This is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) under Contract Number HW684. The task assignment is designated DC019B and involves GHD Services, Inc., a contractor, with Brian Moore serving as the contractor's project manager and Nicole Knutson as the FDEP project manager. The work will be performed at West Side Cleaners (formerly Total Valet & Wardrobe Services) located at 5036 W Colonial Drive, Orlando, Orange County, Florida, under Project Number ERIC_5025.
The task assignment requires GHD Services, Inc. to perform groundwater monitoring activities at the West Side Cleaners site, with a total task value of $6,332.89 on a fixed unit rate basis. The scope of work encompasses two subtasks: Project Management (Subtask 1) and Groundwater Monitoring (Subtask 2). Subtask 2 includes annual groundwater sampling from 31 monitor wells, with passive diffusion bag sampling at seven wells and conventional sampling methods at two additional wells, followed by laboratory analysis using EPA Method 8260 for volatile organic halocarbons. The primary deliverable is a Groundwater Monitoring Report with conclusions and recommendations, due January 30, 2024, with a task completion date of April 1, 2024. Cost breakdowns include direct labor ($1,571.95), overhead and fringe benefits ($2,634.59), laboratory analytical costs ($657.00), field equipment and expenses ($714.70), vehicle rental ($120.00), and subcontractor costs for IDW disposal ($137.50), totaling $6,332.89. Erwin Remediation was selected as the subcontractor for IDW transportation and disposal services.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC019B Completion April 1, 2024
GHD Services, Inc. will perform groundwater monitoring activates at West Side Cleaners.
Nicole Knutson 850-245-8763 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore 813 257 0658
ERIC_5025
5036 W Colonial Dr Orlando, Orange County
West Side Cleaners (Former Total Valet & Wardrobe Services)
✔ $ 6,332.89
$ 6,332.89
Scope of Work
Brian Moore Digitally signed by Brian Moore Date: 2023.11.16 22:07:10 -05'00' Kelly Crain Digitally signed by Kelly Crain
Date: 2023.11.15 10:27:09 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Report & PM - Subtasks 1 & 2 01/30/2024
FDEP Approval of Groundwater Monitoring Report & PM - Subtasks 1 & 2 $ 6,332.89
$ 6,332.89
HW684
DC019B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: ERIC_5025
West Side Cleaners
FROM: Nicole Knutson, Project Manager
SUBJECT: Negotiation Summary
HW684 DC019B
DATE: November 7, 2023
GHD Services, Inc. will perform groundwater monitoring activities at West Side Cleaners (Former Total Valet & Wardrobe Services), as detailed in the November 6, 2023 proposal. Erwin Remediation will perform IDW transportation and disposal services.
Total task amount is $6,332.89. GHD’s time, labor, and subcontractor costs for these activities have been reviewed and are appropriate. The level-of-effort and cost estimate are reasonable for the scope of services. Final deliverable due date is January 30, 2024.
Task completion date is April 1, 2024.
FDEP COST ESTI MATEContractor: GHD Services Inc.
Date: 11/7/2023
Task #: DC019B SubTask 1 Project Management SubTask 6
Site: West Side Cleaners SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$49.53 Project Manager JM 3.65 3.65 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$56.19 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$45.07 Professional Engineer/Sc GE 14.00 14.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.28 Project Engineer/Scientis CH 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $49.53 Project Manager/ Enginee JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $31.78 Staff Engineer/Scientist JW 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.21 Senior Technician SA 11.50 11.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $26.63 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.55 Senior Technician DC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.21 Junior Technician WO 11.50 11.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.00 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $21.63 Administrative Assistant JJ 4.50 4.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 50.15 3.65 46.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,571.95 $180.84 $1,391.11 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $2,040.39 $234.73 $1,805.66 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $594.20 $68.36 $525.84 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $4,206.54 $483.93 $3,722.61 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
FDEP COST ESTI MATEContractor: GHD Services Inc.
Date: 11/7/2023
Task #: DC019B SubTask 1 Project Management SubTask 6
Site: West Side Cleaners SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Travel
Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $125.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $125.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $12.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $137.50 $137.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $657.00 $657.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $76.50 $76.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $733.50 $733.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $574.70 $574.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $714.70 $714.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $5,912.24 $483.93 $5,428.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $420.65 $48.39 $372.26 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $6,332.89 $532.32 $5,800.57 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $6,332.89 Auto-Calculated
Final Total Cost: $6,332.89 Auto-Calculated
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : West Side Cleaners SUBTASK 2: Groundwater Monitoring
DATE: 11/7/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer JH Conclusions and Recommendations 1
Professional Geologist GE Update HASP 1 Professional Geologist GE Field Work Preparation 1 Professional Geologist GE Coordinate IDW Disposal 1 Professional Geologist GE Site Assessment/Remediation Background 1 Professional Geologist GE Groundwater Sampling Scope of Work 1.5 Professional Geologist GE Groundwater Field Parameter Summary 1.5 Professional Geologist GE Water Level evaluation (shallow / deep) 2 Professional Geologist GE Groundwater analytical results evaluation (shallow / deep) 3 Professional Geologist GE Laboratory Validation 1 Professional Geologist GE Conclusion and Recommendations 1
Senior Technician SA Mob/Demob (from Tampa) 4 Senior Technician SA Water Levels (all wells - 31 total) 2.5 Senior Technician SA Sample 1 well 1.5 Senior Technician SA Sample diffusion bags (7 wells) - 30 min each 3.5
11.5
Junior Technician WO Mob/Demob (from Tampa) 4 Junior Technician WO Water Levels (all wells - 31 total) 2.5 Junior Technician WO Sample 1 well 1.5 Junior Technician WO Sample diffusion bags (7 wells) - 30 min each 3.5
11.5
CADD Design PM Groundwater elevation and flow (shallow/deep) 2 CADD Design PM Groundwater Analytical Maps (shallow/deep) 2
Staff Assistants JJ Data Entry (31 water levels/9 well samples) 2 Staff Assistants JJ Summary tables (elevation, analytical) 1.5 Staff Assistants JJ Publish Report/generate pdf 1
4.5
TOTAL LABOR 46.5
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin Remediation IDW Disposal $125.00 drum 1 $125.00
TOTAL $125.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
EPA method 8260 VOHs $73.00 9 $657.00 sample shipping (Two Day - large cooler) $70.00 1 $70.00
Ice $6.50 1 $6.50
TOTAL LAB $733.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 1 $40.00
Diffusion sampler each (small well) $36.00 each 7 $252.00 Groundwater Sampling Kit $290.00 day 1 $290.00 Poly Tubing $0.30 ft 89 $26.70 Silicon Tubing $3.00 ft 2 $6.00
Drum $100.00 drum 1 $100.00
TOTAL EQUIPMENT $714.70
FINAL --7/24/96
COST PROPOSAL FOR TASK DC019B
< West Side Cleaners, 489502256 ERIC_5025>
Groundwater Monitoring
1. INTRODUCTION:
A Soil Vapor Extraction (SVE) system was operated at the West Side Cleaners site until late 2015. At that time, the system was shutdown and soil confirmation sampling was conducted.
