This document is a Task Assignment Change Order (TACO No. 2) issued by the State of Florida Department of Environmental Protection (FDEP) to GHD Services, Inc. under Contract HW684 for work at the Former Polk County Fertilizer site (Site ID ERIC_13343). The change order amends the original Task Assignment BIL02E and incorporates two previously authorized Work Change Directives (WCD #1 and WCD #2) related to soil contamination assessment activities.
The change order increases the total Task Assignment value from $39,370.79 to $40,315.79, representing a net cost increase of $945.00. This increase results from adjustments across multiple subtasks: Subtask 3 (Soil Assessment Activities) showed a cost decrease of $550.00 due to five fewer PAH samples analyzed; Subtask 4 (WCD #1) added $315.00 for three additional dieldrin analyses; and Subtask 5 (WCD #2) added $1,180.00 for six additional dieldrin samples and five additional PAH samples. The Task Assignment completion date was extended from June 30, 2025, to September 19, 2025 (81 additional days). Deliverables include Analytical Data and Field Notes (due August 15, 2025) and an Interim Source Removal Plan with Project Management documentation (due August 15, 2025), with corresponding invoice payments of $25,506.16 and $14,809.63 respectively.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
BIL02E 2 HW684
This Task Assignment Change Order (TACO) settles Work Change Directives 1 and 2, which authorized step out boring analysis for dieldrin and PAH. This is being executed per the TACO request from GHD received on June 16, 2025.
Megan Johnson 850.245.8994 GHD Services, Inc.
Brian Moore 813.971.3882
ERIC_13343
Former Polk County Fertilizer
$ 40,315.79 $ 39,370.79
$ 40,315.79 $ 39,370.79
06/30/2025 09/19/2025 81
1 1 1
GHD Services, Inc.
Brian Moore, P.E.
Vice President
Brian Moore Digitally signed by Brian Moore Date: 2025.06.24 12:13:58 -04'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2025.06.24 10:35:25 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
Ron DeSantis Governor
Alexis A. Lambert Secretary
Memorandum
TO: GHD Services Inc. HW684 Contract File
FROM: Megan Johnson, Contract Manager
DATE: June 23, 2025
SUBJECT: Negotiation Summary – BIL22, Change Order #2 - TA BIL02E C2 Former Polk County Fertilizer - Site ID # ERIC_13343 ISR Plan and Assessment Activities
This Task Assignment Change Order (TACO) settles Work Change Directives #1 and #2, which authorized step out boring analysis for dieldrin and PAH and extends the Task Assignment completion date and deliverable due dates. Specific changes are detailed below:
Subtask 1: Project Management No changes associated with this subtask.
Subtask 2: Interim Source Removal Plan No changes associated with this subtask.
Subtask 3: Soil Assessment Activities There were five fewer samples analyzed for PAH than originally planned under this subtask resulting in a cost actual decrease of ($550.00).
Subtask 4: Work Change Directive #1 Under Work Change Directive #1, three additional samples were analyzed for dieldrin. This resulted in a cost actual increase of $315.00.
Subtask 5: Work Change Directive #2 Under Work Change Directive #2, six additional samples were analyzed for dieldrin, and five additional samples were analyzed for PAHs. This resulted in a cost actual increase of $1,180.00.
Summary The Department’s BIL Contract Manager and GHD’s Contract Manager have both agreed to the above changes. All changes noted above represent a total overall cost increase of $945.00, as shown in the Final LOE. The changes were noted in the TACO Request received from GHD on June 16, 2025. The final cost associated with this TA increased from $39,370.79 to $40,315.79.
Documentation of the changes is included in the attached TACO Request, the Delta LOE spreadsheet and the Final LOE spreadsheet, and the TACO form for BIL02E C2, prepared by the Department.
