CN-370000-HW684-DC014A.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|HW684|68b160b8827755ddf560142dd2a41e53
Contract number
HW684
Issued by
Florida

About this file

This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) to GHD Services, Inc. under Contract Number HW684. The task assignment, identified as DC014A, pertains to soil and groundwater sampling activities at the former Plant City Laundry and Cleaners site located at 401 E Reynolds Street in Plant City, Hillsborough County, Florida. The project is designated ERIC_4722 and falls under FDEP's monitoring and assessment activities. Kevin Kane serves as the FDEP Department Project Manager, while Brian Moore is the Contractor's Project Manager for GHD Services, Inc.

The task assignment requires GHD Services, Inc. to conduct soil and groundwater sampling with a total value of $23,613.77 on a fixed unit rate basis. The work is divided into two subtasks: Subtask 1 covers project management calculated at 13% of direct labor costs ($1,291.04), and Subtask 2 encompasses soil and groundwater testing ($22,322.73). The scope includes soil sampling at 58 locations using stainless-steel hand augers with field screening, laboratory analysis of volatile organic compounds via EPA Method 8260, groundwater sampling from nine monitoring wells across shallow, intermediate, and deep zones, and preparation of a Soil and Groundwater Sampling Summary to be incorporated into an Interim Source Removal Plan. Field work is scheduled to occur between May 2 and May 6, 2022, with a deliverable due date of June 16, 2022, and a task completion date of September 16, 2022. Costs include direct labor ($3,812.36), overhead ($4,948.44), fringe benefits ($1,441.08), vehicle rental ($480.00), laboratory analysis ($8,273.00), field equipment and expendables ($3,528.70), subcontractor services for investigation-derived waste disposal ($110.00), and a completion fee ($1,020.19). The task assignment was signed on April 18, 2022, by both GHD Services, Inc. and FDEP representatives.

View the file

Other files

File Type Posted
CN-370000-HW684-BIL02B.pdf PDF
CN-370000-HW684-BIL02D.pdf PDF
CN-370000-HW684-BIL02G.pdf PDF
CN-370000-HW684-CSS01A.pdf PDF
CN-370000-HW684-CSS1ACO1.pdf PDF
CN-370000-HW684-CSS3BCO1.pdf PDF
CN-370000-HW684-DC001D.pdf PDF
CN-370000-HW684-DC003B.pdf PDF
CN-370000-HW684-DC004A.pdf PDF
CN-370000-HW684-DC004E.pdf PDF
CN-370000-HW684-DC005B.pdf PDF
CN-370000-HW684-DC005E.pdf PDF
CN-370000-HW684-DC006C.pdf PDF
CN-370000-HW684-DC007C.pdf PDF
CN-370000-HW684-DC008A.pdf PDF
CN-370000-HW684-DC008D.pdf PDF
CN-370000-HW684-DC010D.pdf PDF
CN-370000-HW684-DC011D.pdf PDF
CN-370000-HW684-DC012E.pdf PDF
CN-370000-HW684-DC013A.pdf PDF
CN-370000-HW684-DC017B.pdf PDF
CN-370000-HW684-DC018D.pdf PDF
CN-370000-HW684-DC019A.pdf PDF
CN-370000-HW684-DC019B.pdf PDF
CN-370000-HW684-DC01ACO1.pdf PDF
CN-370000-HW684-DC01ACO5.pdf PDF
CN-370000-HW684-DC01ACO6.pdf PDF
CN-370000-HW684-DC021D.pdf PDF
CN-370000-HW684-DC022B.pdf PDF
CN-370000-HW684-DC023A.pdf PDF
CN-370000-HW684-DC025B.pdf PDF
CN-370000-HW684-DC025C.pdf PDF
CN-370000-HW684-DC027A.pdf PDF
CN-370000-HW684-DC028B.pdf PDF
CN-370000-HW684-DC031B.pdf PDF
CN-370000-HW684-DC031C.pdf PDF
CN-370000-HW684-DC032A.pdf PDF
CN-370000-HW684-DC035B.pdf PDF
CN-370000-HW684-DC035C.pdf PDF
CN-370000-HW684-DC039A.pdf PDF
CN-370000-HW684-DC03ACO2.pdf PDF
CN-370000-HW684-DC040B.pdf PDF
CN-370000-HW684-DC040C.pdf PDF
CN-370000-HW684-DC041A.pdf PDF
CN-370000-HW684-DC043A.pdf PDF
CN-370000-HW684-DC044A.pdf PDF
CN-370000-HW684-DC045C.pdf PDF
CN-370000-HW684-DC04A.pdf PDF
CN-370000-HW684-DC053A.pdf PDF
CN-370000-HW684-DC054A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW684

DC014A Completion September 16, 2022

GHD Services, Inc. will conduct soil and groundwater sampling at the former Plant City Laundry and Cleaners site located in Plant City, FL. All work will be conducted in accordance with the scope of work and cost proposal submitted on April 4, 2022.

