This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S. Inc. for environmental remediation services at the former Prather's Laundry & Drycleaning site located at 1530 1st Street, Sarasota, Sarasota County, Florida. The TA is identified as DC026D under master Contract HW680 and is effective through June 12, 2026. The Department Project Manager is Theresa Pepe, and the Contractor's Project Manager is Gus Suarez.
The scope of work comprises four subtasks: (1) Project Management, (2) Annual Groundwater Monitoring for volatile organic compounds (VOHs) involving sampling of 13 wells using passive diffusion bags, (3) Reporting including a written Groundwater Monitoring Report with recommendations, and (4) PFAS sampling of two monitor wells using low-flow sampling techniques with analysis performed at FDEP's Tallahassee laboratory. The total TA value is $13,322.80 on a fixed unit rate basis. Invoicing is contingent upon FDEP approval of deliverables: $11,037.66 upon approval of the Annual Monitoring Report/IDW manifest/Project Management (due 05/15/2026) and $2,285.14 upon approval of PFAS sampling results (due 04/30/2026). The cost estimate includes direct labor, overhead, general and administrative costs, fringe benefits, travel expenses, laboratory analytical costs, and field equipment expenses. All activities will be conducted in accordance with the February 13, 2026 Work Plan submitted by Arcadis.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW680
DC026D Completion June 12, 2026
Arcadis will conduct annual groundwater monitoring including sampling for PFAS compounds from select wells at the site. All activities will be performed according to the February 13, 2026, Work Plan submitted by Arcadis.
Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor
Contractor Gus Suarez Contractor 813-205-4703
ERIC_5441
1530 1st St, Sarasota, Sarasota County
Prather's Laundry & Drycleaning (former)
Contractor Contractor
✔ $ 13,322.80
$ 13,322.80
Scope of Work
Arcadis U.S. Inc.
Contractor Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2026.02.23 10:05:10 -05'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2026.02.20 09:31:02 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Annual Monitoring Report/IDW manifest/Project Management 05/15/2026
PFAS sampling 04/30/2026
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management $ 11,037.66
FDEP approval of PFAS sampling $ 2,285.14
$ 13,322.80
HW680
DC026D
FFLORIDA DEPARTMENT OF
EEnvironmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jay Collins
Lt. Governor
AAlexis A. Lambert Secretary
Memorandum
TO: Negotiation File Prather’s Laundry & Drycleaning (former)
FACID NO. 58-9502850; ERIC_5441
Sarasota, Sarasota County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC026D (HW680) DATE: February 17, 2026
Arcadis U.S. Inc. will perform annual groundwater monitoring from select wells at the site. Groundwater monitoring will ensure that natural attenuation of contaminants continues to occur. Additionally, select wells will be sampled for PFAS compounds. All activities will be conducted in accordance with the February 13, 2026, Work Plan submitted by Chad Hanna of Arcadis.
The final task assignment total is $13,322.80. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.
Subtask 2: Annual Groundwater Monitoring FDEP obtained an access agreement in 2006 with the City of Sarasota, who remains the real property owner of the former Prather’s site.
Arcadis will sample thirteen wells for drycleaning solvents using passive diffusion bags (PDBs). IDW will be disposed by a licensed waste hauler.
Subtask 3: Reporting Arcadis will submit a written report as the final deliverable including recommendations for additional actions as needed.
Prather’s Laundry
ERIC_5441
Subtask 4: PFAS sampling
Arcadis will sample two monitor wells for PFAS compounds using FDEP’s laboratory in Tallahassee. The wells have been chosen based on prior PFAS results and FDEP’s new guidance/flow chart.
Hours and costs are comparable to past task assignments of similar scope.
FDEP COST ESTIMATEContractor: Arcadis, U.S., Inc.
