CN-370000-HW684-DC017B.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|HW684|68b160b8827755ddf560142dd2a41e53
Contract number
HW684
Issued by
Florida

About this file

This is a Task Assignment (TA) document DC017B entered into between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. The task assignment is authorized under Contract Number HW684 and involves groundwater sampling and monitoring services at the Terrace Cleaners site located at 8866 N 56th Street, Temple Terrace, Hillsborough County, Florida (Project Number ERIC_4728). The Department Project Manager is Kevin Kane, and the Contractor's Project Manager is Brian Moore. The task assignment was executed on June 9-10, 2023, with a completion date of November 10, 2023.

GHD Services, Inc. will conduct annual groundwater sampling and prepare a monitoring report in accordance with the scope of work and cost proposal submitted on May 15, 2023. The work consists of two subtasks: Subtask 1 involves project management calculated at 13% of direct labor costs, and Subtask 2 involves groundwater monitoring at six monitor wells (MW007, MW010, MW013, MW016, MW017, and MW018) with depth-to-water measurements at all ten available wells. Samples will be analyzed by a Florida-certified laboratory for volatile organic halocarbons using EPA Method 8260. The total task assignment value is $5,617.64 on a fixed unit rate basis, with the deliverable (Groundwater Monitoring Report and Project Management) due on August 10, 2023. Payment of the full $5,617.64 is contingent upon submittal and FDEP approval of the Groundwater Monitoring Report. Cost components include labor ($3,972.49), travel ($120.00), subcontractor services for IDW disposal ($121.00), laboratory analysis ($496.50), field expenses ($510.40), and a completion fee ($397.25).

View the file

Other files

File Type Posted
CN-370000-HW684-BIL02F.pdf PDF
CN-370000-HW684-BIL2CC03.pdf PDF
CN-370000-HW684-BIL2ECO1.pdf PDF
CN-370000-HW684-BIL2FCO1.pdf PDF
CN-370000-HW684-BIL2GCO1.pdf PDF
CN-370000-HW684-CSS02A.pdf PDF
CN-370000-HW684-CSS03B.pdf PDF
CN-370000-HW684-D033CCO1.pdf PDF
CN-370000-HW684-DC001A.pdf PDF
CN-370000-HW684-DC001F.pdf PDF
CN-370000-HW684-DC002B.pdf PDF
CN-370000-HW684-DC002C.pdf PDF
CN-370000-HW684-DC002D.pdf PDF
CN-370000-HW684-DC003D.pdf PDF
CN-370000-HW684-DC004D.pdf PDF
CN-370000-HW684-DC005A.pdf PDF
CN-370000-HW684-DC005D.pdf PDF
CN-370000-HW684-DC006B.pdf PDF
CN-370000-HW684-DC009C.pdf PDF
CN-370000-HW684-DC009D.pdf PDF
CN-370000-HW684-DC009E.pdf PDF
CN-370000-HW684-DC011A.pdf PDF
CN-370000-HW684-DC011C.pdf PDF
CN-370000-HW684-DC012D.pdf PDF
CN-370000-HW684-DC013B.pdf PDF
CN-370000-HW684-DC014D.pdf PDF
CN-370000-HW684-DC014F.pdf PDF
CN-370000-HW684-DC015A.pdf PDF
CN-370000-HW684-DC015C.pdf PDF
CN-370000-HW684-DC016B.pdf PDF
CN-370000-HW684-DC016C.pdf PDF
CN-370000-HW684-DC017C.pdf PDF
CN-370000-HW684-DC018C.pdf PDF
CN-370000-HW684-DC019C.pdf PDF
CN-370000-HW684-DC019D.pdf PDF
CN-370000-HW684-DC01ACO2.pdf PDF
CN-370000-HW684-DC020B.pdf PDF
CN-370000-HW684-DC025A.pdf PDF
CN-370000-HW684-DC026B.pdf PDF
CN-370000-HW684-DC026D.pdf PDF
CN-370000-HW684-DC027C.pdf PDF
CN-370000-HW684-DC028C.pdf PDF
CN-370000-HW684-DC029C.pdf PDF
CN-370000-HW684-DC031A.pdf PDF
CN-370000-HW684-DC034B.pdf PDF
CN-370000-HW684-DC03ACO1.pdf PDF
CN-370000-HW684-DC03CCO1.pdf PDF
CN-370000-HW684-DC03CCO2.pdf PDF
CN-370000-HW684-DC040A.pdf PDF
CN-370000-HW684-DC045B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection CONTRACTOR Department Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW684