Kevin Kane (850) 245-8971 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

GHD Services, Inc.

GHD Services, Inc.

Brian Moore (813) 257-0658

ERIC_4722

401 E Reynolds St, Plant City, Hillsborough County

Plant City Laundry and Cleaners

✔ $ 23,613.77

$ 23,613.77

Scope of Work

Brian Moore

Contract Manager

Brian Moore Digitally signed by Brian Moore Date: 2022.04.18 16:14:22 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.04.18 14:40:23 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Soil and Groundwater Sampling Summary + Project Management 06/16/2022

Subtask 1 + 2: Upon submittal and FDEP approval of the Soil and Groundwater Sampling Summary + Project Management $ 23,613.77

$ 23,613.77

HW684

DC014A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

TO: HW684 Contract File

FROM: Kevin Kane, Contract Manager

DATE: April 15, 2022

SUBJECT: Task Assignment DC014A

Plant City Laundry and Cleaners

ERIC_4722

Monitoring

GHD Services, Inc. (GHD) will conduct annual soil and groundwater sampling. Specific subtasks are detailed below:

Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.

Subtask 2: Soil and Groundwater Sampling GHD personnel will mobilize to the site and complete soil sampling at a total of fifty-eight

(58) locations. The soil sampling will involve the advancement of a stainless-steel hand auger and soil samples will be field screened with an OVA. Soil samples will be gathered from 0-0.5, 0.5-2, 2-4, and/or 4-6 ft bls for laboratory analysis. Soil sampling will be conducted in accordance with the attached sampling location plan and sampling table.

Soil samples will be submitted to a fixed laboratory for analysis for the presence of VOHs by EPA Method 8260. Aliquots will also be collected for potential SPLP analysis (if determined necessary after review of the totals data). For planning purposes, GHD has planned for ten (10) SPLP analysis. Recommendations will be provided to DEP prior to proceeding with SPLP analysis.

During the same mobilization, GHD will conduct groundwater sampling. Prior to sampling, depth to water will be gathered at all site wells (33 total). Following depth to water measurements, GHD personnel will sample monitor wells MW004S/4I/4D, MW005S/5I/5D, MW006S/6I/6D, MW007S/7I/7D, MW008S/8I/8D, MW011I/11D, and MW012I. Groundwater sampling will be conducted in general accordance with FDEP Standard Operating Procedures. Groundwater samples will be analyzed for VOHs by EPA Method 8260.

Following receipt of analytical results, GHD will prepare a Soil and Groundwater Sampling Summary. GHD will incorporate the results into the ISRP, which is currently being completed under a separate task. The summary of historical and current soil and groundwater sampling results will be summarized in the ISRP.

Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Subcontractors for IDW disposal were chosen on a lowest-cost basis.

The Florida Department of Environmental Protection (FDEP) has a current and valid Site Access Agreement for this site, signed August 14, 2017.

This work will be conducted in line with the scope of work included with GHD’s proposal, received April 4, 2022. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is June 16, 2022, and the completion date for the task assignment is September 16, 2022.

The final cost total for Task Assignment DC014A is $23,613.77.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 04/14/22

Task #: DC014A SubTask 1 Project Management SubTask 6

Site: Plant City Laundry SubTask 2 Soil and Groundwater Testing SubTask 7

Activity/Phase: Assessment SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$40.12 Project Manager JM 10.90 10.9 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$46.33 Sr Professional Engineer JH 2.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$43.28 Professional Engineer/Sc GE 15.00 15.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 52.00 52.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 52.00 52.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 6.50 6.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 8.00 8.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 146.40 10.90 135.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $3,812.36 $438.59 $3,373.77 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 129.80% $4,948.44 $569.29 $4,379.15 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $1,441.08 $165.79 $1,275.29 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $10,201.88 $1,173.67 $9,028.21 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $480.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 04/14/22

Task #: DC014A SubTask 1 Project Management SubTask 6

Site: Plant City Laundry SubTask 2 Soil and Groundwater Testing SubTask 7

Activity/Phase: Assessment SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $480.00 $480.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $7,727.00 $7,727.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $546.00 $546.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $8,273.00 $8,273.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $3,328.70 $3,328.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $3,528.70 $3,528.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $22,593.58 $1,173.67 $21,419.91 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,020.19 $117.37 $902.82 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $23,613.77 $1,291.04 $22,322.73 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Plant City Laundry SUBTASK 2: Soil and Groundwater Testing

DATE: 04/14/22

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr Professional Engineer JH Prepare soil data summary and new cut lines (add to ISRP) 2

