Task Assignment Summary
This Task Assignment (DC015A) is a state contract between the Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. for environmental remediation services at the International Professional Dry Cleaners site located at 10420 NW 7th Ave, Miami, Miami-Dade County. The contract operates under the master contract number HW684 and was executed on May 5, 2022, with a completion date of October 7, 2022. The FDEP Project Manager is Kevin Kane, and GHD's Project Manager is Brian Moore. This task assignment represents a specific work order issued under an existing indefinite delivery contract vehicle.
The contract calls for GHD Services to conduct annual groundwater sampling and monitoring at the contaminated site, with a total fixed-price value of $5,256.30. The work is divided into two subtasks: Subtask 1 (Project Management) at $492.91 and Subtask 2 (Groundwater Monitoring) at $4,763.39. Groundwater sampling will be conducted at three monitoring wells (MW009, MW010, and MW018) with depth-to-water measurements from all 11 wells, using EPA Method 8260 for volatile organic halocarbon analysis. The primary deliverable is a Groundwater Monitoring Report due July 2, 2022, upon FDEP approval. The cost estimate includes direct labor ($1,455.56), overhead and fringe benefits ($2,439.53), laboratory analysis ($277.50), field equipment and supplies ($464.20), vehicle rental ($120.00), investigation-derived waste disposal ($100.00), and a completion fee ($389.51). No option periods or renewals are specified in the task assignment.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC015A Completion October 7, 2022
GHD Services, Inc. will conduct groundwater sampling at the International Professional Dry Cleaners site located in Miami, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on April 18, 2022.
Kevin Kane (850) 245-8971 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore (813) 257-0658
ERIC_4365
10420 NW 7th Ave, Miami, Miami-Dade County
International Professional Dry Cleaners
✔ $ 5,256.30
$ 5,256.30
Scope of Work
Brian Moore
Contract Manager
Brian Moore Digitally signed by Brian Moore Date: 2022.05.05 15:46:30 -04'00'
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.05.05 15:05:03 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Report + Project Management 07/02/2022
Subtasks 1 and 2: Upon submittal and FDEP approval of the Groundwater Monitoring Report + Project Management $ 5,256.30
$ 5,256.30
HW684
DC015A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
TO: HW684 Contract File
FROM: Kevin Kane, Contract Manager
DATE: May 5, 2022
SUBJECT: Task Assignment DC015A
International Professional Dry Cleaners
ERIC_4365
Monitoring
GHD Services, Inc. (GHD) will conduct annual groundwater sampling. Specific subtasks are detailed below:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2: Groundwater Monitoring Groundwater sampling will be conducted at three (3) monitoring wells including monitoring wells MW009, MW010, and MW018. During mobilization for sampling, depth to water measurements will be gathered from all wells (11 total). Groundwater sampling will be conducted in general accordance with FDEP SOPs. Samples will be submitted to a fixed laboratory for analysis for the presence of VOH’s by EPA Method 8260.
Following receipt of analytical data, a Groundwater Monitoring Report will be prepared.
The report will include a detail of field activities along with a summary of laboratory analytical data. The monitoring report will also include recommendations regarding additional monitoring.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Subcontractors for IDW disposal were chosen on a lowest-cost basis.
The Florida Department of Environmental Protection (FDEP) has a current and valid Site Access Agreement for this site, signed May 17, 2019.
This work will be conducted in line with the scope of work included with GHD’s proposal, received April 18, 2022. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is July 2, 2022, and the completion date for the task assignment is October 7, 2022.
The final cost total for Task Assignment DC015A is $5,256.30.
FDEP COST ESTI MATEContractor: GHD Services Inc.
Date: 05/04/22
Task #: DC015A SubTask 1 Project Management SubTask 6
Site: International Professiona SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$40.12 Project Manager JM 4.20 4.2 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$46.33 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$43.28 Professional Engineer/Sc GE 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 11.50 11.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 13.00 13.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 6.00 6.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 3.75 3.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 39.45 4.20 35.25 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,455.56 $167.45 $1,288.11 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $1,889.32 $217.35 $1,671.97 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $550.21 $63.30 $486.91 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,895.09 $448.10 $3,446.99 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 1
FDEP COST ESTI MATEContractor: GHD Services Inc.