Date: 2/13/2026
Task #: DC026D SubTask 1 Project Management
Site: SubTask 2 Groundwater Monitoring Event - VOHs
Activity/Phase: NAM SubTask 3 Reporting
Project Manager: Theresa Pepe SubTask 4 Groundwater Monitoring Event - PFAS
SubTask 5
TTotals 1 2 3 4 5 Labor Rate Category
$89.78 Principal Engineer Suarez, Gus (GS) 5.0 $89.78 Principal Engineer Suarez, Gus (GS) 4 1 2 1 0 $50.00 Senior Engineer Hanna, Chad (CH) 28 4 20 4 0 $34.89 Technician Welch, David (DJW) 34 26 0 8 0 $39.67 Drafter/Design Oliva, Brian (BO) 5 0 5 0 0 $39.94 Project Assistant Cruz, Michele (MC) 7 2 3 2 0
Total Hours 83 5.0 33.0 30.0 15.0 0.0
Direct Labor $3,868.34 $445.03 $1,276.80 $1,497.73 $648.78 $0.00
Overhead 79.00% $3,055.99 $351.57 $1,008.67 $1,183.21 $512.54 $0.00 Gen & Admin 36.00% $1,392.60 $160.21 $459.65 $539.18 $233.56 $0.00 Fringe 37.10% $1,435.16 $165.11 $473.69 $555.66 $240.70 $0.00 Total Labor $9,752.09 $1,121.92 $3,218.81 $3,775.78 $1,635.58 $0.00
Travel Vehicle $360.00 $240.00 $0.00 $120.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Meals $0.00 $0.00 $0.00 $0.00 $0.00 Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $360.00 $240.00 $0.00 $120.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00
Erwin IDW $125.00 $125.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $125.00 $125.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $12.50 $0.00 $0.00 $0.00 Total Subcontractor Cost $137.50 $137.50 $0.00 $0.00 $0.00
Laboratory Analytical Costs $949.00 $949.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $110.00 $110.00 $0.00 $0.00 $0.00 Total Laboratory $1,059.00 $1,059.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $120.00 $80.00 $0.00 $40.00 $0.00 Equipment (Drilling Related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $819.00 $493.00 $0.00 $326.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $1,039.00 $673.00 $0.00 $366.00 $0.00
Subtotal $12,347.59 $1,121.92 $5,328.31 $3,775.78 $2,121.58 $0.00 Completion Fee $975.21 $112.19 $321.88 $377.58 $163.56 $0.00
Total Estimated Cost $13,322.80 $1,234.11 $5,650.19 $4,153.36 $2,285.14 $0.00
Former Prather's Cleaners
REV: 09/25 CEF ARCADIS Page 1
SITE : Former Prather's Cleaners 0 SUBTASK 2: Groundwater Monitoring Event - VOHs
DATE: 2/13/26
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Activities and Email Updates Principal Engineer - GS PE oversight (1hr) 1
Senior Enginner - CMH 4
Field Technician - DJW 26
Project Assistant - MC Process and file field notes (2hrs) 2
TOTAL LABOR 33
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 2 $240.00 $240.00
TOTAL VEHICLE $240.00
STAFF RATE UNIT USEAGE
Meals
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals EESI AWS $2,000.00 Per Day 0 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals Erwin IDW $125.00 per drum 1 $125.00
Total Services: $125.00
TOTAL $125.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOCs 8260 Aqueous $73.00 1.00 13 $949.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $949.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 1 $110.00
Total Shipping: $110.00
TOTAL LAB $1,059.00
EQUIPMENT
Personal Protection Item Rate Unit Usage Totals
Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 2 $80.00
Total Expendables: $80.00 Equipment Items Water Level: Electric Tape $25.00 Per Day 1 $25.00 55-gallon Drum $100.00 Each 1 $100.00 Passive Diffusion Bags - small dia (2" well) $36.00 Each 13 $468.00
Total Equipment Items: $593.00 Equipment Kits Shallow Groundwater Sampling Kit $290.00 Day 0 $0.00
Total Equipment Kits: $0.00
Total Equipment Kits: $673.00
Notifications, field scheduling / support (1hr); prep paperwk/figures, order bottles (1hr), Field readiness with field crew (1hr), review field logs/notes (1hr), FDEP email update (1hr) Prep equipment/calibrations (2hrs); Mob/Demob (5hrs); measure water levels in 28 MWs (4hrs); sample PDB's - 13 wells/install new PDB's (12hrs);
IDW management/sampling (1hr); package/ship samples (1hr); paperwork (1hr)
SUBTASK 3: Reporting
DATE: 2/13/26
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Reporting Principal Engineer - GS PE certification/evaluate data & trends for final deliverable 2 Senior Enginner - CMH Report text, table, figure generation, report table validation, IDW T&D coordination 20 CAD Designer - BO Develop figures for GW results 5
Project Assistant - MC Data entry, report assembly, formatting 3
TOTAL LABOR 30
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 0 $0.00 $0.00
TOTAL VEHICLE $0.00
STAFF RATE UNIT USEAGE
Meals
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals EESI AWS $2,000.00 Per Day 0 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals Erwin IDW $125.00 per drum 0 $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOCs 8260 Aqueous $73.00 1.00 0 $0.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection Item Rate Unit Usage Totals
Total PPE: $0.00 Expendables
Total Expendables: $0.00 Equipment Items
Total Equipment Items: $0.00 Equipment Kits
Total Equipment Kits: $0.00
Total Equipment Kits: $0.00
SUBTASK 4: Groundwater Monitoring Event - PFAS
DATE: 2/13/26
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Field Activities and Email Updates Principal Engineer - GS PE oversight (1hr) 1
Senior Enginner - CMH Notifications, field scheduling / support (1hr); prep paperwk/figures, order bottles (1hr), Field readiness with field crew (1hr) review field logs/notes (1hr) 4 Field Technician - DJW Prep equipment/calibrations (2hrs); Mob/Demob (2hrs); sample 2 wells (2 hrs); IDW management/sampling (1hrs); package/ship samples (1hrs) 8
Project Assistant - MC Process and file field notes (2hrs) 2
TOTAL LABOR 15
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 1 $120.00 $120.00
TOTAL VEHICLE $120.00
STAFF RATE UNIT USEAGE
Meals
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00 Rate Units Usage
Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Personal Protection Item Rate Unit Usage Totals
Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 1 $40.00
Total Expendables: $40.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 100 $30.00 Tubing, Silicon 3/16x3/8 $3.00 Per Foot 2 $6.00
Total Equipment Items: $36.00 Equipment Kits Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00
Total Equipment Kits: $290.00
Total Equipment Kits: $366.00
Arcadis U.S., Inc.
