This is a Task Assignment (TA) document between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. for well abandonment activities. The task assignment is issued under Contract Number HW684, with Task Assignment Number DC026D, and is effective through March 16, 2026. The project location is Darby's Cleaners, located at 3911 Manatee Ave W, Manatee County, Bradenton, Florida 34205, under FDEP Project Number ERIC_4902. The Department Project Manager is Mackenzie Childs (850-245-8929), and the Contractor's Project Manager is Brian Moore (813-971-3882).
The task assignment authorizes GHD Services, Inc. to conduct well abandonment activities including project management and field work. The scope comprises two subtasks: Subtask 1 involves project management calculated at 13% of direct labor costs, and Subtask 2 involves abandoning monitoring wells MW001 and MW002, along with piezometers PZ001 through PZ007, followed by preparation of a well abandonment summary report. The total task assignment value is $4,562.33 on a fixed unit rate basis. The primary deliverable is the Well Abandonment Report due January 16, 2025, with invoice payment contingent upon FDEP review and approval. Direct labor costs total $1,410.18 with overhead (129.80%), fringe benefits (37.80%), and additional expenses including vehicle rental ($120.00), subcontractor equipment procurement ($121.33), field equipment and expendables ($170.00), and a completion fee of $377.36.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC026D Completion March 16, 2026
This Task Assignment authorizes GHD Services, Inc to conduct well abandonment activities at Darby's Cleaners.
Mackenzie Childs 850-245-8929 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore 813-971-3882
ERIC_4902
3911 Manatee Ave W, Manatee County, Bradenton, FL 34205
Darby's Cleaners
✔ $ 4,562.33
$ 4,562.33
Scope of Work
Brian Moore Digitally signed by Brian Moore Date: 2026.03.05 17:39:06 -05'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2026.03.05 13:05:46 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW684
DC026D
Subtasks 1 & 2: Well Abandonment Report + Project Management 01/16/2025
Subtasks 1 & 2: FDEP review and approval of Well Abandonment Report + Project Management $ 4,562.33
$ 4,562.33
TO: HW684 Contract File
Mackenzie Childs, Project Manager
February 20, 2025
Task Assignment DC026D Darby's Cleaners
ERIC_4902
Well Abandonment
FROM:
DATE:
SUBJECT:
This Task Assignment authorizes GHD Services, Inc., hereby referred to as GHD, to well abandonment activities at Darby's Cleaners in Manatee County, Florida (FL). Specific subtasks are detailed below:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2: Well Abandonment GHD personnel will abandon monitoring wells MW001 and MW002 and piezometers PZ001 through PZ007. Following the completion of the field activities, a brief well abandonment summary report will be prepared.
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 2/20/2026
Task #: DC026D SubTask 1 Project Management SubTask 6
Site: Darby's Cleaners SubTask 2 Well Abandonment SubTask 7
Activity/Phase: Well Abandonment SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$51.76 Project Manager JM 3.13 3.13 $77.28 Principal Engineer/Scient MC 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $58.35 Sr Professional Engineer JH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $45.07 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.28 Project Engineer/Scientis CH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $51.76 Project Manager/ Enginee JM 9.00 9.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.65 Staff Engineer/Scientist JW 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $36.80 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $46.69 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $25.00 Senior Technician SA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.01 Senior Technician WM 7.50 7.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $27.87 Senior Technician DC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $21.02 Junior Technician WO 7.50 7.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.65 Junior Technician CD 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $31.58 Drafting Technician KJ 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.06 Administrative Assistant JJ 3.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 35.13 3.13 32.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,410.18 $162.23 $1,247.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $1,830.41 $210.57 $1,619.84 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $533.05 $61.32 $471.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,773.64 $434.12 $3,339.52 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 2/20/2026
Task #: DC026D SubTask 1 Project Management SubTask 6
Site: Darby's Cleaners SubTask 2 Well Abandonment SubTask 7
