of submittal dates for shop drawings, product data, and dates reviewed submittals will be required from Engineer. Indicate decision dates for selection of finishes.

F. Indicate critical path with original baseline indicated.

1.8. Submittals and Revisions to Schedules

A. An initial bar graph schedule is to be prepared by the General Contractor and submitted.

B. Indicate progress of each activity to date of submittal, and projected completion date of each activity.

C. Identify activities modified since previous submittal, major changes in scope, and other identifiable changes.

D. Provide narrative report to define problem areas, anticipated delays, and impact on

Schedule. Report corrective action taken, or proposed, and its effect.

E. Schedules must be revised monthly and when the actual schedule of significant items varies more than seven days from the proposed schedule.

F. Submit revised Construction Schedules for each Application for Payment.

G. Submit an electronic copy of the Construction Schedule.

1.9. Distribution

A. Distribute copies of the computer-generated schedules to Engineer, Owner, other

Contractors, Subcontractors, suppliers, and other concerned parties.

B. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in schedules.

C. Contractor shall coordinate Work Schedule with local business owners.

2.0 Products – Not Used.

3.0 Execution – Not Used.

END OF SECTION