Task Assignment DC008A Summary

This document is a Task Assignment (TA) entered into between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc., a private environmental consulting firm. The task assignment is executed pursuant to Contract Number HW684 and represents a specific work order issued under an existing indefinite delivery vehicle contract. The Department Project Manager is Kevin Kane, and the Contractor's Project Manager is Brian Moore, with the work location at 7252 W Atlantic Boulevard, Margate, Broward County, Florida, at the former Prime Cleaners site (ERIC_4077).

GHD Services, Inc. will conduct two groundwater sampling events at the Prime Cleaners site in accordance with FDEP recommendations dated February 28, 2022. The scope includes three subtasks: Subtask 1 (Project Management at 13% of direct labor), Subtask 2 (Groundwater Sampling in April 2022 with field notes and analytical data due May 20, 2022), and Subtask 3 (Groundwater Sampling in October 2022 with a summary report due December 8, 2022). The total task assignment value is $2,885.47, allocated as follows: Subtask 2 invoice amount of $1,076.81 upon submittal and FDEP approval of field notes and analytical data, and Subtasks 1 and 3 invoice amount of $1,808.66 upon submittal and FDEP approval of the groundwater monitoring summary letter and project management. The task assignment completion date is March 10, 2023. Costs are structured on a fixed unit rate basis with no identified set-asides or option periods.

View the file

Other files

File Type Posted
CN-370000-HW684-BIL02B.pdf PDF
CN-370000-HW684-BIL02D.pdf PDF
CN-370000-HW684-BIL02G.pdf PDF
CN-370000-HW684-CSS01A.pdf PDF
CN-370000-HW684-CSS1ACO1.pdf PDF
CN-370000-HW684-CSS3BCO1.pdf PDF
CN-370000-HW684-DC001D.pdf PDF
CN-370000-HW684-DC003B.pdf PDF
CN-370000-HW684-DC004A.pdf PDF
CN-370000-HW684-DC004E.pdf PDF
CN-370000-HW684-DC005B.pdf PDF
CN-370000-HW684-DC005E.pdf PDF
CN-370000-HW684-DC006C.pdf PDF
CN-370000-HW684-DC007C.pdf PDF
CN-370000-HW684-DC008D.pdf PDF
CN-370000-HW684-DC010D.pdf PDF
CN-370000-HW684-DC011D.pdf PDF
CN-370000-HW684-DC012E.pdf PDF
CN-370000-HW684-DC013A.pdf PDF
CN-370000-HW684-DC014A.pdf PDF
CN-370000-HW684-DC017B.pdf PDF
CN-370000-HW684-DC018D.pdf PDF
CN-370000-HW684-DC019A.pdf PDF
CN-370000-HW684-DC019B.pdf PDF
CN-370000-HW684-DC01ACO1.pdf PDF
CN-370000-HW684-DC01ACO5.pdf PDF
CN-370000-HW684-DC01ACO6.pdf PDF
CN-370000-HW684-DC021D.pdf PDF
CN-370000-HW684-DC022B.pdf PDF
CN-370000-HW684-DC023A.pdf PDF
CN-370000-HW684-DC025B.pdf PDF
CN-370000-HW684-DC025C.pdf PDF
CN-370000-HW684-DC027A.pdf PDF
CN-370000-HW684-DC028B.pdf PDF
CN-370000-HW684-DC031B.pdf PDF
CN-370000-HW684-DC031C.pdf PDF
CN-370000-HW684-DC032A.pdf PDF
CN-370000-HW684-DC035B.pdf PDF
CN-370000-HW684-DC035C.pdf PDF
CN-370000-HW684-DC039A.pdf PDF
CN-370000-HW684-DC03ACO2.pdf PDF
CN-370000-HW684-DC040B.pdf PDF
CN-370000-HW684-DC040C.pdf PDF
CN-370000-HW684-DC041A.pdf PDF
CN-370000-HW684-DC043A.pdf PDF
CN-370000-HW684-DC044A.pdf PDF
CN-370000-HW684-DC045C.pdf PDF
CN-370000-HW684-DC04A.pdf PDF
CN-370000-HW684-DC053A.pdf PDF
CN-370000-HW684-DC054A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW684

DC008A Completion March 10, 2023

GHD Services, Inc. will conduct two groundwater sampling events at the former Prime Cleaners site located in Margate, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on March 29, 2022.

