This document is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S. Inc. for environmental consulting services at the Former Imperial Laundry & Dry Cleaners site located at 901 W. Fairbanks Avenue, Winter Park, Orange County, Florida. The task assignment is designated DC041C under Contract Number HW680, with a completion date of May 8, 2026. The FDEP Project Manager is Theresa Pepe (850-245-8966), and the contractor's Project Manager is Gus Suarez (813-205-4703).

Arcadis will conduct two quarters of groundwater monitoring from select wells at the site, with all activities performed in accordance with the October 8, 2025 Work Plan submitted by Arcadis. The scope includes four subtasks: Project Management (calculated as a percentage of total labor), Quarterly Groundwater Monitoring Event 1 (sampling two recently reinstalled wells for drycleaning solvents), Quarterly Groundwater Monitoring Event 2 (same scope as Event 1), and Reporting (submission of a written report with recommendations for additional actions). The total Task Assignment value is $10,822.52, established on a fixed unit rate basis. The invoicing schedule is tied to FDEP approval of the Groundwater Monitoring Report, IDW manifest, and Project Management deliverables with a due date of March 31, 2026. The cost estimate includes direct labor ($8,364.56), travel ($240.00), laboratory costs ($512.00), field expenses ($732.00), subcontractor services for IDW disposal ($137.50), and a completion fee ($836.46).

View the file

Other files

File Type Posted
CN-370000-HW680-DC003B.pdf PDF
CN-370000-HW680-DC003C.pdf PDF
CN-370000-HW680-DC003D.pdf PDF
CN-370000-HW680-DC004C.pdf PDF
CN-370000-HW680-DC004ECO.pdf PDF
CN-370000-HW680-DC004F.pdf PDF
CN-370000-HW680-DC009B.pdf PDF
CN-370000-HW680-DC009C.pdf PDF
CN-370000-HW680-DC011C.pdf PDF
CN-370000-HW680-DC011D.pdf PDF
CN-370000-HW680-DC013A.pdf PDF
CN-370000-HW680-DC013B.pdf PDF
CN-370000-HW680-DC014C.pdf PDF
CN-370000-HW680-DC015A.pdf PDF
CN-370000-HW680-DC016C.pdf PDF
CN-370000-HW680-DC016F.pdf PDF
CN-370000-HW680-DC019C.pdf PDF
CN-370000-HW680-DC01ACO1.pdf PDF
CN-370000-HW680-DC020B.pdf PDF
CN-370000-HW680-DC020C.pdf PDF
CN-370000-HW680-DC021B.pdf PDF
CN-370000-HW680-DC022B.pdf PDF
CN-370000-HW680-DC023B.pdf PDF
CN-370000-HW680-DC024A.pdf PDF
CN-370000-HW680-DC025A.pdf PDF
CN-370000-HW680-DC026B.pdf PDF
CN-370000-HW680-DC029A.pdf PDF
CN-370000-HW680-DC031A.pdf PDF
CN-370000-HW680-DC032C.pdf PDF
CN-370000-HW680-DC034C.pdf PDF
CN-370000-HW680-DC035A.pdf PDF
CN-370000-HW680-DC036A.pdf PDF
CN-370000-HW680-DC037A.pdf PDF
CN-370000-HW680-DC037B.pdf PDF
CN-370000-HW680-DC037C.pdf PDF
CN-370000-HW680-DC038B.pdf PDF
CN-370000-HW680-DC03ACO1.pdf PDF
CN-370000-HW680-DC040B.pdf PDF
CN-370000-HW680-DC045A.pdf PDF
CN-370000-HW680-DC048A.pdf PDF
CN-370000-HW680-DC050A.pdf PDF
CN-370000-HW680-DC051A.pdf PDF
CN-370000-HW680-DC052A.pdf PDF
CN-370000-HW680-DC053B.pdf PDF
CN-370000-HW680-DC054A.pdf PDF
CN-370000-HW680-DC06BCO2.pdf PDF
CN-370000-HW680-DC07ACO1.pdf PDF
CN-370000-HW680-DC07ACO2.pdf PDF
CN-370000-HW680-DC08BCO1.pdf PDF
CN-370000-HW680-DC09BCO2.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

Additional signatures attached on separate page.

HW680

DC041C Completion May 8, 2026

Arcadis will conduct two quarters of groundwater monitoring from select wells at the site. All activities will be performed according to the October 8, 2025, Work Plan submitted by Arcadis.

Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor

Contractor Gus Suarez Contractor 813-205-4703

ERIC_5039

901 W. Fairbanks Ave, Winter Park, Orange County

Imperial Laundry & Dry Cleaners

Contractor Contractor

✔ $ 10,822.52

$ 10,822.52

Scope of Work

Arcadis U.S. Inc.