DC017B Completion November 10, 2023

GHD Services, Inc. will conduct groundwater sampling at the Terrace Cleaners site located in Temple Terrace, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on May 15, 2023.

Kevin Kane 850-245-8971 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

GHD Services, Inc.

GHD Services, Inc.

Brian Moore 813-257-0658

ERIC_4728

8866 N 56th St, Temple Terrace, Hillsborough County

Terrace Cleaners

✔ $ 5,617.64

$ 5,617.64

Scope of Work

Brian Moore

Project Manager

Brian Moore Digitally signed by Brian Moore Date: 2023.06.10 06:29:34 -04'00'

Kelly Crain

Kelly Crain Digitally signed by Kelly Crain Date: 2023.06.09 15:57:27 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report + Project Management 08/10/2023

Subtasks 1 and 2: Upon submittal and FDEP approval of the Groundwater Monitoring Report + Project Management $ 5,617.64

$ 5,617.64

HW684

DC017B

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

TO: HW684 Contract File

FROM: Kevin Kane, Contract Manager

DATE: June 7, 2023

SUBJECT: Task Assignment DC017B

Terrace Cleaners

ERIC_4728

Monitoring

GHD Services, Inc. (GHD) will conduct annual groundwater sampling. Specific subtasks are detailed below:

Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.

Subtask 2: Groundwater Monitoring Groundwater sampling will be conducted at six (6) site monitor wells. Prior to sampling, depth-to-water measurements will be made at all available wells (10 total). Groundwater sampling will be conducted at wells MW007, MW010, MW013, MW016, MW017, and MW018. Sampling will be conducted in general accordance with FDEP Standard Operating Procedures. The groundwater samples will be for analyzed by a Florida-certified laboratory for the presence of volatile organic halocarbons (VOHs) by EPA Method 8260. Following receipt of analytical data, a summary report will be prepared.

The summary report will include a summary of field sampling procedures and analytical results. The report will also include recommendations for additional monitoring and/or remediation.

GHD and the FDEP confirmed on June 7, 2023, that an Access Agreement with the current real property owner of the aforementioned site has been executed.

This work will be conducted in line with the scope of work included with GHD’s proposal, received May 15, 2023. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is August 10, 2023, and the completion date for the task assignment is November 10, 2023.

The final cost total for Task Assignment DC017B is $5,617.64.

FDEP COST ESTIMATE

Contractor: GHD Services Inc.

Date: 6/7/2023

Task #: DC017B SubTask 1 Project Management SubTask 6

Site: Terrace Cleaners SubTask 2 Groundwater Monitoring SubTask 7

Activity/Phase: Groundwater Monitoring SubTask 3 SubTask 8

Project Manager: Brian Moore, PE SubTask 4 SubTask 9

SubTask 5 SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$44.81 Project Manager JM 3.81 3.81 $51.08 Sr Professional Engineer JH 2.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.28 Professional Engineer/Sc GE 17.00 17.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.53 Senior Technician SA 11.75 11.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.16 Administrative Assistant DA 5.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Total Hours 43.56 3.81 39.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Direct Labor $1,484.49 $170.78 $1,313.71 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 129.80% $1,926.87 $221.67 $1,705.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $561.13 $64.55 $496.58 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,972.49 $457.00 $3,515.49 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

IDW $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $11.00 $11.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $121.00 $121.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $438.00 $438.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $58.50 $58.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $496.50 $496.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $370.40 $370.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $510.40 $510.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $5,220.39 $457.00 $4,763.39 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $397.25 $45.70 $351.55 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $5,617.64 $502.70 $5,114.94 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Terrace Cleaners SUBTASK 2: Groundwater Monitoring