4300 W Cypress Street Suite 450 Tampa Florida 33607 Phone: 813 903 3100 Fax: 813 350 9046 www.arcadis.com
FL Engineering License #7917 FL Geology License #GB564 FL Surveying License #LB7062
1/3
Theresa Pepe Hazardous Waste Cleanup Section Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, Florida 32399
Date: February 13, 2026 Our Ref: TBD Subject: Groundwater Monitoring Event Proposal
Former Prather’s Laundry and Drycleaning 1530 1st Street Sarasota, Florida FDEP Facility ID: ERIC_5441
Dear Ms. Pepe, Arcadis U.S., Inc. (Arcadis) is pleased to submit to the Florida Department of Environmental Protection (FDEP) this proposal to complete groundwater monitoring and reporting activities for the former Prather’s Drycleaners site in Sarasota, Sarasota County, Florida (Site). This proposal includes a description of the proposed scope of work, and the associated estimated cost and schedule for their completion.
Scope of Work The scope of work is comprised of four tasks. The tasks include project management, groundwater monitoring for VOHs, reporting, and groundwater monitoring for PFAS. A brief description of each task follows.
Task 1: Project Management This task consists of project management activities and health and safety efforts in relation to the completion of Tasks 2 through 4.
Task 2: Groundwater Sampling for VOHs This proposal includes the sampling of 13 wells in February 2026 as listed below:
Surficial Aquifer: Monitor well MW030A; and, Upper and Lower Intermediate Aquifer Zones: Monitor wells MW04B, MW04C, MW04E, MW04F, MW05BR, MW11B, MW13B, MW13C, MW19B, MW19C, MW21B, and MW25C.
Ms. Theresa Pepe Florida Department of Environmental Protection February 13, 2026 www.arcadis.com
2026.02 - Prather's Cleaners NAM Proposal
2/3
Arcadis will collect samples from the PDB samplers by transferring the groundwater in the PDB samplers into laboratory supplied sample vials for the analysis of VOHs using Environmental Protection Agency (EPA) Test Method 8260. The samples will be analyzed by a fixed-based National Environmental Laboratory Accreditation Program (NELAP)-certified laboratory (Eurofins). After collecting each sample, a new PDB will be deployed in the monitor wells for future sampling purposes. During the groundwater sampling activities, a full round of water levels will be obtained to assist in calculating lateral and vertical flow gradients/direction in each of the subsurface depth-intervals. IDW generated during sampling activities will be containerized on-site and removed for transportation and disposal by a licensed waste hauler (Erwin Remediation, Inc.).
Task 3: Reporting A Groundwater Monitoring Report (GMR) documenting the sampling methodology and results, including updated tables summarizing the analytical results, figures depicting groundwater flow, estimated extent/magnitude of VOH and PFAS impacts, and laboratory report will be provided to the FDEP. The report will be signed and sealed by a Florida-registered professional geologist or engineer.
Task 4: Groundwater Sampling for PFAS Groundwater samples will be collected from MW-4B and MW-30A using the low-flow sampling technique and shipped to the FDEP laboratory in Tallahassee, Florida for PFAS analysis. Results will be included in the GMR described above and a comprehensive table will be maintained with all PFAS data obtained for the Site. IDW generated during the PFAS sampling activities will be combined with the VOH sampling IDW and transported off- Site once both events have been completed.
Cost Estimate and Schedule A CEF is attached for the above scope of work. The total cost to complete this scope of work is $13,322.80 (Attachment 1). Arcadis proposes the following invoicing schedule:
Completion of groundwater monitoring field activities $7,935.33 Annual GMR submittal and PM $5,387.47
Arcadis proposes to complete the annual groundwater sampling event in February 2026. The GMR will be submitted within 60 days of receipt of the laboratory analytical data.
Ms. Theresa Pepe Florida Department of Environmental Protection February 13, 2026 www.arcadis.com
2026.02 - Prather's Cleaners NAM Proposal
3/3
Closing Remarks Arcadis appreciates the opportunity to assist the FDEP at this site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact us.
Sincerely, Arcadis U.S., Inc.
Chad M. Hanna Gus Suarez, P.E.
Senior Environmental Specialist Project Manager Email: Chad.hanna@arcadis.com Email: Gus.suarez@arcadis.com Phone: 813.353.5765 Phone: 813.353.5778