Contractor Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2025.10.14 13:56:14 -04'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2025.10.14 11:04:00 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Groundwater Monitoring Report/IDW manifest/Project Management 03/31/2026

FDEP approval of Groundwater Monitoring Report/IDW manifest/Project Management $ 10,822.52

$ 10,822.52

HW680

DC041C

FFLORIDA DEPARTMENT OF

EEnvironmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jay Collins

Lt. Governor

AAlexis A. Lambert Secretary

Memorandum

TO: Negotiation File Imperial Laundry & Dry Cleaners

FACID NO. 48-9503059; ERIC_5039

Winter Park, Orange County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC041C (HW680) DATE: October 10, 2025

Arcadis U.S. Inc. will perform two quarters of groundwater monitoring from select wells at the site. Groundwater monitoring will ensure that natural attenuation of contaminants continues to occur. All activities will be conducted in accordance with the October 8, 2025, Work Plan submitted by Chad Hanna of Arcadis.

The final task assignment total is $10,822.52. Arcadis may invoice according to the attached schedule.

Specific negotiated subtasks are as follows:

Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.

Subtasks 2 and 3: Quarterly Groundwater Monitoring FDEP obtained an access agreement in December 2021 with the City of Winter Park, who remains the real property owner of the former Imperial site.

Arcadis will sample two recently reinstalled wells for drycleaning solvents per the recommendation of the Waste Site Cleanup Section’s Geologist. IDW will be disposed by a licensed waste hauler.

Subtask 4: Reporting Arcadis will submit a written report as the final deliverable including recommendations for additional actions as needed.

FDEP COST ESTIMATEContractor: Arcadis, U.S., Inc.

Date: 10/8/2025

Task #: DC041C SubTask 1 Project Management

Site: SubTask 2 Groundwater Monitoring Event 1 - VOHs

Activity/Phase: NAM SubTask 3 Groundwater Monitoring Event 2 - VOHs

Project Manager: Theresa Pepe SubTask 4 Reporting

SubTask 5

TTotals 1 2 3 4 5 Labor Rate Category

$89.78 Principal Engineer Suarez, Gus (GS) 4.3 $89.78 Principal Engineer Suarez, Gus (GS) 4 1 1 2 0 $50.00 Senior Engineer Hanna, Chad (CH) 18 5 5 8 0 $41.50 Project Scientist Brooks, Eric (EAB) 8 0 0 8 0 $34.89 Technician Welch, David (DJW) 26 13 13 0 0 $39.67 Drafter/Design Oliva, Brian (BO) 5 0 0 5 0 $39.94 Project Assistant Cruz, Michele (MC) 6 2 2 2 0

Total Hours 71 4.3 21.0 21.0 25.0 0.0

Direct Labor $3,317.96 $381.71 $873.23 $873.23 $1,189.79 $0.00

Overhead 79.00% $2,621.18 $301.55 $689.85 $689.85 $939.93 $0.00 Gen & Admin 36.00% $1,194.46 $137.42 $314.36 $314.36 $428.32 $0.00 Fringe 37.10% $1,230.96 $141.61 $323.97 $323.97 $441.41 $0.00 Total Labor $8,364.56 $962.29 $2,201.41 $2,201.41 $2,999.45 $0.00

Travel Vehicle $240.00 $120.00 $120.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Meals $0.00 $0.00 $0.00 $0.00 $0.00 Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $240.00 $120.00 $120.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00

Erwin IDW $125.00 $0.00 $125.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 Utility Location $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $125.00 $0.00 $125.00 $0.00 $0.00 Handling Fee $12.50 $0.00 $12.50 $0.00 $0.00 Total Subcontractor Cost $137.50 $0.00 $137.50 $0.00 $0.00

Laboratory Analytical Costs $292.00 $146.00 $146.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $220.00 $110.00 $110.00 $0.00 $0.00 Total Laboratory $512.00 $256.00 $256.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $80.00 $40.00 $40.00 $0.00 $0.00 Equipment (Drilling Related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $652.00 $326.00 $326.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $732.00 $366.00 $366.00 $0.00 $0.00

Subtotal $9,986.06 $962.29 $2,943.41 $3,080.91 $2,999.45 $0.00 Completion Fee $836.46 $96.23 $220.14 $220.14 $299.95 $0.00

Total Estimated Cost $10,822.52 $1,058.52 $3,163.55 $3,301.05 $3,299.40 $0.00

Former Imperial Cleaners

REV: 09/25 CEF ARCADIS Page 1

SITE : Former Imperial Cleaners 0 SUBTASK 2: Groundwater Monitoring Event 1 - VOHs

DATE: 10/8/25

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Activities and Email Updates Principal Engineer - GS Field readiness with project team, PE oversight (1hr) 1

Senior Enginner - CMH 5

Field Technician - DJW 13

Project Assistant - MC Process and file field notes (2hrs) 2

TOTAL LABOR 21

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 1 $120.00 $120.00

TOTAL VEHICLE $120.00

STAFF RATE UNIT USEAGE

Meals

Category/Staff Rate Unit Usage Totals $36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00