DATE: 6/7/2023

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr Professional Engineer JH Conclusions/Recommendations 2

Professional Geologists GE Contact Property Owner/Prepare field SOW 1 Professional Geologists GE Field work preparation 1 Professional Geologists GE Historical Summary 2 Professional Geologists GE Groundwater sampling methodology 1 Professional Geologists GE Profile IDW and coordinate disposal 1 Professional Geologists GE Field parameter summaries 2 Professional Geologists GE Groundwater Flow summary (shallow) 2 Professional Geologists GE Groundwater Well analytical summary (shallow/deep) 3 Professional Geologists GE Laboratory data validation 2 Professional Geologists GE Conclusions/Recommendations 2

Senior Technician SA Mob/demob (1 day) 1 Senior Technician SA Water Levels (10 wells total)) 1.75 Senior Technician SA Groundwater Sampling (6 wells) 9

11.75

Drafting Technician PM Water Level map (shallow zone only) 2 Drafting Technician PM Groundwater Analytical Results (shallow and deep) 2

Staff Assistants DA Field Data Entry (6 GW samples/10 WLs) 1 Staff Assistants DA Update summary tables (DP, WLs, parameter, analytical) 2 Staff Assistants DA Publish Report (generate pdf) 2

TOTAL LABOR 39.75

VEHICLE TYPE RATE UNIT USEAGE

Company Truck $120.00 day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

Erwin IDW Disposal $110 drum 1 $110.00

TOTAL $110.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

VOHs $73.00 6 $438.00 sample shipping (Two Day) small cooler $52.00 1 $52.00

Ice $6.50 1 $6.50

TOTAL LAB $496.50

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendable $40.00 day 1 $40.00

Groundwater Sampling Kit $290.00 Day 1 $290.00 Poly Tubing $0.30 ft 208 $62.40 silicon Tubing $3.00 ft 6 $18.00

Drum $100.00 drum 1 $100.00

TOTAL EQUIPMENT $510.40

FINAL --7/24/96

COST PROPOSAL FOR TASK DC017B

Terrace Cleaners, ERIC_4728

Groundwater Monitoring

1. INTRODUCTION:

Although site redevelopment activities began several years ago, during the past seven years, site redevelopment has been stalled. The developer completed demolished the former strip center, and the southern portion of the property was renovated. In addition, Interim Source Removal (ISR) activities were undertaken that included the excavation and off-site disposal of PCE-impacted soils. Currently, the location of the former drycleaner is grass and asphalt covered; however, construction activities are occurring immediately north of the site. The site is currently being utilized for the storage of construction materials. In 2016, GHD oversaw the installation of replacement monitor wells on-site. The previous monitoring report (July 2022) recommended continued annual groundwater monitoring and DEP approved the recommendation on August 11, 2022. Task DC017B includes annual monitoring.

Subtask 1: Project Management Subtask 1 includes all activities associated with project management of sampling of site monitoring wells, and report preparation.

Subtask 2: Groundwater Sampling Groundwater sampling will be conducted at six (6) site monitor wells. Prior to sampling, depth-to-water measurements will be made at all available wells (10 total). Groundwater sampling will be conducted at wells MW007, MW010, MW013, MW016, MW017, and MW018. Sampling will be conducted in general accordance with FDEP Standard Operating Procedures. The groundwater samples will be for analyzed by a Florida-certified laboratory for the presence of volatile organic halocarbons (VOHs) by EPA Method 8260.

Following receipt of analytical data, a summary report will be prepared. The summary report will include a summary of field sampling procedures and analytical results. The report will also include recommendations for additional monitoring and/or remediation.