Kevin Kane (850) 245-8971 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

GHD Services, Inc.

GHD Services, Inc.

Brian Moore (813) 257-0658

ERIC_4077

7252 W Atlantic Blvd, Margate, Broward County

Prime Cleaners

✔ $ 2,885.47

$ 2,885.47

Scope of Work

Brian Moore

Contract Manager

Brian Moore Digitally signed by Brian Moore Date: 2022.04.20 14:11:28 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.04.20 11:05:07 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Field Notes and Analytical Data 05/20/2022

Groundwater Monitoring Summary Letter + Project Management 12/08/2022

Subtask 2: Upon submittal and FDEP approval of the Field Notes and Analytical Data $ 1,076.81

Subtasks 1 & 3: Upon submittal and FDEP approval of the Groundwater Monitoring Summary Letter + Project Management $ 1,808.66

$ 2,885.47

HW684

DC008A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

TO: HW684 Contract File

FROM: Kevin Kane, Contract Manager

DATE: April 20, 2022

SUBJECT: Task Assignment DC008A

Prime Cleaners

ERIC_4077

Monitoring

GHD Services, Inc. (GHD) will conduct two groundwater sampling events. Specific subtasks are detailed below:

Subtask 1: Project Management Project management is calculated at 13% of the direct labor.

Subtask 2: Groundwater Sampling (April 2022) The initial sampling event will be conducted in April 2022. Groundwater sampling will be conducted at monitor well MW004. Prior to sampling, depth to water measurements will be gathered at MW004 only. Groundwater sampling will be conducted in general accordance with FDEP Standard Operating Procedures. The groundwater sample from MW004 will be analyzed for the presence of volatile organic halocarbons by EPA Method 8260. Following receipt of analytical data, GHD will submit an email summary with field notes and laboratory analytical results.

Subtask 3: Groundwater Sampling (October 2022) The second sampling event will be conducted in October 2022. Groundwater sampling will be conducted at monitor well MW004. Prior to sampling, depth to water measurements will be gathered at MW004 only. Groundwater sampling will be conducted in general accordance with FDEP Standard Operating Procedures. The groundwater sample from MW004 will be analyzed for the presence of volatile organic halocarbons by EPA Method 8260. Upon receipt of analytical data, a summary report will be prepared. The summary report will include a detail of field sampling methodology along with field and laboratory results. The report will include summary tables and figures depicting groundwater analytical data. The report will also include recommendations for additional testing and/or monitoring.

The Florida Department of Environmental Protection (FDEP) has a current and valid Site Access Agreement for this site, signed May 13, 2020.

This work will be conducted in line with the scope of work included with GHD’s proposal, received March 29, 2022. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is December 8, 2022, and the completion date for the task assignment is March 10, 2023.

The final cost total for Task Assignment DC008A is $2,885.47.

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 04/20/22

Task #: DC008A SubTask 1 Project Management SubTask 6

Site: Prime Cleaners SubTask 2 Groundwater Sampling SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 Groundwater Sampling SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$40.12 Project Manager JM 2.20 2.2 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$46.33 Sr Professional Engineer JH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$43.28 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 7.00 3.50 3.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 8.50 2.75 5.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 1.00 0.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 1.00 0.25 0.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00

$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0

Total Hours 19.70 2.20 6.50 11.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $759.24 $87.35 $255.31 $416.58 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 129.80% $985.49 $113.38 $331.39 $540.72 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $287.00 $33.02 $96.51 $157.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $2,031.73 $233.75 $683.21 $1,114.77 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $120.00 $60.00 $60.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 1

FDEP COST ESTIMATEContractor: GHD Services Inc.