Date: 05/04/22
Task #: DC015A SubTask 1 Project Management SubTask 6
Site: International Professiona SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $219.00 $219.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $58.50 $58.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $277.50 $277.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $424.20 $424.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $464.20 $464.20 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $4,866.79 $448.10 $4,418.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $389.51 $44.81 $344.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $5,256.30 $492.91 $4,763.39 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Iinternational Professional Cleaners SUBTASK 2: Groundwater Monitoring
DATE: 05/04/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr. Professional Engineer JH Conclusions/Recommendations 1
Project Manager JM Specify laboratory data deliverable/Sample Kit 1 Project Manager JM Field sampling SOW/coordinate site access 1 Project Manager JM Coordinate IDW disposal 1 Project Manager JM QA/QC field and laboratory data 1 Project Manager JM Project Background 1 Project Manager JM Groundwater Sampling Methods 1 Project Manager JM Groundwater flow evaluation (shallow, intermediate, deep) 2 Project Manager JM Water Quality Parameter Summary 1 Project Manager JM Groundwater Analtycial Results 2 Project Manager JM QA/QC Laboratory Data 1 Project Manager JM Conclusions/Recommendations 1
Project Engineer/Scientist TC Mob/demob (from Wellington) 4 Project Engineer/Scientist TC Water Levels (all wells - 21 total) 3 Project Engineer/Scientist TC Groundwater Sampling (3 wells) 4.5
11.5
Drafting Technician PM Prepare GW Flow maps (shallow, intermediate, deep) 4 Drafting Technician PM Prepare VOC plume figures with updated concentration data 2
Staff Assistant DA Data Entry (11 wls, and 3 monitor wells) 0.75 Staff Assistant DA Document Preparation/Publishing 2 Staff Assistant DA Update GIS/ADAPT 1
3.75
TOTAL LABOR 35.25
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00 $0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin IDW Disposal 1 drum $100.00 $100.00
TOTAL $100.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs EPA 8260 $73.00 3 $219.00 Sample Shipping Small Cooler (2 day) $52.00 1 $52.00
Ice $6.50 1 $6.50
TOTAL LAB $277.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Expendables $40.00 day 1 $40.00
Equipment (Analytical Related)
Groundwater Sampling Kit $290.00 day 1 $290.00 Poly Tubing (HDPE) $0.30 ft 84 $25.20 Silicon Tubing $3.00 ft 3 $9.00 55-gallon drum $100.00 drum 1 $100.00
Equipment (Other) $0.00
TOTAL EQUIPMENT $464.20
FINAL --7/24/96
COST PROPOSAL FOR TASK DC015A
<International Professional Cleaners, ERIC_4365 >
Groundwater Monitoring
1. INTRODUCTION:
Active remediation was conducted at this site between July 2004 and early 2016. Given the uncertainty associated with the location of any remaining subsurface contaminant mass and the variation in mass recovery rates through SVE, the value associated with continued system operations is unclear. As such, and based on recent discussions with the Department, system shutdown and periodic groundwater monitoring was recommended for the subject site. Given that the subject facility is currently actively drycleaning with PCE, periodic monitoring was recommended until drycleaning operations and/or the use of PCE is discontinued. Task DC015A includes annual groundwater monitoring in accordance with GHD recommendations and FDEP approval.
Subtask 1: Project Management Subtask 1 includes all activities associated with the completing annual groundwater sampling, analysis, and reporting for the International Professional Cleaners Site.
Subtask 2: Groundwater Monitoring
Groundwater sampling will be conducted in June 2022. Monitoring wells MW009, MW010, and MW018 will be sampled with volatile organic halocarbon (VOH) analysis using EPA Method 8260. During mobilization for sampling, depth to water measurements will be gathered from all wells (11 total). Groundwater sampling will be conducted in general accordance with FDEP SOPs.
Following groundwater sampling and receipt of analytical data, a summary report will be prepared. The summary report will include a description of field sampling methodology and analytical results. The report will also include recommendations regarding the next step toward site rehabilitation.
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
Groundwater Monitoring Report 7/2/22
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Brian Moore
GHD
5904 Hampton Oaks Parkway – Suite F
Tampa, FL 33610
March 16, 2020
Re: IP Cleaners - Miami, FL
Mr. Moore:
The price for disposal of two (2) drums of non-hazardous groundwater located in Miami, FL will be $100.00 per drum, or $200.00 total, for both transportation and disposal.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
From: Jamie Infinger To: Brian Moore Subject: RE: IP Cleaners - Miami Date: Monday, March 16, 2020 8:39:32 AM Attachments: image001.png image002.png image003.png image004.png
$95.00 per drum plus $150.00 stop charge Have a great day
Thanks, Jamie Infinger A Nationwide Waste Disposal Company Clean Management Environmental Group, Inc.