Deliverables:

Deliverable Deliverable Due Date

Groundwater Monitoring Report 8/10/23

408 Ditmar Street

Pensacola, FL 32503

ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562

(850) 292-6511

To: Mr. Brian Moore

GHD

5904 Hampton Oaks Parkway – Suite F

Tampa, FL 33610

May 23, 2022

Re: Transportation and Disposal of Non-Hazardous Soil and Water – Florida

Mr. Moore:

The price for disposal of drums of non-hazardous soil or groundwater located in the State of Florida will be $110.00 per drum, for both transportation and disposal.

This pricing is valid for all regions in the State of Florida except for the Florida Keys.

Pricing for sites located in the Florida Keys will be bid on a case-by-case basis dependent on the volume of drums and the location.

This quote is valid for 180 days.

Respectfully, Jonathan Erwin

Erwin Remediation, Inc.

Email: ErwinRemediation@Gmail.com

Office: (850) 292-6511 mailto:Remediation@Gmail.com

6/28/22, 10:23 AM Clark Environmental Inc.: Quote Builder quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 1/2

Quote Number: 19644

QUOTE

QUOTED TO: Brian Moore

QUOTE DATE: 1/1/2022

COMPANY NAME: GHD - 2022 QUOTED BY: Craig Burns

PHONE NUMBER:

Ext.

FAX NUMBER:

PROJECT REFERENCE: Drum Trans & Disposal for non-haz materials - Petro, Dry Cleaner & PFAS

CUSTOMER PO:

CONTACT EMAIL:

SITE ADDRESS: TBD

CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE FOLLOWING

COST ESTIMATE FOR

THE SITE/ PROJECT LISTED ABOVE.

DESCRIPTION PRICE QTY. UNIT TOTAL

NON HAZ DRUM DISPOSAL**Soils, Solids, Sludges** $80.00 DRUM $0.00

NON HAZ DRUM DISPOSAL**Liquids, PPE, Pads/Rags** $60.00 DRUM $0.00

TRANSPORTATION: 0-100 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site

$30.00 DRUM $0.00

TRANSPORTATION: 101-250 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site

$40.00 DRUM $0.00

TRANSPORTATION: 251-400 miles from CLARK Mulberry FL <11 drums/site - surcharge of $200/site

$50.00 DRUM $0.00

Totes T&D is available. CLARK can also deliver new drums to each site if needed :$40 + tax

$0.00 . $0.00

HAZ Drums to be quoted case-by-case $0.00 . $0.00

OPTIONAL LINE ITEMS

***10% FSC applied to the total cost of the invoice*** $0.00 . $0.00

TOTAL REQUIRED ITEMS $0.00

TOTAL OPTIONAL ITEMS $0.00

GRAND TOTAL $0.00

NOTES: Rates apply for FL. Labs and profiles must be approved prior to pick ups.

**Petro Sites required: TCLP 4 metals & TCLP Benzene**Dry Cleaner Sites require 8260 VOH's** Craig Burns

863.327.6289 - cburns@clarkenv.com

This quote will remain valid for 2022 and based on payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.

quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 2/2

Name (print) Title

Signature Date

CLARK ENVIRONMENTAL, INC. * 755 Prairie Industrial Pkwy. * Mulberry, Florida 33860 Telephone: 863-425-4884 * Fax: 863-425-2854

WWW.ClarkEnvironmental.com

From: Craig Burns To: Brian Moore Subject: GHD_IDW Drum Rates FL Date: Tuesday, June 28, 2022 10:26:46 AM Attachments: image001.png image002.png image003.png image004.png image005.png GHD Drum Rates FL 2022.pdf

Here you go Brian. I do this for a lot of engineering/consulting firms.

Be aware of the low stop less than 6 drums at $50/flat Be aware of the 10% to the total cost for FSC (implemented April 15).

Pass around the GHD Florida offices

From: Brian Moore <Brian.Moore@ghd.com> Sent: Tuesday, June 28, 2022 10:05 AM To: Craig Burns <cburns@clarkenvironmental.com> Subject: IDW Drums

Craig, Is it possible to provide a generic quote for IDW water disposal.

Assumption is non-haz with necessary analytical Maybe provide a range of locations

South florida or central florida, or both?

