This document is a Task Assignment (TA) under Contract Number HW684 between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. The task assignment, designated DC019A, was executed on June 1, 2022, and is specific to groundwater monitoring activities at the West Side Cleaners site located at 5036 W Colonial Drive, Orlando, Orange County, Florida. The project is identified under ERIC_5025. The FDEP Project Manager is Kevin Kane, and the Contractor's Project Manager is Brian Moore.
The task assignment consists of two subtasks: Subtask 1 (Project Management) and Subtask 2 (Groundwater Monitoring). The work involves conducting annual groundwater sampling in July 2022, including depth-to-water measurements from 31 site monitoring wells, sampling of passive diffusion bags at seven wells, and conventional sampling of two additional wells. All samples are analyzed using EPA Method 8260 for volatile organic halocarbons by a Florida-certified laboratory. The deliverable is a Groundwater Monitoring Report due September 9, 2022, with a task completion date of December 9, 2022. The total task assignment value is $6,172.85 on a fixed unit rate basis. Costs include direct labor ($1,499.95), overhead (129.80%), fringe benefits (37.80%), vehicle rental ($120.00), laboratory analysis ($733.50), investigation-derived waste disposal ($121.00), field equipment ($783.10), and a completion fee ($401.39). Project management is calculated at 13% of direct labor.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC019A Completion December 9, 2022
GHD Services, Inc. will conduct groundwater sampling at the West Side Cleaners site located in Orlando, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on May 25, 2022.
Kevin Kane (850) 245-8971 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore (813) 257-0658
ERIC_5025
5036 W Colonial Dr., Orlando, Orange County
West Side Cleaners
✔ $ 6,172.85
$ 6,172.85
Scope of Work
Brian Moore
Project Manager
Brian Moore Digitally signed by Brian Moore Date: 2022.06.01 22:19:53 -04'00'
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.06.01 11:22:37 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Report + Project Management 09/09/2022
Subtasks 1 & 2: Upon submittal and FDEP approval of the Groundwater Monitoring Report + Project Management $ 6,172.85
$ 6,172.85
HW684
DC019A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
TO: HW684 Contract File
FROM: Kevin Kane, Contract Manager
DATE: June 1, 2022
SUBJECT: Task Assignment DC019A
West Side Cleaners
ERIC_5025
Monitoring
GHD Services, Inc. (GHD) will conduct annual groundwater sampling. Specific subtasks are detailed below:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2: Groundwater Monitoring GHD will conduct annual groundwater sampling in July 2022. Prior to groundwater sampling, depth to water measurements will be gathered from all available site monitor wells (31 total). GHD will sample passive diffusion bags (PDBs) present at seven (7) site monitor wells including MW014, MW018, MW021, MW023, MW024, MW026, and MW027. In addition, GHD will also sample monitoring wells MW019 and MW028 using conventional methods per FDEP recommendations. All samples will be submitted to a Florida-certified laboratory and analyzed for the presence of volatile organic halocarbons by EPA Method 8260. Upon receipt of the data, a Groundwater Monitoring Report will be prepared. The Groundwater Monitoring Report will include a detail of field sampling methodology, a summary of groundwater elevation data and flow interpretations, as well as a summary of groundwater analytical results. The report will also include conclusions and recommendations for additional monitoring and/or remedial activities.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Subcontractors for IDW disposal were chosen on a lowest-cost basis. The Florida Department of Environmental Protection (FDEP) has a current and valid site access agreement for this site, signed May 25, 2022.
This work will be conducted in line with the scope of work included with GHD’s proposal, received May 25, 2022. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is September 9, 2022, and the completion date for the task assignment is December 9, 2022.
The final cost total for Task Assignment DC019A is $6,172.85.
