CN-370000-HW684-BIL02B.pdf
PDF 1 MB Posted
- Contract number
- HW684
- Issued by
- Florida
About this file
This Task Assignment (TA BIL02B) is a contract between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. for environmental assessment services. The contract is entered into pursuant to Contract Number HW684 and operates under federal funding from the State & Tribal Response Program Bipartisan Infrastructure Law (BIL) cooperative agreement administered by FDEP on behalf of the U.S. Environmental Protection Agency (EPA). The project involves assessment activities at the Former Polk County Fertilizer site located at 0 Citrus Ave, Haines City, Polk County, Florida (Site ID ERIC_13343). Key personnel include Allison Hankins as the FDEP Project Manager and Brian Moore as the Contractor's Project Manager for GHD Services, Inc.
The scope of work consists of two subtasks: Subtask 1 addresses project management of QAPP preparation at a negotiated cost of $638.23, while Subtask 2 covers preparation of a Site-Specific Quality Assurance Project Plan (QAPP) at a cost of $4,909.45, for a total TA value of $5,547.68. The QAPP will include site background details, field sampling objectives, sampling plan with locations and testing rationale, laboratory analytical methods, field methods, and data validation approaches. The deliverable is due September 27, 2023, with a payment milestone upon completion of QAPP preparation and FDEP approval of the Site Specific QAPP/Project Management components. The services are conducted using federal funds from the BIL funding cooperative agreement, and labor costs reflect GHD's standard billing rates including overhead (129.80%), fringe benefits (37.80%), and a completion fee of $504.33.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
BIL02B Completion October 27, 2023
GHD Services, Inc. will prepare a Site-Specific Quality Assurance Project Plan (QAPP) in accordance with the cost proposal and Level of Effort (LOE) submitted on August 16, 2023.
Allison Hankins 850 245 8990 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore 813 971 3882
ERIC_13343
0 Citrus Ave, Haines City
Former Polk County Fertilizer
✔ $ 5,547.68
$ 5,547.68
Scope of Work
Brian Moore
Vice President
Brian Moore Digitally signed by Brian Moore Date: 2023.08.16 15:35:39 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2023.08.16 13:53:44 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Site-Specific QAPP, Project Management 09/27/2023
Upon completion of QAPP preparation and DEP approval of Site Specific QAPP/Project Management (Subtasks 1 & 2) $ 5,547.68
$ 5,547.68
HW684
BIL02B
www.FloridaDEP.gov
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: GHD Services Inc. HW684 Contract File
FROM: Allison Hankins, Contract Manager
DATE: August 16, 2023
SUBJECT: Negotiation Summary – BIL22, Task Assignment (TA) BIL02B
Former Polk County Fertilizer - Site ID # ERIC_13343 Site-Specific Quality Assurance Project Plan
This TA is for the preparation of a Site-Specific Quality Assurance Project Plan for activities at the Former Polk County Fertilizer site, located at 0 Citrus Ave, Haines City, Polk County. The services under this task are being conducted using federal funds from the State & Tribal Response Program Bipartisan Infrastructure Law (BIL) funding cooperative agreement that is administered by the Department on behalf of the U.S. Environmental Protection Agency (EPA).
Subtask 1: Project Management This subtask is a percentage of the overall project and has been negotiated as a contract rate. It includes project management, overhead, general, administrative, and fringe costs. The agreed upon cost of this subtask is $638.23.
Subtask 2: Preparation of a Site-Specific Quality Assurance Project Plan Workplan In accordance with an EPA directive, this subtask includes the completion of a Work Plan/Quality Assurance Project Plan (QAPP). The QAPP Workplan will include details regarding the site background, objectives of the field sampling, a sampling plan detailing locations and rationale for testing, laboratory analytical methods, field methods to be utilized, and the approach to data validation and use. The agreed upon cost of this subtask is $4,909.45.
Summary The Department’s SRP Contract Manager and GHD’s Contract Manager have both agreed to the scope of work and associated costs. The final cost associated with this TA is $5,547.68.
Documentation of these costs is included in the Cost Proposal/Level of Effort (CP/LOE) Form and CP/LOE narrative provided by GHD on August 16, 2023, and the TA Form for BIL02B prepared by the Department. The final deliverable for this TA must be received by the Department no later than September 27, 2023.
http://www.floridadep.gov/
FDEP COST ESTI MATEContractor: GHD Services Inc.
Date: 8/16/2023
Task #: BILA02B SubTask 1 Project Management SubTask 6
Site: former Polk Country Ferti SubTask 2 QAPP SubTask 7
Activity/Phase: Assessment SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$49.53 Project Manager JM 4.38 4.38 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$56.19 Sr Professional Engineer JH 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$45.07 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.11 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $49.53 Project Manager/ Engine JM 26.00 26.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $35.16 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.53 Senior Technician SA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $20.35 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $24.89 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.25 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.00 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 4.00 4.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.27 Administrative Assistant DA 2.00 2.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Total Hours 40.38 4.38 36.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,884.66 $216.82 $1,667.84 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $2,446.29 $281.43 $2,164.86 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $712.40 $81.96 $630.44 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $5,043.35 $580.21 $4,463.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
FDEP COST ESTI MATEContractor: GHD Services Inc.