Thanks in advance

We have many sites that we generate 1 gw drum of IDW and would like to streamline the vendor coordination

BRIAN MOORE PE

GHD

Proudly employee owned | ghd.com 5904 Hampton Oaks Parkway Suite F Tampa FL 33610 USA O 813 971 3882 D 813 257 0658 M 813 335 2147 E brian.moore@ghd.com

The Power of Commitment

Connect

Please consider our environment before printing this email

CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please mailto:cburns@clarkenvironmental.com mailto:Brian.Moore@ghd.com https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttp-253A-252F-252Fwww.ghd.com-252F-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093857306-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3DorO8Q-252BVqTyo6Ej-252F8ZwSbVyQzLpZtJywYELQonaQNZfo-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3DsMxOUn-szAtJTATQBUgjjDdI6e6b1jo5alN-ez9vKSM%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=K3MyGMhP6XEk1ApT%2FRIPjGR%2BUFJFG9ahCVCi8Z9R1n0%3D&reserved=0 mailto:brian.moore@ghd.com https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Fwww.linkedin.com-252Fcompany-252Fghd-252F-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093857306-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3D5HB99sCNyHUdh3ySqo-252BMbX9lHf94JW-252BuI1gRPH6qLGY-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3DBQdX3FW3jjZZNHH7wbXXUS30LUnS3GtU1HJ8G56Snwo%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=%2BQlcPM%2FGtFT%2FrIbbuGi0PnSgurtBD8yqWgV1hvkvk00%3D&reserved=0 https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Fwww.facebook.com-252FGHDGroup-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093867263-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3DKXDgOYLYSf-252BwLLtpvQNMpyPzR3DV5-252FDBogAW3HWif9Y-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3DdHZdva6F1f6cSXNf7WLXU9x5VBxbTV01G78hKDk-cSA%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=142JKLTMfwfz%2FAO%2FXHrz%2FUodXSRzYWWBygfbg7vBIWs%3D&reserved=0 https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Ftwitter.com-252FGHDspeaks-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093877221-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3Duwh4lLmvdNCQkyPoUgiL7r2l9-252BmFgEv2JbZPLM3ptM0-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3D6FLD5pJDe4zG94aUPcPkIB9mx5JTMUxrAOX-fjV9l3o%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=O7BUsLKToxyyPXzZcLcBA1z3Q7%2FKvVsiCNGMGHOzln0%3D&reserved=0 https://aus01.safelinks.protection.outlook.com/?url=https%3A%2F%2Furldefense.proofpoint.com%2Fv2%2Furl%3Fu%3Dhttps-3A__aus01.safelinks.protection.outlook.com_-3Furl-3Dhttps-253A-252F-252Fwww.youtube.com-252Fchannel-252FUCwUGfe6zgaddIXqA7entIwQ-26data-3D04-257C01-257CBrian.Moore-2540ghd.com-257Cfa117ac0b4ea478d385e08d89e2a2290-257C5e4e864c3b824180a5155c8fb718fff8-257C0-257C0-257C637433251093877221-257CUnknown-257CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0-253D-257C1000-26sdata-3DVTPo9BdB-252FyUkff7ZLoE6J99Jt9f-252Fvtuta-252Fsm1KEOuNc-253D-26reserved-3D0%26d%3DDwMFAg%26c%3DeuGZstcaTDllvimEN8b7jXrwqOf-v5A_CdpgnVfiiMM%26r%3Dhv7dluAS8UQz_IXXEGLvDVzJ2x4J8uCkF4c8FXTHlTQ%26m%3DJpAZt4T_rnkT_pB7eSktTYyhW2NA_zzo1v0y7ygI9EI%26s%3D9S3nI6ai6gtzPu1y34Kb_OuqwixCpq0TgIkmYlOz0gk%26e%3D&data=05%7C01%7CBrian.Moore%40ghd.com%7Caf4f3d316c0e40f0573508da59122c8b%7C5e4e864c3b824180a5155c8fb718fff8%7C0%7C0%7C637920232054565445%7CUnknown%7CTWFpbGZsb3d8eyJWIjoiMC4wLjAwMDAiLCJQIjoiV2luMzIiLCJBTiI6Ik1haWwiLCJXVCI6Mn0%3D%7C3000%7C%7C%7C&sdata=YX45%2BiFGXo7axCd4VDmEIFdcmHajQE6n8KvktA7llOs%3D&reserved=0 quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 1/2