Professional Engineer/Scientist GE Prepare field scope of work and laboratory coordination 1 Professional Engineer/Scientist GE Uility Locate 0.5 Professional Engineer/Scientist GE Coordination with property owner for work 1 Professional Engineer/Scientist GE Review field package (QA/QC) 1 Professional Engineer/Scientist GE Soil Sampling Methodology (add to ISRP) 2 Professional Engineer/Scientist GE Groundwater Sampling Methodology (add to ISRP) 1 Professional Engineer/Scientist GE Characterize IDW and complete profiling 1 Professional Engineer/Scientist GE Soil Sampling Results (add to ISRP) 2 Professional Engineer/Scientist GE Groundwater Flow Evaluation (shallow/int/deep) 2 Professional Engineer/Scientist GE Groundwater Sampling Results (shallow/int/deep) 2 Professional Engineer/Scientist GE QA/QC Laboratory Data 1.5

Senior Technician WM Mob/demob (5 days) 7.5 Senior Technician WM Soil Borings (58 borings - 0.5 hour per boring) 29 Senior Technician WM Water Levels (33 total) 2 Senior Technician WM Groundwater Sampling (9 wells) 13.5

Senior Technician SA Mob/demob (5 days) 7.5 Senior Technician SA Soil Borings (58 borings - 0.5 hour per boring) 29 Senior Technician SA Water Levels (33 total) 2 Senior Technician SA Groundwater Sampling (9 wells) 13.5

Drafting Technician PM 58 boring locations with soil data 3 Drafting Technician PM Water level contours (3 zones) 2 Drafting Technician PM Groundwater data (shallow/int/deep) 1.5

6.5

Administrative Assistant DA Data Entry (28 soil borings, 33 wl, 18 gw) 4 Administrative Assistant DA Update Summary Tables 2 Administrative Assistant DA Finalize pdf document 2

TOTAL LABOR 135.5

VEHICLE TYPE RATE UNIT USEAGE

Company Truck $480.00 week 1 $480.00

TOTAL VEHICLE $480.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin IDW Disposal 1 drum $100.00 $100.00

TOTAL $100.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs - soil EPA 8260 $73.00 71 $5,183.00 VOHs - gw EPA 8260 $73.00 18 $1,314.00

SPLP (zero head space) $50.00 10 $500.00 VOHs Leachate analysis (8260) $73.00 10 $730.00 ice $6.50 4 $26.00 Shipping (soil) large cooler -overnight $150.00 3 $450.00 shipping (gw) Large cooler - 2 day $70.00 1 $70.00

TOTAL LAB $8,273.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables

Expendables $40.00 day 5 $200.00

Equipment (Analytical Related) Groundwater Sampling Kit $290.00 day 4 $1,160.00 Poly Tubing (HDPE) $0.30 ft 259 $77.70 Silicon Tubing $3.00 ft 18 $54.00 Soil Sampling Kit (through concrete) $235.00 day 3 $705.00 Drum $100.00 drum 1 $100.00 Encore Sampler $16.00 each 77 $1,232.00

Equipment (Other) $0.00

TOTAL EQUIPMENT $3,528.70

FINAL --7/24/96

COST PROPOSAL FOR TASK DC014A

<Plant City Laundry / FDEP ERIC_4722>

< Soil and Groundwater Testing >

1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >

Intertek (PSI) previously completed initial soil assessment at the former Plant City Laundry site located in Plant City, Hillsborough County, and a Site Assessment Report was submitted in February 2021 and revised in November 2021. An Interim Source Removal Plan (ISRP) was submitted in December 2021. The assessment identified impacted groundwater and soil beneath the site. In anticipation of potential source removal, additional soil testing was recently recommended along with groundwater monitoring. Task DC014A includes soil and groundwater sampling. The results of the sampling will be incorporated into the ISRP that is currently being prepared by GHD.

Subtask 1: Project Management Subtask 1 includes all tasks associated with project management of the soil and groundwater testing activities at the former Plant City Laundry site.

Subtask 2: Soil and Groundwater Sampling Initially, GHD will coordinate site access with the current property owner. GHD personnel will mobilize to the site and complete soil sampling at a total of fifty eight (58) locations. The soil sampling will involve the advancement of a stainless steel hand auger and soil samples will be field-screened with an OVA. Soil samples will be gathered from 0-0.5, 0.5-2, 2-4, and/or 4-6 ft bls for laboratory analysis. Soil sampling will be conducted in accordance with the attached sampling location plan and sampling table. Soil samples will be submitted to a fixed laboratory for analysis for the presence of VOHs by EPA Method 8260. Aliquots will also be collected for potential SPLP analysis (if determined necessary after review of the totals data).