Date: 04/20/22

Task #: DC008A SubTask 1 Project Management SubTask 6

Site: Prime Cleaners SubTask 2 Groundwater Sampling SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 Groundwater Sampling SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $60.00 $60.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $146.00 $73.00 $73.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $117.00 $58.50 $58.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $263.00 $131.50 $131.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $20.00 $20.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $227.56 $113.78 $113.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $267.56 $133.78 $133.78 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $2,682.29 $233.75 $1,008.49 $1,440.05 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $203.18 $23.38 $68.32 $111.48 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $2,885.47 $257.13 $1,076.81 $1,551.53 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

REV: 02/03 Page 2

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Prime Cleaners SUBTASK 2: Groundwater Sampling

DATE: 04/20/22

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager JM Specify laboratory data deliverable/Sample Kit 0.5 Project Manager JM Field sampling SOW/coordinate site access 0.5 Project Manager JM Site Access 0.25 Project Manager JM QA/QC field and laboratory data 0.5 Project Manager JM Summary Email 1

2.75

Project Scientist TC mob/demb (from Wellington) 2 Project Scientist TC Groundwater Sampling (1 wells) 1.5

3.5

Staff Assistant DA Data Entry 0.25 0.25

TOTAL LABOR 6.5

VEHICLE TYPE RATE UNIT USEAGE

Company Truck $120.00 day 0.5 $60.00

TOTAL VEHICLE $60.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00 $0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs 8260 $73.00 1 $73.00 shipping 2 day $52.00 1 $52.00 ice $6.50 1 $6.50

TOTAL LAB $131.50

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables

Expendables $40.00 day 0.5 $20.00

Equipment (Analytical Related)

Groundwater Sampling Kit $208.55 day 0.5 $104.28 Poly Tubing (HDPE) $0.25 ft 30 $7.50 Silicon Tubing $2.00 ft 1 $2.00

Equipment (Other) $0.00

TOTAL EQUIPMENT $133.78

FINAL --7/24/96

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Prime Cleaners SUBTASK 3: Groundwater Sampling

DATE: 04/20/22

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager JM Specify laboratory data deliverable/Sample Kit 0.5 Project Manager JM Field sampling SOW/coordinate site access 0.5 Project Manager JM Site Access 0.25 Project Manager JM QA/QC field and laboratory data 0.5 Project Manager JM Prepare Groundwater Sampling Summary (Letter Report) 4

5.75

Project Scientist TC mob/demb (from Wellington) 2 Project Scientist TC Groundwater Sampling (1 wells) 1.5

3.5

Drafting Technician PM Update Analytical Figure 1

Staff Assistant DA Data Entry 0.25 Staff Assistant DA Publish Report 0.5

0.75

TOTAL LABOR 11

VEHICLE TYPE RATE UNIT USEAGE

Company Truck $120.00 day 0.5 $60.00

TOTAL VEHICLE $60.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00 $0.00 $0.00 $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

$0.00 $0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs 8260 $73.00 1 $73.00 shipping 2 day $52.00 1 $52.00 ice $6.50 1 $6.50

TOTAL LAB $131.50

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables

Expendables $40.00 day 0.5 $20.00

Equipment (Analytical Related)

Groundwater Sampling Kit $208.55 day 0.5 $104.28 Poly Tubing (HDPE) $0.25 ft 30 $7.50 Silicon Tubing $2.00 ft 1 $2.00

Equipment (Other) $0.00

TOTAL EQUIPMENT $133.78

FINAL --7/24/96

COST PROPOSAL FOR TASK DC008A

<Prime Cleaners /ERIC_4077> < Groundwater Monitoring >

1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >

The Prime Cleaners site is located in Margate, Broward County. Site Assessment and remedial activities have been ongoing at the site for several years. In 2019, GHD completed groundwater sampling and recommended annual monitoring since the interior of the former drycleaner suite was not accessible. As part of Task DC008A, GHD will conduct groundwater sampling in accordance with recent FDEP recommendations dated February 28, 2022. The recommended scope of work includes completing two sampling events for monitor well MW004. The sampling is being conducted in anticipation of well abandonment and site renovations.