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Former Polk County Fertilizer Site SUBTASK 2: Design
DATE: 6/23/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer GK Statistical Analysis of existing data 6 Sr Professional Engineer GK Establish Cleanup Levels through Iterative Scenarios 6
Project Manager JM Soil and Groundwater Assessment Summary (ISRP) 12 Project Manager JM Remedial Alternative Evaluation 4 Project Manager JM Excavation Layout 4 Project Manager JM Volume calculations 4 Project Manager JM Access Considerations 4 Project Manager JM Dust Control 4 Project Manager JM Dust Monitoring 3 Project Manager JM Health and Safety Provisions 3 Project Manager JM Soil Characterization/Profiling 2 Project Manager JM Mointoring and Reporting 3 Project Manager JM Cost Estimate 4 Project Manager JM RAP Checklist 2 Project Manager JM Schedule 2
Drafting Technician KJ Assessment figures 6 Drafting Technician KJ Prepare Excavation Layouts 4
Staff Assistants JJ Document Preparation/Publishing/build pdf 3
TOTAL LABOR 76
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
FINAL --7/24/96
SITE : Former Polk County Fertilizer SUBTASK 3: Soil Sampling
DATE: 6/23/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager JM Contact Property Owner 4 Project Manager JM Field Work Preparation 4 Project Manager JM Evaluate Data and Determine need for additional analysis of contingency samples 8 Project Manager JM Data Summary 8
Sr Technician WM Mob/demob (6 days) 12 Sr Technician WM Locate/measure soil borings 4 Sr Technician WM Soil Borings (61 total - 1 hr per boring) 61
Sr Technician SA Mob/demob (6 days) 12 Sr Technician SA Locate/measure soil borings 4 Sr Technician SA Soil Borings (61 total - 1 hr per boring) 61
Staff Assistants JJ Data Entry and Summary Tables 4
TOTAL LABOR 182
VEHICLE TYPE RATE UNIT USEAGE
WM Company Truck $480.00 week 1 $480.00 WM Company Truck $120.00 day 1 $120.00 SA Company Truck $480.00 week 1 $480.00 SA Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $1,200.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
OCPs Soil EPA 8081 $105.00 32 $3,360.00 PAHs Soil EPA 8270 SIM $110.00 9 $990.00 Sample Shipping - soil overnight - large cooler $150.00 2 $300.00 Ice $6.50 2 $13.00
TOTAL LAB $4,663.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 6 $240.00
Soil Assessment Kit $700.00 week 1 $700.00 Soil Assessment Kit $175.00 day 1 $175.00
GPS (Trimble) $700.00 week 1 $700.00 GPS (Trimble) $175.00 day 1 $175.00
TOTAL EQUIPMENT $1,990.00
SUBTASK 4: WCD#1
DATE: 6/23/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
OCPs Soil EPA 8081 $105.00 3 $315.00
TOTAL LAB $315.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
SUBTASK 5: WCD#2
DATE: 6/23/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
OCPs Soil EPA 8081 $105.00 6 $630.00 PAHs Soil EPA 8270 SIM $110.00 5 $550.00
TOTAL LAB $630.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
SUBTASK 3: Soil Sampling
DATE: 6/23/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager JM Contact Property Owner 0 Project Manager JM Field Work Preparation 0 Project Manager JM Evaluate Data and Determine need for additional analysis of contingency samples 0 Project Manager JM Data Summary 0
Sr Technician WM Mob/demob (6 days) 0 Sr Technician WM Locate/measure soil borings 0 Sr Technician WM Soil Borings (61 total - 1 hr per boring) 0
Sr Technician SA Mob/demob (6 days) 0 Sr Technician SA Locate/measure soil borings 0 Sr Technician SA Soil Borings (61 total - 1 hr per boring) 0
Staff Assistants JJ Data Entry and Summary Tables 0
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
WM Company Truck $480.00 week 0 $0.00 WM Company Truck $120.00 day 0 $0.00 SA Company Truck $480.00 week 0 $0.00 SA Company Truck $120.00 day 0 $0.00
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