P: (800)-538-8131 F: (843)-538-7845 C: (912)-674-6783 jinfinger@cleanmanagement.com www.cleanmanagement.com
From: Brian.Moore@ghd.com [mailto:Brian.Moore@ghd.com] Sent: Sunday, March 15, 2020 11:45 AM To: Jamie Infinger <jinfinger@cleanmanagement.com> Subject: IP Cleaners - Miami
Jamie, Can you provide quote for disposal of 2 drums of water from the above site. Low level solvents, assume non-haz thanks
Brian Moore, PE
GHD
Proudly employee owned T: 813 257 0658 | M: 813 335 2147 | E: Brian.Moore@ghd.com 5904 Hampton Oaks Parkway Suite F Tampa Florida 33610 USA | www.ghd.com Connect
WATER | ENERGY & RESOURCES | ENVIRONMENT | PROPERTY & BUILDINGS | TRANSPORTATION
mailto:jinfinger@cleanmanagement.com mailto:Brian.Moore@ghd.com mailto:jinfinger@cleanmanagement.com http://www.cleanmanagement.com/ mailto:Brian.Moore@ghd.com http://www.ghd.com/ https://www.linkedin.com/company/ghd https://www.facebook.com/GHDGroup https://twitter.com/GHD_Namerica https://www.youtube.com/channel/UCwUGfe6zgaddIXqA7entIwQ https://www.ghd.com/en/sectors/water.aspx https://www.ghd.com/en/sectors/energy---resources.aspx https://www.ghd.com/en/sectors/environment.aspx https://www.ghd.com/en/sectors/property---buildings.aspx https://www.ghd.com/en/sectors/transportation.aspx
Please consider our environment before printing this email
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
This e-mail has been scanned for viruses
ID Task Mode
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Mon 4/18/22Fri 4/29/22
2 Subtask 1: Project Management
64 days Mon 5/2/22 Thu 7/28/22
3 Subtask 2: Groundwater Monitoring
48 days Tue 5/24/22 Thu 7/28/22
4 Field Work Preparation 2 wks Tue 5/24/22 Mon 6/6/22
5 Groundwater Sampling 1 day Wed 6/8/22 Wed 6/8/22
6 Groundwater Monitoring Report
6 wks Fri 6/17/22 Thu 7/28/22
4/10 4/17 4/24 5/1 5/8 May
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC015A at the International Professional Cleaners site located in Miami, Miami- Dade County
Project: TA_015A Date: Mon 4/18/22
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Mon 4/18/22Fri 4/29/22
2 Subtask 1: Project Management
64 days Mon 5/2/22 Thu 7/28/22
3 Subtask 2: Groundwater Monitoring
48 days Tue 5/24/22 Thu 7/28/22
4 Field Work Preparation 2 wks Tue 5/24/22 Mon 6/6/22
5 Groundwater Sampling 1 day Wed 6/8/22 Wed 6/8/22
6 Groundwater Monitoring Report
6 wks Fri 6/17/22 Thu 7/28/22
Jenna Martin
Thomas Cozzie
5/15 5/22 5/29 6/5 6/12 June
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC015A at the International Professional Cleaners site located in Miami, Miami- Dade County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Mon 4/18/22Fri 4/29/22
2 Subtask 1: Project Management
64 days Mon 5/2/22 Thu 7/28/22
3 Subtask 2: Groundwater Monitoring
48 days Tue 5/24/22 Thu 7/28/22
4 Field Work Preparation 2 wks Tue 5/24/22 Mon 6/6/22
5 Groundwater Sampling 1 day Wed 6/8/22 Wed 6/8/22
6 Groundwater Monitoring Report
6 wks Fri 6/17/22 Thu 7/28/22
6/19 6/26 7/3 7/10 7/17 July
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC015A at the International Professional Cleaners site located in Miami, Miami- Dade County
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Mon 4/18/22Fri 4/29/22
2 Subtask 1: Project Management
64 days Mon 5/2/22 Thu 7/28/22
3 Subtask 2: Groundwater Monitoring
48 days Tue 5/24/22 Thu 7/28/22
4 Field Work Preparation 2 wks Tue 5/24/22 Mon 6/6/22
5 Groundwater Sampling 1 day Wed 6/8/22 Wed 6/8/22
6 Groundwater Monitoring Report
6 wks Fri 6/17/22 Thu 7/28/22 Jeremy Hess,Jenna Martin,Peter McLean,Debra Andrew
7/24 7/31 8/7 8/14 8/21 August
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC015A at the International Professional Cleaners site located in Miami, Miami- Dade County
File details come from the government source that posted it. Updated .