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 05/31/22
Task #: DC019A SubTask 1 Project Management SubTask 6
Site: West Side Cleaners SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: Groundwater Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$40.12 Project Manager JM 4.30 4.3 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$46.33 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$43.28 Professional Engineer/Sc GE 14.00 14.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 11.00 11.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 11.00 11.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 51.30 4.30 47.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,499.95 $172.56 $1,327.39 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $1,946.93 $223.98 $1,722.95 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $566.98 $65.23 $501.75 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,013.86 $461.77 $3,552.09 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 1
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 05/31/22
Task #: DC019A SubTask 1 Project Management SubTask 6
Site: West Side Cleaners SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: Groundwater Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $11.00 $11.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $121.00 $121.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $657.00 $657.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $76.50 $76.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $733.50 $733.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $743.10 $743.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $783.10 $783.10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $5,771.46 $461.77 $5,309.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $401.39 $46.18 $355.21 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $6,172.85 $507.95 $5,664.90 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : West Side Cleaners SUBTASK 2: Groundwater Monitoring
DATE: 05/31/22
LABOR CATEGORY
STAFF-TITLE HOURS
Sr Professional Engineer JH 1
Professional Geologist GE 1.5 Professional Geologist GE 1 Professional Geologist GE 1 Professional Geologist GE 1 Professional Geologist GE 1.5 Professional Geologist GE 1 Professional Geologist GE 2 Professional Geologist GE 3 Professional Geologist GE 1 Professional Geologist GE 1
Senior Technician SA 4 Senior Technician SA 2.5 Senior Technician SA 1.5 Senior Technician SA 3
Junior Technician WO 4 Junior Technician WO 2.5 Junior Technician WO 1.5 Junior Technician WO 3
CADD Design PM 2 CADD Design PM 2
Staff Assistants DA 2 Staff Assistants DA 1.5 Staff Assistants DA 1 Staff Assistants DA
*PROVIDE TIME REQUIRED FOR EACH PERSON
WORK DESCRIPTION
Conclusions and Recommendations
Order sample kit/develop field scope of work/contact property owner Verify COC after sampling/review results when received Coordinate IDW Disposal Site Assessment/Remediation Background Groundwater Sampling Scope of Work Groundwater Field Parameter Summary Water Level evaluation (shallow / deep) Groundwater analytical results evaluation (shallow / deep)
QA/QC
Conclusion and Recommendations
Mob/Demob (from Tampa) Water Levels (all wells - 31 total) Sample 1 well Sample diffusion bags (7 wells)
Mob/Demob (from Tampa) Water Levels (all wells - 31 total) Sample 1 well Sample diffusion bags (7 wells)
Groundwater elevation and flow (shallow/deep) Groundwater Analytical Maps (shallow/deep)
Data Entry (31 water levels/9 well samples) Summary tables (elevation, analytical) Publish Report/generate pdf GIS/Adapt update 1.5
TOTAL LABOR 47
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin Remediation IDW Disposal 1 drum $110.00 $110.00
TOTAL $110.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
EPA method 8260 VOHs $73.00 9 $657.00 sample shipping (Two Day - large cooler) $70.00 1 $70.00
Ice $6.50 1 $6.50
TOTAL LAB $733.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Expendables $40.00 day 1 $40.00
Equipment (Analytical Related)
Diffusion sampler each (small well) $36.00 each 7 $252.00 Groundwater Sampling Kit $290.00 day 1 $290.00 Poly Tubing $0.30 ft 277 $83.10 Silicon Tubing $3.00 ft 6 $18.00 Drum $100.00 drum 1 $100.00
Equipment (Other) $0.00
TOTAL EQUIPMENT $783.10
FINAL --7/24/96
COST PROPOSAL FOR TASK DC019A
< West Side Cleaners, 489502256, ERIC_5025>
Groundwater Monitoring
1. INTRODUCTION:
A Soil Vapor Extraction (SVE) system was operated at the West Side Cleaners site until late 2015. At that time, the system was shutdown and soil confirmation sampling were conducted.
Since the drycleaner was still active and utilized PCE in its operation, continued system shutdown was recommended along with periodic groundwater monitoring. Task DC019A includes annual groundwater monitoring in accordance with GHD recommendations and Department approval dated October 21, 2021.
Subtask 1: Project Management Includes all tasks associated with project management for completion of groundwater sampling and reporting.
Subtask 2: Groundwater Monitoring Subtask 2 includes annual groundwater sampling in July 2022. Prior to groundwater sampling, depth to water measurements will be gathered from all available site monitor wells (31 total). During a previous sampling in July 2019, GHD personnel installed passive diffusion bags (PDB) at select site monitor wells. As such, PDB sampling is proposed at seven (7) site monitor wells including MW014, MW018, MW021, MW023, MW024, MW026, and MW027.
In addition to the use of existing PDBs, GHD will also sample monitoring wells MW019 and MW028 using conventional methods per FDEP recommendations. These wells do not contain diffusion bags. All samples will be submitted to a Florida-certified laboratory and analyzed for the presence of volatile organic halocarbons by EPA Method 8260.
Upon receipt of analytical data, a summary report will be prepared. The summary report will include a detail of field sampling methodology, a summary of groundwater elevation data and flow interpretations, as well as a summary of groundwater analytical results. The report will also include conclusions and recommendations for additional monitoring and/or remedial activities.
Deliverables:
Deliverable Deliverable Due Date
Groundwater Monitoring Report 9/9/22
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Brian Moore
GHD
5904 Hampton Oaks Parkway – Suite F
Tampa, FL 33610
May 23, 2022
Re: Transportation and Disposal of Non-Hazardous Soil and Water – Florida
Mr. Moore:
The price for disposal of drums of non-hazardous soil or groundwater located in the State of Florida will be $110.00 per drum, for both transportation and disposal.
This pricing is valid for all regions in the State of Florida except for the Florida Keys.
Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.
This quote is valid for 180 days.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
From: Jamie Infinger To: Brian Moore Subject: RE: IP Cleaners - Miami Date: Monday, March 16, 2020 8:39:32 AM Attachments: image001.png image002.png image003.png image004.png
$95.00 per drum plus $150.00 stop charge Have a great day
Thanks, Jamie Infinger A Nationwide Waste Disposal Company Clean Management Environmental Group, Inc.