Activity/Phase: Well Abandonment SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) Atlantic Supply $110.30 $110.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $110.30 $110.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $11.03 $11.03 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $121.33 $121.33 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $130.00 $130.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $170.00 $170.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $4,184.97 $434.12 $3,750.85 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $377.36 $43.41 $333.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $4,562.33 $477.53 $4,084.80 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $4,562.33 Auto-Calculated
Final Total Cost: $4,562.33 Auto-Calculated
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Darby's Cleaners SUBTASK 2: Well Abandonment
DATE: 2/20/2026
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager JM Field Work Preparation 1 Project Manager JM Well Abandonment Permitting and Completions 2 Project Manager JM Prepare Well Abandonment Summary 6
Princial Engineer MC Well abandonment permitting 4
Senior Technician WM Mob/Demob from Tampa (1 day) 2 Senior Technician WM Abandon Wells (1 hr/well) - 2 wells 2 Senior Technician WM Abandon piezometers (0.5 hr/piezometers) - 7 wells 3.5
7.5
Junior Technician WO Mob/Demob (3 days) 2 Junior Technician WO Well Abandonment (2 wells) 2 Junior Technician WO Abandon piezometers (0.5 hr/piezometers) - 7 wells 3.5
7.5
Drafting Technician KJ Prepare site plan with wells abandoned 1
Staff Assistants JJ Revise tables/upload pictures 1 Staff Assistants JJ Document Preparation/Publishing/pdf 2
TOTAL LABOR 32
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Atlantic Supply Portland Grout $14.20 per 47lb bag 3 $42.60 Atlantic Supply Delivery $60.00 each 1 $60.00 Atlantic Supply Taxes $7.70 each 1 $7.70
TOTAL $110.30
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 1 $40.00
Construction Supplies $75.00 day 1 $75.00 water level indicator $25.00 day 1 $25.00 Peristaltic Pump $30.00 day 1 $30.00
TOTAL EQUIPMENT $170.00
FINAL --7/24/96
COST PROPOSAL FOR TASK DC026D
<Darby’s Cleaners/FDEP ERIC_4902>
< Well Abandonment >
1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >
GHD completed assessment at the Darby’s Cleaners site located in Bradenton, Manatee County. Based on the most recent results, site closure criteria were met and a Site Rehabilitation Completion Order (SRCO) was issued by the Department. Task DC026D includes well abandonment activities.
Subtask 1: Project Management Subtask 1 includes all tasks associated with project management of well abandonment and reporting for the Darby’s Cleaners site.
Subtask 2: Well Abandonment GHD personnel will obtain well abandonment permits from the local Health Department (Manatee County). The permitting will be conducted by GHDs licensed water well driller.
Following permit receipt, GHD personnel will mobilize to the subject site and abandon monitoring wells MW001 and MW002 and piezometers PZ001 through PZ007. The well abandonment will be conducted in accordance with applicable Water Management District guidelines. The wells will be grouted from bottom up using the tremie method. Following well abandonment, the concrete pad and manhole will be filled with concrete to match the existing land surface. All waste well material and concrete will be disposed off-site.
Following completion of the field activities, a brief well abandonment summary report will be prepared. The summary report will include copies of well permits, a site plan showing the location of the abandoned well and detailed photo documentation of the well abandonment activities.
Deliverables:
Deliverable Deliverable Due Date
Well Abandonment Report 1/16/2026
From: Robyn Cox To: Brian Moore Subject: RE: Darby"s Cleaners Date: Wednesday, November 12, 2025 1:41:14 PM
Hi Brian~
Our Portland is $12.80 per bag.
Thanks, Robyn Cox Branch Manager 727-530-9581
From: Brian Moore <Brian.Moore@ghd.com> Sent: Wednesday, November 12, 2025 1:30 PM To: Robyn Cox <rcox@atlanticsupply.com> Subject: RE: Darby's Cleaners portland
From: Robyn Cox <rcox@atlanticsupply.com> Sent: Wednesday, November 12, 2025 1:06 PM To: Brian Moore <Brian.Moore@ghd.com> Subject: RE: Darby's Cleaners
Hi Brian~
I’m not sure what neat cement is. We carry Portland and Concrete Mix.
Thanks, Robyn Cox Branch Manager 727-530-9581
From: Brian Moore <Brian.Moore@ghd.com> Sent: Wednesday, November 12, 2025 9:49 AM To: Robyn Cox <rcox@atlanticsupply.com> Subject: Darby's Cleaners mailto:rcox@atlanticsupply.com mailto:Brian.Moore@ghd.com mailto:rcox@atlanticsupply.com mailto:Brian.Moore@ghd.com mailto:Brian.Moore@ghd.com mailto:rcox@atlanticsupply.com
Robyn, Can you provide a price for neat cement grout, per bag?