Quote Number: 19644

QUOTE

QUOTED TO: Brian Moore

QUOTE DATE: 1/1/2022

COMPANY NAME: GHD - 2022 QUOTED BY: Craig Burns

PHONE NUMBER:

Ext.

FAX NUMBER:

PROJECT REFERENCE: Drum Trans & Disposal for non-haz materials - Petro, Dry Cleaner & PFAS

CUSTOMER PO:

CONTACT EMAIL:

SITE ADDRESS: TBD

CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE FOLLOWING

COST ESTIMATE FOR

THE SITE/ PROJECT LISTED ABOVE.

DESCRIPTION PRICE QTY. UNIT TOTAL

NON HAZ DRUM DISPOSAL**Soils, Solids, Sludges** $80.00 DRUM $0.00

NON HAZ DRUM DISPOSAL**Liquids, PPE, Pads/Rags** $60.00 DRUM $0.00

TRANSPORTATION: 0-100 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site

$30.00 DRUM $0.00

TRANSPORTATION: 101-250 miles from CLARK Mulberry FL <6 drums/site - surcharge of $50/site

$40.00 DRUM $0.00

TRANSPORTATION: 251-400 miles from CLARK Mulberry FL <11 drums/site - surcharge of $200/site

$50.00 DRUM $0.00

Totes T&D is available. CLARK can also deliver new drums to each site if needed :$40 + tax

$0.00 . $0.00

HAZ Drums to be quoted case-by-case $0.00 . $0.00

OPTIONAL LINE ITEMS

***10% FSC applied to the total cost of the invoice*** $0.00 . $0.00

TOTAL REQUIRED ITEMS $0.00

TOTAL OPTIONAL ITEMS $0.00

GRAND TOTAL $0.00

NOTES: Rates apply for FL. Labs and profiles must be approved prior to pick ups.

**Petro Sites required: TCLP 4 metals & TCLP Benzene**Dry Cleaner Sites require 8260 VOH's** Craig Burns

863.327.6289 - cburns@clarkenv.com

This quote will remain valid for 2022 and based on payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.

quote.clarkenvironmental.com/Quotes/ViewQuote?quoteId=19644 2/2

Name (print) Title

Signature Date

CLARK ENVIRONMENTAL, INC. * 755 Prairie Industrial Pkwy. * Mulberry, Florida 33860 Telephone: 863-425-4884 * Fax: 863-425-2854

WWW.ClarkEnvironmental.com delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.

Whatever Waste, LLC 3834 Mandarin Woods Dr. No.

Jacksonville, Florida 32223 United States 904.881.1957

Brian Moore PE

GHD

5904 Hampton Road Parkway Suite F Tampa, FL 33610

Estimate Number 062922.1

Notes Dry Cleaner Site Locations: Central and South Florida Regions excluding Florida Keys Required analytical data for non-haz disposal acceptance would be VOCs and includes waste profiling assistance if the IDW-GW drums don't fall under a blanket waste profile DOT shippable drums must be on a hard surface at each accessible location

Terms Non-hazardous IDW drum pickup, transport and disposal pricing is based on per service event No-load drum fee if unable to pickup drums on any site in Central FL is $150; in South FL is $200 Pricing is valid or subject to change on a monthly basis in part due to escalating fuel prices Payment required within 45 days after email receipt of invoice

Indemnification: Each party agrees to indemnify, defend and hold harmless each other for and from any loss