OCPs Soil EPA 8081 $105.00 0 $0.00 PAHs Soil EPA 8270 SIM $110.00 -5 ($550.00) Sample Shipping - soil overnight - large cooler $150.00 0 $0.00 Ice $6.50 0 $0.00
TOTAL LAB ($550.00)
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 0 $0.00
Soil Assessment Kit $700.00 week 0 $0.00 Soil Assessment Kit $175.00 day 0 $0.00
GPS (Trimble) $700.00 week 0 $0.00 GPS (Trimble) $175.00 day 0 $0.00
TOTAL EQUIPMENT $0.00
SUBTASK 4: WCD#1
DATE: 6/23/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
OCPs Soil EPA 8081 $105.00 3 $315.00
TOTAL LAB $315.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
SUBTASK 5: WCD#2
DATE: 6/23/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
TOTAL LABOR 0
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
OCPs Soil EPA 8081 $105.00 6 $630.00 PAHs Soil EPA 8270 SIM $110.00 5 $550.00
TOTAL LAB $630.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
SITE : Former Polk County Fertilizer Site SUBTASK 2: Design
DATE: 6/23/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer GK Statistical Analysis of existing data 6 Sr Professional Engineer GK Establish Cleanup Levels through Iterative Scenarios 6
Project Manager JM Soil and Groundwater Assessment Summary (ISRP) 12 Project Manager JM Remedial Alternative Evaluation 4 Project Manager JM Excavation Layout 4 Project Manager JM Volume calculations 4 Project Manager JM Access Considerations 4 Project Manager JM Dust Control 4 Project Manager JM Dust Monitoring 3 Project Manager JM Health and Safety Provisions 3 Project Manager JM Soil Characterization/Profiling 2 Project Manager JM Mointoring and Reporting 3 Project Manager JM Cost Estimate 4 Project Manager JM RAP Checklist 2 Project Manager JM Schedule 2
Drafting Technician KJ Assessment figures 6 Drafting Technician KJ Prepare Excavation Layouts 4
Staff Assistants JJ Document Preparation/Publishing/build pdf 3
TOTAL LABOR 76
VEHICLE TYPE RATE UNIT USEAGE
TOTAL VEHICLE $0.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
TOTAL EQUIPMENT $0.00
SUBTASK 3: Soil Sampling
DATE: 6/23/2025
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager JM Contact Property Owner 4 Project Manager JM Field Work Preparation 4 Project Manager JM Evaluate Data and Determine need for additional analysis of contingency samples 8 Project Manager JM Data Summary 8
Sr Technician WM Mob/demob (6 days) 12 Sr Technician WM Locate/measure soil borings 4 Sr Technician WM Soil Borings (61 total - 1 hr per boring) 61
Sr Technician SA Mob/demob (6 days) 12 Sr Technician SA Locate/measure soil borings 4 Sr Technician SA Soil Borings (61 total - 1 hr per boring) 61
Staff Assistants JJ Data Entry and Summary Tables 4
TOTAL LABOR 182
VEHICLE TYPE RATE UNIT USEAGE
WM Company Truck $480.00 week 1 $480.00 WM Company Truck $120.00 day 1 $120.00 SA Company Truck $480.00 week 1 $480.00 SA Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $1,200.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
TOTAL $0.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
OCPs Soil EPA 8081 $105.00 32 $3,360.00 PAHs Soil EPA 8270 SIM $110.00 14 $1,540.00 Sample Shipping - soil overnight - large cooler $150.00 2 $300.00 Ice $6.50 2 $13.00
TOTAL LAB $5,213.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 day 6 $240.00
Soil Assessment Kit $700.00 week 1 $700.00 Soil Assessment Kit $175.00 day 1 $175.00
GPS (Trimble) $700.00 week 1 $700.00 GPS (Trimble) $175.00 day 1 $175.00
TOTAL EQUIPMENT $1,990.00
Site Name: Site ID #:
Contract #: Contractor:
� Reason for Work Change Directive :
� Description of Work Change Directive :
� Attachments (if applicable, list documents supporting change):
� Costs (if negotiated unit costs, provide information below):
WCP WCD 07-2018
Authorized Contractor Signature:
Authorized FDEP Signature:
WORK CHANGE DIRECTIVE FORM
FDEP Supervisor Approval:
(if applicable)
Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.