For planning purposes, GHD has planned for ten (10) SPLP analysis. Recommendations will be provided to DEP prior to proceeding with SPLP analysis.

During the same mobilization, GHD will conduct groundwater sampling. Prior to sampling, depth to water will be gathered at all site wells (33 total). Following depth to water measurements, GHD personnel will sample monitor wells MW004S/4I/4D, MW005S/5I/5D, MW006S/6I/6D, MW007S/7I/7D, MW008S/8I/8D, MW011I/11D, and MW012I. Groundwater sampling will be conducted in general accordance with FDEP Standard Operating Procedures.

Groundwater samples will be analyzed for VOHs by EPA Method 8260.

Following receipt of analytical results, GHD will incorporate the results into the ISRP, which is currently being completed under a separate task. The summary of historical and current soil and groundwater sampling results will be summarized in the ISRP.

Deliverables:

Deliverable Deliverable Due Date

Field Notes, Laboratory Analytical Data, and DEP receipt of ISRP 6/16/22

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

March 16, 2020

Re: IP Cleaners - Miami, FL

Mr. Moore:

The price for disposal of two (2) drums of non-hazardous groundwater located in Miami, FL will be $100.00 per drum, or $200.00 total, for both transportation and disposal.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

From: Jamie Infinger To: Brian Moore Subject: RE: IP Cleaners - Miami Date: Monday, March 16, 2020 8:39:32 AM Attachments: image001.png image002.png image003.png image004.png

$95.00 per drum plus $150.00 stop charge Have a great day

Thanks, Jamie Infinger A Nationwide Waste Disposal Company Clean Management Environmental Group, Inc.

P: (800)-538-8131 F: (843)-538-7845 C: (912)-674-6783 jinfinger@cleanmanagement.com www.cleanmanagement.com

From: Brian.Moore@ghd.com [mailto:Brian.Moore@ghd.com] Sent: Sunday, March 15, 2020 11:45 AM To: Jamie Infinger <jinfinger@cleanmanagement.com> Subject: IP Cleaners - Miami

Jamie, Can you provide quote for disposal of 2 drums of water from the above site. Low level solvents, assume non-haz thanks

Brian Moore, PE

GHD

Proudly employee owned T: 813 257 0658 | M: 813 335 2147 | E: Brian.Moore@ghd.com 5904 Hampton Oaks Parkway Suite F Tampa Florida 33610 USA | www.ghd.com Connect

WATER | ENERGY & RESOURCES | ENVIRONMENT | PROPERTY & BUILDINGS | TRANSPORTATION

mailto:jinfinger@cleanmanagement.com mailto:Brian.Moore@ghd.com mailto:jinfinger@cleanmanagement.com http://www.cleanmanagement.com/ mailto:Brian.Moore@ghd.com http://www.ghd.com/ https://www.linkedin.com/company/ghd https://www.facebook.com/GHDGroup https://twitter.com/GHD_Namerica https://www.youtube.com/channel/UCwUGfe6zgaddIXqA7entIwQ https://www.ghd.com/en/sectors/water.aspx https://www.ghd.com/en/sectors/energy---resources.aspx https://www.ghd.com/en/sectors/environment.aspx https://www.ghd.com/en/sectors/property---buildings.aspx https://www.ghd.com/en/sectors/transportation.aspx

Please consider our environment before printing this email

CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.

This e-mail has been scanned for viruses

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 4/4/22 Fri 4/15/22

2 Subtask 1: Project Management

44 days Mon 4/18/22

Thu 6/16/22

3 Subtask 2: Soil and Groundwater Sampling

44 days Mon 4/18/22

Thu 6/16/22

4 Field Work Preparation2 wks Mon 4/18/22Fri 4/29/22

5 Soil Sampling 3 days Mon 5/2/22 Wed 5/4/22

6 Groundwater Sampling2 days Thu 5/5/22 Fri 5/6/22

7 Data Review/Summary3 wks Fri 5/27/22 Thu 6/16/22

3/27 April

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC014A at the Plant City Laundry facility located in Plant City, Hillsborough County

Project: TA_014A Date: Mon 4/4/22

4/3 4/10 4/17

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC014A at the Plant City Laundry facility located in Plant City, Hillsborough County gabrielle Enos

William McKinney,Skylar Albritton

William McKinney,Skylar Albritton

4/24 5/1 5/8 May

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC014A at the Plant City Laundry facility located in Plant City, Hillsborough County

5/15 5/22 5/29 June

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC014A at the Plant City Laundry facility located in Plant City, Hillsborough County gabrielle Enos,Jeremy Hess,Peter McLean,Debra Andrews

6/5 6/12 6/19

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC014A at the Plant City Laundry facility located in Plant City, Hillsborough County

File details come from the government source that posted it. Updated .