Date: 8/16/2023
Task #: BILA02B SubTask 1 Project Management SubTask 6
Site: former Polk Country Ferti SubTask 2 QAPP SubTask 7
Activity/Phase: Assessment SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $5,043.35 $580.21 $4,463.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $504.33 $58.02 $446.31 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $5,547.68 $638.23 $4,909.45 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Cost from Prior CEF: Manual Entry Cost from Delta CEF; Manual Entry
Cost (Prior + Delta): $0.00 Auto-Calculated Rounding Error: $5,547.68 Auto-Calculated
Final Total Cost: $5,547.68 Auto-Calculated
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : former Polk County Fertilizer
SUBTASK 2: QAPP
DATE: 8/16/2023
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Professional Engineer JH Finalize QAPP 4
Project Manager JM Prepare QAPP 4 Project Manager JM Overview and Study objectives 4 Project Manager JM Sampling Locations and Rationale 6 Project Manager JM Data Generation and quality/handling 4 Project Manager JM Field Work Methods and Sampling Protocols 4 Project Manager JM Data Validation 4
Drafting Technician PM Prepare figures for QAPP 4
Administrative Assistant DA Finalize QAPP 2
TOTAL LABOR 36
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
FINAL --7/24/96
COST PROPOSAL FOR TASK BIL02B
<Former Polk County Fertilizer Site/FDEP ERIC_13343>
< Quality Assurance Project Plan >
1. INTRODUCTION: <DISCUSS SCOPE OF WORK, DATES >
GHD Services Inc. (GHD) is pleased to submit this proposal to prepare a Quality Assurance Project Plan (QAPP) prior to initiating field activities in accordance with our path forward recommendations for the referenced site located in Haines City, Polk County. Our proposed scope of work is included below.
Subtask 1: Project Management Subtask 1 includes all tasks associated with project management of the QAPP preparation for the Former Polk County Fertilizer Site.
Subtask 2: Site-Specific Quality Assurance Project Plan Prior to initiating field work associated with the Targeted Brownfield Assessment process a site-specific quality assurance project plan (QAPP) will be prepared. The QAPP will include details regarding the site background, objectives of the field sampling, a sampling plan detailing locations and rationale for testing, laboratory analytical methods, field methods to be utilized, and the approach to data validation and use. The QAPP will be submitted to the Department for review prior to initiating field activities.
Deliverables:
Deliverable Deliverable Due Date
QAPP 9/22/23
ID Task Mode
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 8/16/23Tue 8/29/23
2 Subtask 1: Project Management
18 days Wed 8/30/23
Fri 9/22/23
3 Subtask 2: QAPP Preparation
18 days Wed 8/30/23
Fri 9/22/23
4 Site Summary 1 wk Wed 8/30/23Tue 9/5/23
5 Sampling Plan 1 wk Wed 9/6/23 Tue 9/12/23
6 Field and Laboratory Methods
1 wk Wed 9/13/23
Tue 9/19/23
7 Reporting and Data Validation
3 days Wed 9/20/23
Fri 9/22/23
8/6 8/13 8/20
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task BIL02B at the former Polk County Fertilizer Site located in Haines City, Polk County
Project: TA_002B Date: Wed 8/16/23
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 8/16/23Tue 8/29/23
2 Subtask 1: Project Management
18 days Wed 8/30/23
Fri 9/22/23
3 Subtask 2: QAPP Preparation
18 days Wed 8/30/23
Fri 9/22/23
4 Site Summary 1 wk Wed 8/30/23Tue 9/5/23
5 Sampling Plan 1 wk Wed 9/6/23 Tue 9/12/23
6 Field and Laboratory Methods
1 wk Wed 9/13/23
Tue 9/19/23
7 Reporting and Data Validation
3 days Wed 9/20/23
Fri 9/22/23
Jenna Martin
Jenna Mart
8/27 9/3 9/10 September
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task BIL02B at the former Polk County Fertilizer Site located in Haines City, Polk County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 8/16/23Tue 8/29/23
2 Subtask 1: Project Management
18 days Wed 8/30/23
Fri 9/22/23
3 Subtask 2: QAPP Preparation
18 days Wed 8/30/23
Fri 9/22/23
4 Site Summary 1 wk Wed 8/30/23Tue 9/5/23
5 Sampling Plan 1 wk Wed 9/6/23 Tue 9/12/23
6 Field and Laboratory Methods
1 wk Wed 9/13/23
Tue 9/19/23
7 Reporting and Data Validation
3 days Wed 9/20/23
Fri 9/22/23 tin,Peter McLean
Jenna Martin
Jenna Martin,Jeremy Hess,Peter McLean,Debra
9/17 9/24 10/1 October
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task BIL02B at the former Polk County Fertilizer Site located in Haines City, Polk County
| Task Assignment Form_BIL02B |
| Negotiation Summary - PolkCountyFert |
| BILA2B_CORRECTED |
| Subtask 2 |
| Cost Estimate |
| TA_002B_Corrected |
| Schedule - TA_002B |
File details come from the government source that posted it. Updated .