01 26 00 - Contract Modifications.pdf
PDF 90 KB Posted
- Attached to
- 2027 Sewer System Improvements Project
- Solicitation number
- Not on record
- Issued by
- Dauphin County, Harveys Lake Borough, Pennsylvania
About this file
This file is a contract modification procedures document that establishes the processes for handling changes to work, requests for interpretation, and change orders for construction projects undertaken by Capital Region Water in Pennsylvania. The procedures outline the responsibilities of the contractor to carefully review contract documents and promptly notify the engineer of any errors, inconsistencies, or discrepancies. The document distinguishes between minor changes issued by the engineer through field orders and more significant modifications requiring formal proposal requests and change orders. For owner-initiated proposal requests, contractors must submit cost estimates within 10 business days that include quantities, unit costs, applicable taxes, delivery charges, equipment rental, labor costs, and updated construction schedules reflecting the impact of proposed changes. Contractors may also propose changes independently by submitting detailed change proposals to the engineer that document the reason for modification and its effects on contract price and time.
Change orders are executed only upon owner approval of proposal requests and must be processed through the formal Change Order Form procedure. Contractors are required to promptly revise their Schedule of Values, Applications for Payment, and Progress Schedules to reflect authorized changes as separate line items and adjust contract pricing and timelines accordingly. All changes must be entered into record documents to maintain accurate project documentation. The procedures establish clear communication protocols requiring contractors to designate an authorized individual responsible for receiving change documents and disseminating information to subcontractors, with liaison time allocated in construction schedules for queries and clarifications with the engineer.
View the file
Other files
Show 40 more
Latest 50 of 116 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 26 00 - Contract
Modification Procedures
1.0 General
1.1 Summary
A. Section Includes:
1. Change procedures.
B. Related Sections:
1. Document 00 60 00 – Project Forms.
2. Document 00 63 13 – RFI Form.
3. Document 00 63 63 – Change Order Form.
4. Section 01 26 13 – Requests for Interpretation.
1.2 Change Procedures
A. Submittals: Submit name of individual who is authorized to receive change documents and is responsible for informing others in Contractor's employ or
Subcontractors of changes to the Work.
B. Carefully study and compare Contract Documents before proceeding with fabrication and installation of Work. Promptly advise Engineer of any error, inconsistency, omission, or apparent discrepancy.
C. Requests for Interpretation (RFI) and Clarifications: Allot time in construction scheduling for liaison with Engineer; establish procedures for handling queries and clarifications:
1. Refer to Section 01 26 13 – Requests for Interpretation.
2. Engineer may respond with a direct answer on the Request for Interpretation form, Field Order, or Proposal Request.
1.3 Minor Changes in the Work
A. Engineer will advise of minor changes in the Work not involving adjustment to
Contract Price or Contract Time by issuing supplemental instructions on a Field
Order.
1.4 Proposal Requests
A. Owner-Initiated Proposal Requests: Engineer may issue Proposal Request including a detailed description of proposed change with supplementary or revised Drawings and
Specifications:
1. Proposal Requests issued by Engineer are not instructions either to stop work in progress or to execute the proposed change.
2. Contractor will prepare and submit estimate within 10 business days:
a. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and equipment directly attributable to the change.
d. Include an updated Construction Schedule that indicates the effect of the change.
B. Contractor may propose changes by submitting a Change Proposal to Engineer, describing proposed change and its full effect on the Work. Include a statement describing reason for the change and the effect on Contract Price and Contract Time with full documentation:
1. Notice: Comply with General Conditions where latent or changed conditions require modifications to the Contract.
2. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and equipment directly attributable to the change.
5. Include an updated Construction Schedule that indicates the effect of the change.
C. Document requested substitutions according to Section 01 25 00 - Substitution
Procedures.
1.5 Change Order Procedures
A. On Owner's approval of a Proposal Request, Engineer will issue a Change Order for execution by Owner and Contractor:
1. Change Order Forms: Document 00 63 63 – Change Order Form.
B. Stipulated Price Change Order: Based on Proposal Request and Contractor's price quotation or Contractor's request for Change Order as approved by Engineer.
C. Unit Price Change Order: For Contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis.
D. Correlation of Contractor Submittals:
1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as separate line item and adjust Contract Price.
2. Promptly revise Progress Schedules to reflect change in Contract Time, adjust times for other items of Work affected by the change, and resubmit.
3. Promptly enter changes in Record Documents.
1.6 Work Change Directive
A. Not Used.
2.0 Products – Not Used.
3.0 Execution – Not Used.
END OF SECTION