Subtask 1: Project Management Subtask 1 includes all activities associated with project management of the groundwater monitoring activities.

Subtask 2: Groundwater Sampling The initial sampling event will be conducted in April 2022. Groundwater sampling will be conducted at monitor well MW004. Prior to sampling, depth to water measurements will be gathered at MW004 only. Groundwater sampling will be conducted in general accordance with FDEP Standard Operating Procedures. The groundwater sample from MW004 will be analyzed for the presence of volatile organic halocarbons by EPA Method 8260.

Following receipt of analytical data, GHD will submit an email summary with field notes and laboratory analytical results.

Subtask 3: Groundwater Sampling The second sampling event will be conducted in October 2022. Groundwater sampling will be conducted at monitor well MW004. Prior to sampling, depth to water measurements will be gathered at MW004 only. Groundwater sampling will be conducted in general accordance with FDEP Standard Operating Procedures. The groundwater sample from MW004 will be analyzed for the presence of volatile organic halocarbons by EPA Method 8260.

Upon receipt of analytical data, a summary report will be prepared. The summary report will include a detail of field sampling methodology along with field and laboratory results. The report will include summary tables and figures depicting groundwater analytical data. The report will also include recommendations for additional testing and/or monitoring.

Deliverables:

Deliverable Deliverable Due Date Field Notes and Analytical Data 5/20/22

Groundwater Monitoring Summary Letter 12/8/22

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/29/22 Mon 4/11/22

2 Subtask 1: Project Management

173 days Tue 4/12/22 Thu 12/8/22

3 Subtask 2: Groundwater Sampling

29 days Tue 4/12/22 Fri 5/20/22

4 Field Work Preparation 2 wks Tue 4/12/22 Mon 4/25/22

5 Groundwater Sampling 1 day Tue 4/26/22 Tue 4/26/22

6 Email Summary 3 wks Mon 5/2/22 Fri 5/20/22

7 Subtask 3: Groundwater Sampling

42 days Wed 10/12/22

Thu 12/8/22

8 Field Work Preparation 2 wks Wed 10/12/22Tue 10/25/22

9 Groundwater Sampling 1 wk Wed 10/26/22Tue 11/1/22

10 Groundwater Sampling Summary Letter

4 wks Fri 11/11/22 Thu 12/8/22

Jenna Martin

Thomas Cozz

3/20 3/27 4/3 4/10 4/17 4/24 5/1 April May

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC008A at the Prime Cleaners facility located in Margate, Broward County

Project: TA_008A Date: Tue 3/29/22

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/29/22 Mon 4/11/22

2 Subtask 1: Project Management

173 days Tue 4/12/22 Thu 12/8/22

3 Subtask 2: Groundwater Sampling

29 days Tue 4/12/22 Fri 5/20/22

4 Field Work Preparation 2 wks Tue 4/12/22 Mon 4/25/22

5 Groundwater Sampling 1 day Tue 4/26/22 Tue 4/26/22

6 Email Summary 3 wks Mon 5/2/22 Fri 5/20/22

7 Subtask 3: Groundwater Sampling

42 days Wed 10/12/22

Thu 12/8/22

8 Field Work Preparation 2 wks Wed 10/12/22Tue 10/25/22

9 Groundwater Sampling 1 wk Wed 10/26/22Tue 11/1/22

10 Groundwater Sampling Summary Letter

4 wks Fri 11/11/22 Thu 12/8/22 zie

Jenna Martin

5/8 5/15 5/22 5/29 6/5 6/12 6/19 June

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC008A at the Prime Cleaners facility located in Margate, Broward County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/29/22 Mon 4/11/22

