This document is a Task Assignment (TA) under Contract Number HW684 between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. The task assignment, designated DC019A, was executed on June 1, 2022, and is specific to groundwater monitoring activities at the West Side Cleaners site located at 5036 W Colonial Drive, Orlando, Orange County, Florida. The project is identified under ERIC_5025. The FDEP Project Manager is Kevin Kane, and the Contractor's Project Manager is Brian Moore.

The task assignment consists of two subtasks: Subtask 1 (Project Management) and Subtask 2 (Groundwater Monitoring). The work involves conducting annual groundwater sampling in July 2022, including depth-to-water measurements from 31 site monitoring wells, sampling of passive diffusion bags at seven wells, and conventional sampling of two additional wells. All samples are analyzed using EPA Method 8260 for volatile organic halocarbons by a Florida-certified laboratory. The deliverable is a Groundwater Monitoring Report due September 9, 2022, with a task completion date of December 9, 2022. The total task assignment value is $6,172.85 on a fixed unit rate basis. Costs include direct labor ($1,499.95), overhead (129.80%), fringe benefits (37.80%), vehicle rental ($120.00), laboratory analysis ($733.50), investigation-derived waste disposal ($121.00), field equipment ($783.10), and a completion fee ($401.39). Project management is calculated at 13% of direct labor.

View the file

Other files

File Type Posted
CN-370000-HW684-BIL02F.pdf PDF
CN-370000-HW684-BIL2CC03.pdf PDF
CN-370000-HW684-BIL2ECO1.pdf PDF
CN-370000-HW684-BIL2FCO1.pdf PDF
CN-370000-HW684-BIL2GCO1.pdf PDF
CN-370000-HW684-CSS02A.pdf PDF
CN-370000-HW684-CSS03B.pdf PDF
CN-370000-HW684-D033CCO1.pdf PDF
CN-370000-HW684-DC001A.pdf PDF
CN-370000-HW684-DC001F.pdf PDF
CN-370000-HW684-DC002B.pdf PDF
CN-370000-HW684-DC002C.pdf PDF
CN-370000-HW684-DC002D.pdf PDF
CN-370000-HW684-DC003D.pdf PDF
CN-370000-HW684-DC004D.pdf PDF
CN-370000-HW684-DC005A.pdf PDF
CN-370000-HW684-DC005D.pdf PDF
CN-370000-HW684-DC006B.pdf PDF
CN-370000-HW684-DC009C.pdf PDF
CN-370000-HW684-DC009D.pdf PDF
CN-370000-HW684-DC009E.pdf PDF
CN-370000-HW684-DC011A.pdf PDF
CN-370000-HW684-DC011C.pdf PDF
CN-370000-HW684-DC012D.pdf PDF
CN-370000-HW684-DC013B.pdf PDF
CN-370000-HW684-DC014D.pdf PDF
CN-370000-HW684-DC014F.pdf PDF
CN-370000-HW684-DC015A.pdf PDF
CN-370000-HW684-DC015C.pdf PDF
CN-370000-HW684-DC016B.pdf PDF
CN-370000-HW684-DC016C.pdf PDF
CN-370000-HW684-DC017C.pdf PDF
CN-370000-HW684-DC018C.pdf PDF
CN-370000-HW684-DC019C.pdf PDF
CN-370000-HW684-DC019D.pdf PDF
CN-370000-HW684-DC01ACO2.pdf PDF
CN-370000-HW684-DC020B.pdf PDF
CN-370000-HW684-DC025A.pdf PDF
CN-370000-HW684-DC026B.pdf PDF
CN-370000-HW684-DC026D.pdf PDF
CN-370000-HW684-DC027C.pdf PDF
CN-370000-HW684-DC028C.pdf PDF
CN-370000-HW684-DC029C.pdf PDF
CN-370000-HW684-DC031A.pdf PDF
CN-370000-HW684-DC034B.pdf PDF
CN-370000-HW684-DC03ACO1.pdf PDF
CN-370000-HW684-DC03CCO1.pdf PDF
CN-370000-HW684-DC03CCO2.pdf PDF
CN-370000-HW684-DC040A.pdf PDF
CN-370000-HW684-DC045B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW684

DC019A Completion December 9, 2022

GHD Services, Inc. will conduct groundwater sampling at the West Side Cleaners site located in Orlando, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on May 25, 2022.

Kevin Kane (850) 245-8971 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

GHD Services, Inc.

