AF FORM 66.xls
XLS spreadsheet 42 KB Posted
- Attached to
- Natural Gas System Repair Federal contract opportunity
- Solicitation number
- FA4427-08-R-0105
About this file
Air Force Form 66 Submittal
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| pd254D.doc | DOC document | |
| Fill in documents.doc | DOC document | |
| pd254D.doc | DOC document | |
| Solicitation.rtf | RTF text file | |
| Travis AFB Entry Procedures.doc | DOC document | |
| LIST OF TASKS 3-11-08.doc | DOC document | |
| Atch 6 - Past Performance Survey and Reference Letterdemo.doc | DOC document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
A
| PROJECT NUMBER | PROJECT TITLE | SOLICITATION/CONTRACT NUMBER | |||||||||||||||||||
| SCHEDULE OF MATERIAL SUBMITTALS | NATURAL GAS SYSTEM REPAIR | FA4427-08-R-0105 | |||||||||||||||||||
| TO BE COMPLETED BY PROJECT ENGINEER | TO BE COMPLETED BY CONTRACT ADMINISTRATOR | ||||||||||||||||||||
| NUMBER OF COPIES REQUIRED | |||||||||||||||||||||
| LINE NUMBER | ITEM OR DESCRIPTION OF ITEM, CONTRACT REFERENCE, TYPE OF SUBMITTAL | CERTIFICATION OF COMPLIANCE | SHOP DRAWINGS | SAMPLES | COLOR SELECTION | MANUFACTURE'S RECOMMENDATIONS | MANUFACTURER'S WARRANTY | CATALOG DATA | OPERATING INSTRUCTIONS | TESTS | REPORTS | REQUIRED SUBMISSION DATE | DATE RECEIVED IN CONTRACTING | DATE TO CIVIL ENGINEERING | RETURN SUSPENSE DATE | FOLLOW-UP | DATE CONTRACTOR NOTIFIED | CONTRACTOR RESUBMITTAL | FINAL APPROVAL | REMARKS | |
| APPROVED | DISAPPROVED | ||||||||||||||||||||
| 1 | Section 01572, Para 1.2 Waste Management Plan | 3 | 15D | Due 15 days after contract award | |||||||||||||||||
| 2 | Section 02316, Para 3.4 Testing | 3 | 4D | Due 4 days after test | |||||||||||||||||
| 3 | Section 02316, Para 3.4.3 Field Density Tests | 3 | 4D | Due 4 days after test | |||||||||||||||||
| 4 | Section 02556, Para 1.2 SD-02 Drawings | 2 | 2W | Due 2 weeks before istallation | |||||||||||||||||
| 5 | Section 02556, Para 1.2 SD-03 Product Data | 3 | 3 | 2W | Due 2 weeks before istallation | ||||||||||||||||
| 6 | Section 02556, Para 1.2 SD-07 Certificates | 2 | 2W | Due 2 weeks after istallation | |||||||||||||||||
| 7 | Section 02556, Para 1.2 SD-10 Operation and Maintenance Data | 3 | 2W | Due 2 weeks after istallation | |||||||||||||||||
| 8 | Section 02556, Para 3.12 Tests | 3 | 1D | Daily | |||||||||||||||||
| 9 | Section 02722, Para 1.3 SD-03 Product Data | 3 | 2W | Due 2 weeks after istallation | |||||||||||||||||
| 10 | Section 02722, Para 1.3 SD-06 Test Reports | 3 | 30D | Due 30 days before istallation | |||||||||||||||||
| 11 | Section 02744, Para 1.2 SD-03 Product Data | 3 | 1D | Daily | |||||||||||||||||
| 12 | Section 02744, Para 1.2 SD-06 Test Reports | 3 | 1D | Daily | |||||||||||||||||
| 13 | Section 02754, Para 1.2 SD-03 Product Data | 3 | 2W | Due 2 weeks before istallation | |||||||||||||||||
| 14 | Section 02754, Para 1.2 SD-03 Product Data | 3 | 2W | Due 2 weeks before istallation | |||||||||||||||||
| 15 | |||||||||||||||||||||
| 16 | |||||||||||||||||||||
| 17 | |||||||||||||||||||||
| 18 | |||||||||||||||||||||
| 19 | |||||||||||||||||||||
| AF Form 66, OCT 89 | PREVIOUS EDITION WILL BE USED |
&RPage &P
File details come from the government source that posted it. Updated .