Since the drycleaner was still active and utilized PCE in its operation, continued system shutdown was recommended along with periodic groundwater monitoring. Task DC019B includes annual groundwater monitoring in accordance with GHD recommendations from the previous Monitoring Report (September 21, 2022) and Department approval dated November 15, 2022.
Subtask 1: Project Management Includes all tasks associated with project management for completion of groundwater sampling and reporting.
Subtask 2: Groundwater Monitoring Subtask 2 includes annual groundwater sampling. Prior to groundwater sampling, depth to water measurements will be gathered from all available site monitor wells (31 total). During a previous sampling in July 2019, GHD personnel installed passive diffusion bags (PDB) at select site monitor wells. As such, PDB sampling is proposed at seven (7) site monitor wells including MW014, MW018, MW021, MW023, MW024, MW026, and MW027. In addition to the use of existing PDBs, GHD will also sample monitoring wells MW019 and MW028 using conventional methods per FDEP recommendations. These wells do not contain diffusion bags.
All samples will be submitted to a Florida-certified laboratory and analyzed for the presence of volatile organic halocarbons by EPA Method 8260.
Upon receipt of analytical data, a summary report will be prepared. The summary report will include a detail of field sampling methodology, a summary of groundwater elevation data and flow interpretations, as well as a summary of groundwater analytical results. The report will also include conclusions and recommendations for additional monitoring and/or remedial activities.
Deliverables:
Deliverable Deliverable Due Date
Groundwater Monitoring Report 1/30/24
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_v2.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v1.pdf |
| Cost Estimate |
| Subtask 2 |
| Subtask 3 |
| Subtask 4 |
| Subtask 5 |
| Subtask 6 |
| 2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev1_12-12-22.pdf |
| Table 1 for SAWP |
| Monitoring Well Locations |
| Utility Locate Bids_Compiled.pdf |
| Geosyntec Utility-272_Geotek_1500 |
| Geoview Utility Quote_2000_COT FTF SIS |
| Tallahassee Fire Training Division_V1_Bloodhound_3700 |
| Drilling Bids_Compiled.pdf |
| PDS_Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (sonic) |
| Direct Push |
| City of Tallahassee Fire Training Site_GW Protection PFAS Free Water Estimate Email |
| Cascade_Geosyntec Consultants, Inc. - City of Tallahassee Fire Training Facility - PN221026-118844 |
| GW Protection_Geosyntec (T) 1022060 S.pdf |
| Invoice |
| Geosyntec, Tallahassee Fire Training Division, Tallahassee, FL (MOT).xlsx.pdf |
| Sheet1 |
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v1.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| COT FTF (ERIC_ 7413)_HW683 SOW_Supplemental Assessment_2022-12_txt_v2.pdf |
| Subtask 1 – Project Management |
| Subtask 2 – Site Assessment Work Plan, Health and Safety Plan, Access Agreements, and Source Water Sampling |
| Subtask 3 –Monitoring Well Installation |
| Right-of-Way Permitting |
| Utility Locate and Drilling Subcontractors |
| Monitoring Well Installation |
| Subtask 4 – Monitoring Well Sampling and Surveying |
| Laboratory Analysis |
| Trip Report |
| Subtask 5 – Investigation Derived Waste |
| Trip Report |
| Subtask 6 – Supplemental Site Assessment Report |
| Invoice and Deliverable Schedule: |
| ATTACHMENT A |
| ATTACHMENT B |
| ATTACHMENT C |
| ATTACHMENT D |
| ATTACHMENT E |
| ATTACHMENT F |
| Attachment A -COT FTF (ERIC_7413)_HW683 CEF-LOE_Supplemental Assessment_2022-12_v2.pdf |
| Cost Estimate |
| Subtask 2 |
| Subtask 3 |
| Subtask 4 |
| Subtask 5 |
| Subtask 6 |
| 2022-11_COT FTF Groundwater Assessment Rationale Table_Drilling_Rev2.pdf |
| Table 1 for SAWP |
| Monitoring Well Locations |
File details come from the government source that posted it. Updated .