GHD Services, Inc.

Brian Moore (813) 257-0658

ERIC_5025

5036 W Colonial Dr., Orlando, Orange County

West Side Cleaners

✔ $ 6,172.85

$ 6,172.85

Scope of Work

Brian Moore

Project Manager

Brian Moore Digitally signed by Brian Moore Date: 2022.06.01 22:19:53 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.06.01 11:22:37 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report + Project Management 09/09/2022

Subtasks 1 & 2: Upon submittal and FDEP approval of the Groundwater Monitoring Report + Project Management $ 6,172.85

$ 6,172.85

HW684

DC019A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

TO: HW684 Contract File

FROM: Kevin Kane, Contract Manager

DATE: June 1, 2022

SUBJECT: Task Assignment DC019A

West Side Cleaners

ERIC_5025

Monitoring

GHD Services, Inc. (GHD) will conduct annual groundwater sampling. Specific subtasks are detailed below:

Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.

Subtask 2: Groundwater Monitoring GHD will conduct annual groundwater sampling in July 2022. Prior to groundwater sampling, depth to water measurements will be gathered from all available site monitor wells (31 total). GHD will sample passive diffusion bags (PDBs) present at seven (7) site monitor wells including MW014, MW018, MW021, MW023, MW024, MW026, and MW027. In addition, GHD will also sample monitoring wells MW019 and MW028 using conventional methods per FDEP recommendations. All samples will be submitted to a Florida-certified laboratory and analyzed for the presence of volatile organic halocarbons by EPA Method 8260. Upon receipt of the data, a Groundwater Monitoring Report will be prepared. The Groundwater Monitoring Report will include a detail of field sampling methodology, a summary of groundwater elevation data and flow interpretations, as well as a summary of groundwater analytical results. The report will also include conclusions and recommendations for additional monitoring and/or remedial activities.

Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Subcontractors for IDW disposal were chosen on a lowest-cost basis. The Florida Department of Environmental Protection (FDEP) has a current and valid site access agreement for this site, signed May 25, 2022.

This work will be conducted in line with the scope of work included with GHD’s proposal, received May 25, 2022. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is September 9, 2022, and the completion date for the task assignment is December 9, 2022.

The final cost total for Task Assignment DC019A is $6,172.85.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 05/31/22

Task #: DC019A SubTask 1 Project Management SubTask 6

Site: West Side Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$40.12 Project Manager JM 4.30 4.3 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$46.33 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$43.28 Professional Engineer/Sc GE 14.00 14.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 11.00 11.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 11.00 11.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 51.30 4.30 47.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $1,499.95 $172.56 $1,327.39 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 129.80% $1,946.93 $223.98 $1,722.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $566.98 $65.23 $501.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,013.86 $461.77 $3,552.09 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 05/31/22

Task #: DC019A SubTask 1 Project Management SubTask 6

Site: West Side Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $11.00 $11.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $121.00 $121.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $657.00 $657.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $76.50 $76.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $733.50 $733.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $743.10 $743.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $783.10 $783.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $5,771.46 $461.77 $5,309.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $401.39 $46.18 $355.21 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $6,172.85 $507.95 $5,664.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : West Side Cleaners SUBTASK 2: Groundwater Monitoring

DATE: 05/31/22

LABOR CATEGORY

STAFF-TITLE HOURS

Sr Professional Engineer JH 1

Professional Geologist GE 1.5 Professional Geologist GE 1 Professional Geologist GE 1 Professional Geologist GE 1 Professional Geologist GE 1.5 Professional Geologist GE 1 Professional Geologist GE 2 Professional Geologist GE 3 Professional Geologist GE 1 Professional Geologist GE 1

Senior Technician SA 4 Senior Technician SA 2.5 Senior Technician SA 1.5 Senior Technician SA 3

Junior Technician WO 4 Junior Technician WO 2.5 Junior Technician WO 1.5 Junior Technician WO 3

CADD Design PM 2 CADD Design PM 2

Staff Assistants DA 2 Staff Assistants DA 1.5 Staff Assistants DA 1 Staff Assistants DA

*PROVIDE TIME REQUIRED FOR EACH PERSON

WORK DESCRIPTION

Conclusions and Recommendations

Order sample kit/develop field scope of work/contact property owner Verify COC after sampling/review results when received Coordinate IDW Disposal Site Assessment/Remediation Background Groundwater Sampling Scope of Work Groundwater Field Parameter Summary Water Level evaluation (shallow / deep) Groundwater analytical results evaluation (shallow / deep)