Estimate Date 06/29/2022

Description Rate Qty Line Total

IDW-GW Drum Transport & Disposal - Central FL Sites

(1) Regional Stop Fee $600 - then $150 per 55-gal drum < 10 drums

$150.00 1 $150.00

IDW-GW Drum Transport & Disposal - Central FL Sites

(1) Regional Stop Fee $300 - then $150 per 55-gal drum > 10 drums

$150.00 1 $150.00

IDW-GW Drum Transport & Disposal - South FL Sites

(1) Regional Stop Fee $850 - then $200 per 55-gal drum < 10 drums

$200.00 1 $200.00

IDW-GW Drum Transport & Disposal - South FL Sites

(1) Regional Stop Fee $425 - then $200 per 55-gal drum > 10 drums

$200.00 1 $200.00

Subtotal

Tax

700.00

0.00

Estimate Total (USD) $700.00 or liability arising out of the party's breach of this agreement, scope of work, except for gross negligence, willful misconduct or bad faith.

ID Task Mode

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 5/15/23Fri 5/26/23

2 Subtask 1: Project Management

54 days Mon 5/29/23

Thu 8/10/23

3 Subtask 2:

Groundwater Monitoring

54 days Mon 5/29/23

Thu 8/10/23

4 Field Work Preparation3 wks Mon 5/29/23Fri 6/16/23

5 Groundwater Sampling1 day Tue 6/20/23 Tue 6/20/23

6 Groundwater Monitoring Report

6 wks Fri 6/30/23 Thu 8/10/23

5/7 5/14 5/21 5/28 June

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC017B at the Terrace Cleaners facility located in Temple Terrace, Hillsborough County

Project: TA_014B Date: Mon 5/15/23

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 5/15/23Fri 5/26/23

2 Subtask 1: Project Management

54 days Mon 5/29/23

Thu 8/10/23

3 Subtask 2:

Groundwater Monitoring

54 days Mon 5/29/23

Thu 8/10/23

4 Field Work Preparation3 wks Mon 5/29/23Fri 6/16/23

5 Groundwater Sampling1 day Tue 6/20/23 Tue 6/20/23

6 Groundwater Monitoring Report

6 wks Fri 6/30/23 Thu 8/10/23

Gabrielle Enos

Skylar Albritton

6/4 6/11 6/18 6/25 Jul

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC017B at the Terrace Cleaners facility located in Temple Terrace, Hillsborough County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 5/15/23Fri 5/26/23

2 Subtask 1: Project Management

54 days Mon 5/29/23

Thu 8/10/23

3 Subtask 2:

Groundwater Monitoring

54 days Mon 5/29/23

Thu 8/10/23

4 Field Work Preparation3 wks Mon 5/29/23Fri 6/16/23

5 Groundwater Sampling1 day Tue 6/20/23 Tue 6/20/23

6 Groundwater Monitoring Report

6 wks Fri 6/30/23 Thu 8/10/23

7/2 7/9 7/16 7/23 y

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC017B at the Terrace Cleaners facility located in Temple Terrace, Hillsborough County

Task Name Duration Start Finish

1 LOE Submittal/Approval 2 wks Mon 5/15/23Fri 5/26/23

2 Subtask 1: Project Management

54 days Mon 5/29/23

Thu 8/10/23

3 Subtask 2:

Groundwater Monitoring

54 days Mon 5/29/23

Thu 8/10/23

4 Field Work Preparation3 wks Mon 5/29/23Fri 6/16/23

5 Groundwater Sampling1 day Tue 6/20/23 Tue 6/20/23

6 Groundwater Monitoring Report

6 wks Fri 6/30/23 Thu 8/10/23 Jeremy Hess,Gabrielle Enos,Peter McL

7/30 8/6 8/13 8/20 August

Task

Split

Milestone

Summary

Project Summary

Inactive Task

Inactive Milestone

Inactive Summary

Manual Task

Duration-only

Manual Summary Rollup

Manual Summary

Start-only

Finish-only

External Tasks

External Milestone

Deadline

Progress

Manual Progress

Schedule for the Implementation of Task DC017B at the Terrace Cleaners facility located in Temple Terrace, Hillsborough County

File details come from the government source that posted it. Updated .