Thanks
BRIAN MOORE PE
GHD
Proudly employee owned | ghd.com 5904 Hampton Oaks Parkway Suite F Tampa FL 33610 USA O 813 971 3882 D 813 257 0658 M 813 335 2147 E brian.moore@ghd.com
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furl.avanan.click%2Fv2%2Fr01%2F___http%3A%2Fwww.ghd.com%2F___.YXAzOmF0bGFudGljc3VwcGx5OmE6bzpiYTliNWFmNmEzYWFkN2EwNTc5ZmE3MzkzODczYWFlZjo3OmI3ZTE6NDVhNDA3YWZlOTE2YjUwMWM1MThiMmZkMzExOGJjODc3MjkzODRmNjI3NDQxOThhN2Q5MmIwNzg0ZWFhYmE5ZTpoOlQ6Tg&data=05%7C02%7CBrian.Moore%40ghd.com%7C9933a2108fd34ab7b4c908de221b09ff%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C638985696739263105%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=vV9nsV93z0tbqTFGaY5C10t0uJswShS1WL6nXz0HiXg%3D&reserved=0 mailto:brian.moore@ghd.com
From: Dalton, James B To: Brian Moore; Childs, Mackenzie Subject: RE: Well Abandonment for Darby"s (ERIC_4902) Date: Monday, August 4, 2025 4:46:04 PM
Probably doesn’t matter much, but I’d lean towards keeping MW006, even if we don’t sample it routinely.
Thanks Breck
James Breck Dalton, P.G.
Professional Geologist II Waste Site Cleanup Section Florida Department of Environmental Protection James.b.dalton@FloridaDEP.gov Office: 850-245-8892
From: Brian Moore <brian.moore@ghd.com> Sent: Monday, August 4, 2025 4:36 PM To: Childs, Mackenzie <Mackenzie.Childs@FloridaDEP.gov> Cc: Dalton, James B <James.B.Dalton@FloridaDEP.gov> Subject: RE: Well Abandonment for Darby's (ERIC_4902)
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Mackenzie, Based on the ongoing assessment at Center Cleaners, we would recommend leaving wells MW003, MW004, and MW005 that are associated with Darby’s and abandon the remaining.
MW001, MW002, MW006, and PZ001 through PZ007.
Please advise if this acceptable and I will generate a proposal
BRIAN MOORE PE
GHD
Proudly employee owned | ghd.com 5904 Hampton Oaks Parkway Suite F Tampa FL 33610 USA O 813 971 3882 D 813 257 0658 M 813 335 2147 E brian.moore@ghd.com
From: Childs, Mackenzie <Mackenzie.Childs@FloridaDEP.gov> Sent: Friday, June 20, 2025 11:07 AM mailto:James.B.Dalton@FloridaDEP.gov mailto:brian.moore@ghd.com mailto:Mackenzie.Childs@FloridaDEP.gov https://floridadep.gov/ mailto:James.b.dalton@FloridaDEP.gov http://www.ghd.com/ mailto:brian.moore@ghd.com mailto:Mackenzie.Childs@FloridaDEP.gov
To: Brian Moore <brian.moore@ghd.com> Subject: Well Abandonment for Darby's (ERIC_4902)
Brian, The SRCO for Darby’s was approved. Could you please send a proposal for well abandonment?
Thanks!
Mackenzie Childs, FCCM Florida Department of Environmental Protection Waste Site Cleanup Section Environmental Specialist II Mackenzie.Childs@FloridaDEP.gov Office: 850-245-8929
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
mailto:brian.moore@ghd.com https://floridadep.gov/ mailto:Mackenzie.Childs@FloridaDEP.gov http://survey.dep.state.fl.us/?refemail=Mackenzie.Childs@FloridaDEP.gov
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_v2.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v1.pdf |
| Cost Estimate |
| Subtask 2 |
| Subtask 3 |
| Subtask 4 |
| Subtask 5 |
| Subtask 6 |
| 2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev1_12-12-22.pdf |
| Table 1 for SAWP |
| Monitoring Well Locations |
| Utility Locate Bids_Compiled.pdf |
| Geosyntec Utility-272_Geotek_1500 |
| Geoview Utility Quote_2000_COT FTF SIS |
| Tallahassee Fire Training Division_V1_Bloodhound_3700 |
| Drilling Bids_Compiled.pdf |
| PDS_Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (sonic) |
| Direct Push |
| City of Tallahassee Fire Training Site_GW Protection PFAS Free Water Estimate Email |
| Cascade_Geosyntec Consultants, Inc. - City of Tallahassee Fire Training Facility - PN221026-118844 |
| GW Protection_Geosyntec (T) 1022060 S.pdf |
| Invoice |
| Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (MOT).xlsx.pdf |
| Sheet1 |
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v1.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v2.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v2.pdf |
| Cost Estimate |
| Subtask 2 |
| Subtask 3 |
| Subtask 4 |
| Subtask 5 |
| Subtask 6 |
| 2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev2.pdf |
| Table 1 for SAWP |
| Monitoring Well Locations |