QA/QC

Conclusion and Recommendations

Mob/Demob (from Tampa) Water Levels (all wells - 31 total) Sample 1 well Sample diffusion bags (7 wells)

Mob/Demob (from Tampa) Water Levels (all wells - 31 total) Sample 1 well Sample diffusion bags (7 wells)

Groundwater elevation and flow (shallow/deep) Groundwater Analytical Maps (shallow/deep)

Data Entry (31 water levels/9 well samples) Summary tables (elevation, analytical) Publish Report/generate pdf GIS/Adapt update 1.5

TOTAL LABOR 47

VEHICLE TYPE RATE UNIT USEAGE

Company Truck $120.00 day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin Remediation IDW Disposal 1 drum $110.00 $110.00

TOTAL $110.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA method 8260 VOHs $73.00 9 $657.00 sample shipping (Two Day - large cooler) $70.00 1 $70.00

Ice $6.50 1 $6.50

TOTAL LAB $733.50

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables

Expendables $40.00 day 1 $40.00

Equipment (Analytical Related)

Diffusion sampler each (small well) $36.00 each 7 $252.00 Groundwater Sampling Kit $290.00 day 1 $290.00 Poly Tubing $0.30 ft 277 $83.10 Silicon Tubing $3.00 ft 6 $18.00 Drum $100.00 drum 1 $100.00

Equipment (Other) $0.00

TOTAL EQUIPMENT $783.10

FINAL --7/24/96

COST PROPOSAL FOR TASK DC019A

< West Side Cleaners, 489502256, ERIC_5025>

Groundwater Monitoring

1. INTRODUCTION:

A Soil Vapor Extraction (SVE) system was operated at the West Side Cleaners site until late 2015. At that time, the system was shutdown and soil confirmation sampling were conducted.

Since the drycleaner was still active and utilized PCE in its operation, continued system shutdown was recommended along with periodic groundwater monitoring. Task DC019A includes annual groundwater monitoring in accordance with GHD recommendations and Department approval dated October 21, 2021.

Subtask 1: Project Management Includes all tasks associated with project management for completion of groundwater sampling and reporting.

Subtask 2: Groundwater Monitoring Subtask 2 includes annual groundwater sampling in July 2022. Prior to groundwater sampling, depth to water measurements will be gathered from all available site monitor wells (31 total). During a previous sampling in July 2019, GHD personnel installed passive diffusion bags (PDB) at select site monitor wells. As such, PDB sampling is proposed at seven (7) site monitor wells including MW014, MW018, MW021, MW023, MW024, MW026, and MW027.

In addition to the use of existing PDBs, GHD will also sample monitoring wells MW019 and MW028 using conventional methods per FDEP recommendations. These wells do not contain diffusion bags. All samples will be submitted to a Florida-certified laboratory and analyzed for the presence of volatile organic halocarbons by EPA Method 8260.

Upon receipt of analytical data, a summary report will be prepared. The summary report will include a detail of field sampling methodology, a summary of groundwater elevation data and flow interpretations, as well as a summary of groundwater analytical results. The report will also include conclusions and recommendations for additional monitoring and/or remedial activities.

Deliverables:

Deliverable Deliverable Due Date

Groundwater Monitoring Report 9/9/22

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

May 23, 2022

Re: Transportation and Disposal of Non-Hazardous Soil and Water – Florida

Mr. Moore:

The price for disposal of drums of non-hazardous soil or groundwater located in the State of Florida will be $110.00 per drum, for both transportation and disposal.

This pricing is valid for all regions in the State of Florida except for the Florida Keys.

Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

From: Jamie Infinger To: Brian Moore Subject: RE: IP Cleaners - Miami Date: Monday, March 16, 2020 8:39:32 AM Attachments: image001.png image002.png image003.png image004.png

$95.00 per drum plus $150.00 stop charge Have a great day

Thanks, Jamie Infinger A Nationwide Waste Disposal Company Clean Management Environmental Group, Inc.