P: (800)-538-8131 F: (843)-538-7845 C: (912)-674-6783 jinfinger@cleanmanagement.com www.cleanmanagement.com
From: Brian.Moore@ghd.com [mailto:Brian.Moore@ghd.com] Sent: Sunday, March 15, 2020 11:45 AM To: Jamie Infinger <jinfinger@cleanmanagement.com> Subject: IP Cleaners - Miami
Jamie, Can you provide quote for disposal of 2 drums of water from the above site. Low level solvents, assume non-haz thanks
Brian Moore, PE
GHD
Proudly employee owned T: 813 257 0658 | M: 813 335 2147 | E: Brian.Moore@ghd.com 5904 Hampton Oaks Parkway Suite F Tampa Florida 33610 USA | www.ghd.com Connect
WATER | ENERGY & RESOURCES | ENVIRONMENT | PROPERTY & BUILDINGS | TRANSPORTATION
mailto:jinfinger@cleanmanagement.com mailto:Brian.Moore@ghd.com mailto:jinfinger@cleanmanagement.com http://www.cleanmanagement.com/ mailto:Brian.Moore@ghd.com http://www.ghd.com/ https://www.linkedin.com/company/ghd https://www.facebook.com/GHDGroup https://twitter.com/GHD_Namerica https://www.youtube.com/channel/UCwUGfe6zgaddIXqA7entIwQ https://www.ghd.com/en/sectors/water.aspx https://www.ghd.com/en/sectors/energy---resources.aspx https://www.ghd.com/en/sectors/environment.aspx https://www.ghd.com/en/sectors/property---buildings.aspx https://www.ghd.com/en/sectors/transportation.aspx
Please consider our environment before printing this email
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
This e-mail has been scanned for viruses
ID Task Mode
Task Name Duration Start Finish
1 LOE Submittal/Approva2 wks Wed 5/25/22Tue 6/7/22
2 Subtask 1: Project Management
68 days Wed 6/8/22 Fri 9/9/22
3 Subtask 2:
Groundwater Monitoring
47 days Thu 7/7/22 Fri 9/9/22
4 Field Work Preparat 2 wks Thu 7/7/22 Wed 7/20/22
5 Groundwater Sampl1 day Fri 7/22/22 Fri 7/22/22
6 Groundwater Monitoring Report
6 wks Mon 8/1/22 Fri 9/9/22
5/15 5/22 5/29 6/5 6/12 June
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC019A at West Side Cleaners located in Orlando, Orange County
Project: TA_019A Date: Wed 5/25/22
Task Name Duration Start Finish
1 LOE Submittal/Approva2 wks Wed 5/25/22Tue 6/7/22
2 Subtask 1: Project Management
68 days Wed 6/8/22 Fri 9/9/22
3 Subtask 2:
Groundwater Monitoring
47 days Thu 7/7/22 Fri 9/9/22
4 Field Work Preparat 2 wks Thu 7/7/22 Wed 7/20/22
5 Groundwater Sampl1 day Fri 7/22/22 Fri 7/22/22
6 Groundwater Monitoring Report
6 wks Mon 8/1/22 Fri 9/9/22
Gabr
S
6/19 6/26 7/3 7/10 7/17 July
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC019A at West Side Cleaners located in Orlando, Orange County
Task Name Duration Start Finish
1 LOE Submittal/Approva2 wks Wed 5/25/22Tue 6/7/22
2 Subtask 1: Project Management
68 days Wed 6/8/22 Fri 9/9/22
3 Subtask 2:
Groundwater Monitoring
47 days Thu 7/7/22 Fri 9/9/22
4 Field Work Preparat 2 wks Thu 7/7/22 Wed 7/20/22
5 Groundwater Sampl1 day Fri 7/22/22 Fri 7/22/22
6 Groundwater Monitoring Report
6 wks Mon 8/1/22 Fri 9/9/22 rielle Enos
Skylar Albritton,William Ouchie
7/24 7/31 8/7 8/14 8/21 August
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC019A at West Side Cleaners located in Orlando, Orange County
Task Name Duration Start Finish
1 LOE Submittal/Approva2 wks Wed 5/25/22Tue 6/7/22
2 Subtask 1: Project Management
68 days Wed 6/8/22 Fri 9/9/22
3 Subtask 2:
Groundwater Monitoring
47 days Thu 7/7/22 Fri 9/9/22
4 Field Work Preparat 2 wks Thu 7/7/22 Wed 7/20/22
5 Groundwater Sampl1 day Fri 7/22/22 Fri 7/22/22
6 Groundwater Monitoring Report
6 wks Mon 8/1/22 Fri 9/9/22 Jeremy Hess,Gabrielle Enos,Peter McLean,D
8/28 9/4 9/11 9/18 9/25 September Oc
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC019A at West Side Cleaners located in Orlando, Orange County
File details come from the government source that posted it. Updated .