Task Assignment #: Work Change Directive #:
Maximum Estimated Increase in Task Amount:
Former Polk County Fertilizer ERIC_
HW684 GHD Services Inc.
BIL02E 1
Soil dieldrin exceedances require analysis of step out borings
3 additional dieldrin analysi
3 dieldrin analysis $105 = $415
$ 500.00
Brian Moore Digitally signed by Brian Moore Date: 2025.05.06 17:56:51 -04'00'
Megan R. Johnson Digitally signed by Megan R.
Johnson Date: 2025.05.07 15:05:32 -04'00'
Scott L Sweeney
Digitally signed by Scott L Sweeney Date: 2025.05.08 07:18:54 -04'00'
Site Name: Site ID #:
Contract #: Contractor:
� Reason for Work Change Directive :
� Description of Work Change Directive :
� Attachments (if applicable, list documents supporting change):
� Costs (if negotiated unit costs, provide information below):
WCP WCD 07-2018
Authorized Contractor Signature:
Authorized FDEP Signature:
WORK CHANGE DIRECTIVE FORM
FDEP Supervisor Approval:
(if applicable)
Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.
Task Assignment #: Work Change Directive #:
Maximum Estimated Increase in Task Amount:
Former Polk County Fertilizer ERIC_
HW684 GHD Services Inc.
BIL02E 2
Additional IDW generated during well installation
Soil dieldrin exceedances require analysis of step out borings
6 dieldrin analysis $105 = $630 6 PAH analysis $110 = $660
$ 1,400.00
Brian Moore Digitally signed by Brian Moore Date: 2025.05.13 15:13:14 -04'00'
Megan R. Johnson Digitally signed by Megan R.
Johnson Date: 2025.05.13 15:46:14 -04'00'
Scott L Sweeney
Digitally signed by Scott L Sweeney Date: 2025.05.14 06:52:42 -04'00'
From: Brian Moore To: Johnson, Megan R Subject: RE: Polk County Fertilizer Site Date: Monday, June 16, 2025 4:33:56 PM Attachments: image001.png image002.png image003.png image004.png image005.png image006.png TA_002E Final CO1.xlsx TA_002E Delta CO2.xlsx TA_002E Final CO2.xlsx BIL02E WCD#1_DEP signed.pdf BIL02E WCD#2_DEP signed.pdf
EXTERNAL MESSAGE
This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.
Megan, A proposed change order to rectify WCD#1 and 2 and a sample # adjustment on Subtask 3
Please add 45 day extension for the ISRP to 8/15/25
Thank you
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department�s Project Manager: Department�s Project Manager Phone:
Contractor Name: (Contractor ) ntractor�st �s Project Manager: ontractor�s t�s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
BIL02E 1 HW684
This Task Assignment Change Order (TACO) authorizes additional soil sampling that is needed prior to writing the ISR Plan. This is being executed per the TACO request from GHD received on February 26, 2025.
Megan Johnson 850.245.8994 Contractor GHD Services, Inc. Contractor
Contractor Brian Moore Contractor 813.971.3882
ERIC_13343
Former Polk County Fertilizer
$ 39,370.79 $ 10,911.55
$ 39,370.79 $ 10,911.55
Completion Completion 05/02/2025 06/30/2025 59
1 1 1
GHD Services, Inc.
Contractor
Brian Moore, P.E.
Vice President
Brian Moore Digitally signed by Brian Moore Date: 2025.03.06 09:08:34 -05'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2025.03.03 16:35:03 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW684
BIL02E
$ 39,370.79
Analytical Data and Field Notes.
Interim Source Removal Plan; Project Management.
Department approval of Analytical Data and Field Notes (Subtask 3)
Department approval of Project Management and Interim Source Removal Plan (Subtasks 1 and 2)
05/05/2025
05/23/2025
$ 14,809.63
$ 24,561.16