P: (800)-538-8131 F: (843)-538-7845 C: (912)-674-6783 jinfinger@cleanmanagement.com www.cleanmanagement.com

From: Brian.Moore@ghd.com [mailto:Brian.Moore@ghd.com] Sent: Sunday, March 15, 2020 11:45 AM To: Jamie Infinger <jinfinger@cleanmanagement.com> Subject: IP Cleaners - Miami

Jamie, Can you provide quote for disposal of 2 drums of water from the above site. Low level solvents, assume non-haz thanks

Brian Moore, PE

GHD

Proudly employee owned T: 813 257 0658 | M: 813 335 2147 | E: Brian.Moore@ghd.com 5904 Hampton Oaks Parkway Suite F Tampa Florida 33610 USA | www.ghd.com Connect

WATER | ENERGY & RESOURCES | ENVIRONMENT | PROPERTY & BUILDINGS | TRANSPORTATION

mailto:jinfinger@cleanmanagement.com mailto:Brian.Moore@ghd.com mailto:jinfinger@cleanmanagement.com http://www.cleanmanagement.com/ mailto:Brian.Moore@ghd.com http://www.ghd.com/ https://www.linkedin.com/company/ghd https://www.facebook.com/GHDGroup https://twitter.com/GHD_Namerica https://www.youtube.com/channel/UCwUGfe6zgaddIXqA7entIwQ https://www.ghd.com/en/sectors/water.aspx https://www.ghd.com/en/sectors/energy---resources.aspx https://www.ghd.com/en/sectors/environment.aspx https://www.ghd.com/en/sectors/property---buildings.aspx https://www.ghd.com/en/sectors/transportation.aspx

Please consider our environment before printing this email

CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.

This e-mail has been scanned for viruses

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approva2 wks Wed 5/25/22Tue 6/7/22

2 Subtask 1: Project Management

68 days Wed 6/8/22 Fri 9/9/22

3 Subtask 2:

Groundwater Monitoring

47 days Thu 7/7/22 Fri 9/9/22

4 Field Work Preparat 2 wks Thu 7/7/22 Wed 7/20/22

5 Groundwater Sampl1 day Fri 7/22/22 Fri 7/22/22

6 Groundwater Monitoring Report

6 wks Mon 8/1/22 Fri 9/9/22

5/15 5/22 5/29 6/5 6/12 June

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC019A at West Side Cleaners located in Orlando, Orange County

Project: TA_019A Date: Wed 5/25/22

Task Name Duration Start Finish

1 LOE Submittal/Approva2 wks Wed 5/25/22Tue 6/7/22

2 Subtask 1: Project Management

68 days Wed 6/8/22 Fri 9/9/22

3 Subtask 2:

Groundwater Monitoring

47 days Thu 7/7/22 Fri 9/9/22

4 Field Work Preparat 2 wks Thu 7/7/22 Wed 7/20/22

5 Groundwater Sampl1 day Fri 7/22/22 Fri 7/22/22

6 Groundwater Monitoring Report

6 wks Mon 8/1/22 Fri 9/9/22

Gabr

S

6/19 6/26 7/3 7/10 7/17 July

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC019A at West Side Cleaners located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approva2 wks Wed 5/25/22Tue 6/7/22

2 Subtask 1: Project Management

68 days Wed 6/8/22 Fri 9/9/22

3 Subtask 2:

Groundwater Monitoring

47 days Thu 7/7/22 Fri 9/9/22

4 Field Work Preparat 2 wks Thu 7/7/22 Wed 7/20/22

5 Groundwater Sampl1 day Fri 7/22/22 Fri 7/22/22

6 Groundwater Monitoring Report

6 wks Mon 8/1/22 Fri 9/9/22 rielle Enos

Skylar Albritton,William Ouchie

7/24 7/31 8/7 8/14 8/21 August

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC019A at West Side Cleaners located in Orlando, Orange County

Task Name Duration Start Finish

1 LOE Submittal/Approva2 wks Wed 5/25/22Tue 6/7/22

2 Subtask 1: Project Management

68 days Wed 6/8/22 Fri 9/9/22

3 Subtask 2:

Groundwater Monitoring

47 days Thu 7/7/22 Fri 9/9/22

4 Field Work Preparat 2 wks Thu 7/7/22 Wed 7/20/22

5 Groundwater Sampl1 day Fri 7/22/22 Fri 7/22/22

6 Groundwater Monitoring Report

6 wks Mon 8/1/22 Fri 9/9/22 Jeremy Hess,Gabrielle Enos,Peter McLean,D

8/28 9/4 9/11 9/18 9/25 September Oc

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC019A at West Side Cleaners located in Orlando, Orange County