2 Subtask 1: Project Management

173 days Tue 4/12/22 Thu 12/8/22

3 Subtask 2: Groundwater Sampling

29 days Tue 4/12/22 Fri 5/20/22

4 Field Work Preparation 2 wks Tue 4/12/22 Mon 4/25/22

5 Groundwater Sampling 1 day Tue 4/26/22 Tue 4/26/22

6 Email Summary 3 wks Mon 5/2/22 Fri 5/20/22

7 Subtask 3: Groundwater Sampling

42 days Wed 10/12/22

Thu 12/8/22

8 Field Work Preparation 2 wks Wed 10/12/22Tue 10/25/22

9 Groundwater Sampling 1 wk Wed 10/26/22Tue 11/1/22

10 Groundwater Sampling Summary Letter

4 wks Fri 11/11/22 Thu 12/8/22

6/26 7/3 7/10 7/17 7/24 7/31 8/7 July August

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC008A at the Prime Cleaners facility located in Margate, Broward County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/29/22 Mon 4/11/22

2 Subtask 1: Project Management

173 days Tue 4/12/22 Thu 12/8/22

3 Subtask 2: Groundwater Sampling

29 days Tue 4/12/22 Fri 5/20/22

4 Field Work Preparation 2 wks Tue 4/12/22 Mon 4/25/22

5 Groundwater Sampling 1 day Tue 4/26/22 Tue 4/26/22

6 Email Summary 3 wks Mon 5/2/22 Fri 5/20/22

7 Subtask 3: Groundwater Sampling

42 days Wed 10/12/22

Thu 12/8/22

8 Field Work Preparation 2 wks Wed 10/12/22Tue 10/25/22

9 Groundwater Sampling 1 wk Wed 10/26/22Tue 11/1/22

10 Groundwater Sampling Summary Letter

4 wks Fri 11/11/22 Thu 12/8/22

8/14 8/21 8/28 9/4 9/11 9/18 9/25 September O

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC008A at the Prime Cleaners facility located in Margate, Broward County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/29/22 Mon 4/11/22

2 Subtask 1: Project Management

173 days Tue 4/12/22 Thu 12/8/22

3 Subtask 2: Groundwater Sampling

29 days Tue 4/12/22 Fri 5/20/22

4 Field Work Preparation 2 wks Tue 4/12/22 Mon 4/25/22

5 Groundwater Sampling 1 day Tue 4/26/22 Tue 4/26/22

6 Email Summary 3 wks Mon 5/2/22 Fri 5/20/22

7 Subtask 3: Groundwater Sampling

42 days Wed 10/12/22

Thu 12/8/22

8 Field Work Preparation 2 wks Wed 10/12/22Tue 10/25/22

9 Groundwater Sampling 1 wk Wed 10/26/22Tue 11/1/22

10 Groundwater Sampling Summary Letter

4 wks Fri 11/11/22 Thu 12/8/22

Jenna Martin

Thomas Cozzie

10/2 10/9 10/16 10/23 10/30 11/6 11/13 October November

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC008A at the Prime Cleaners facility located in Margate, Broward County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Tue 3/29/22 Mon 4/11/22

2 Subtask 1: Project Management

173 days Tue 4/12/22 Thu 12/8/22

3 Subtask 2: Groundwater Sampling

29 days Tue 4/12/22 Fri 5/20/22

4 Field Work Preparation 2 wks Tue 4/12/22 Mon 4/25/22

5 Groundwater Sampling 1 day Tue 4/26/22 Tue 4/26/22

6 Email Summary 3 wks Mon 5/2/22 Fri 5/20/22

7 Subtask 3: Groundwater Sampling

42 days Wed 10/12/22

Thu 12/8/22

8 Field Work Preparation 2 wks Wed 10/12/22Tue 10/25/22

9 Groundwater Sampling 1 wk Wed 10/26/22Tue 11/1/22

10 Groundwater Sampling Summary Letter

4 wks Fri 11/11/22 Thu 12/8/22 Jenna Martin,Peter McLean,Debra And

11/20 11/27 12/4 12/11 12/18 12/25 1/1 December January

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC008A at the Prime Cleaners facility located in Margate, Broward County