Hotel Category/Staff Rate Unit Usage Totals

$150.00 Per Day 0 $0.00 $150.00 Per Day 0 $0.00

Total Meal/Hotel: $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals EESI AWS $2,000.00 Per Day 0 $0.00

Total Equip.: $0.00 Services Procurement

Name Purpose Rate Units Usage Totals Erwin IDW $125.00 per drum 0 $0.00

Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOCs 8260 Aqueous $73.00 1.00 2 $146.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $146.00

Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 1 $110.00

Total Shipping: $110.00

TOTAL LAB $256.00

EQUIPMENT

Personal Protection Item Rate Unit Usage Totals

Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 1 $40.00

Total Expendables: $40.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 100 $30.00 Tubing, Silicon 3/16x3/8 $3.00 Per Foot 2 $6.00 55-gallon Drum $100.00 Each 0 $0.00

Total Equipment Items: $36.00 Equipment Kits Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00

Total Equipment Kits: $290.00

Total Equipment Kits: $366.00

Prep equipment/calibrations (2hrs); Mob/Demob (5hrs); measure water levels in 9 MWs (1hr); sample 2 wells (2hrs); IDW management/sampling (1hr); package/ship samples (1hr); paperwork (1hr)

Notifications, field scheduling / support (1hr); prep paperwk/figures, order bottles (1hr), Field readiness with field crew (1hr), review field logs/notes (1hr), FDEP email update (1hr)

SUBTASK 3: Groundwater Monitoring Event 2 - VOHs

DATE: 10/8/25

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Field Activities and Email Updates Principal Engineer - GS Field readiness with project team, PE oversight (1hr) 1

Senior Enginner - CMH 5

Field Technician - DJW 13

Project Assistant - MC Process and file field notes (2hrs) 2

TOTAL LABOR 21

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 1 $120.00 $120.00

TOTAL VEHICLE $120.00

STAFF RATE UNIT USEAGE

Meals

Category/Staff Rate Unit Usage Totals $36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00

Hotel Category/Staff Rate Unit Usage Totals

$150.00 Per Day 0 $0.00 $150.00 Per Day 0 $0.00

Total Meal/Hotel: $0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals EESI AWS $2,000.00 Per Day 0 $0.00

Total Equip.: $0.00 Services Procurement

Name Purpose Rate Units Usage Totals Erwin IDW $125.00 per drum 1 $125.00

Total Services: $125.00

TOTAL $125.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOCs 8260 Aqueous $73.00 1.00 2 $146.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $146.00

Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 1 $110.00

Total Shipping: $110.00

TOTAL LAB $256.00

EQUIPMENT

Personal Protection Item Rate Unit Usage Totals

Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 1 $40.00

Total Expendables: $40.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 100 $30.00 Tubing, Silicon 3/16x3/8 $3.00 Per Foot 2 $6.00 55-gallon Drum $100.00 Each 0 $0.00

Total Equipment Items: $36.00 Equipment Kits Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00

Total Equipment Kits: $290.00

Total Equipment Kits: $366.00

Notifications, field scheduling / support (1hr); prep paperwk/figures, order bottles (1hr), Field readiness with field crew (1hr), review field logs/notes (1hr), FDEP email update (1hr)

Prep equipment/calibrations (2hrs); Mob/Demob (5hrs); measure water levels in 9 MWs (1hr); sample 2 wells (2hrs); IDW management/sampling (1hr); package/ship samples (1hr); paperwork (1hr)

SUBTASK 4: Reporting

DATE: 10/8/25

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Annual Groundwater Monitoring Report Principal Engineer - GS PE finalization/certification 2 Senior Enginner - CMH Report text, table, figure generation, report table validation, IDW T&D coordination 8 Project Scientist - EAB Report text, table, figure generation 8 CAD Designer - BO Develop figures for GW results 5 Project Assistant - MC Data entry, report assembly, formatting 2

TOTAL LABOR 25

VEHICLE TYPE RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals $0.00 Per Day 0 $0.00

Total Equip.: $0.00 Services Procurement

Name Purpose Rate Units Usage Totals

Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00 Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB $0.00

EQUIPMENT

Personal Protection Item Rate Unit Usage Totalsy

Total PPE: $0.00 Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00 Equipment Items y

Total Equipment Items: $0.00 Equipment Kits

Total Equipment Kits: $0.00

Total Equipment Kits: $0.00

Arcadis U.S., Inc.

4300 W Cypress Street Suite 450 Tampa Florida 33607 Phone: 813 903 3100 Fax: 813 350 9046 www.arcadis.com

FL Engineering License #7917 FL Geology License #GB564 FL Surveying License #LB7062

1/3

Theresa Pepe Hazardous Waste Cleanup Section Florida Department of Environmental Protection 2600 Blair Stone Road Tallahassee, Florida 32399

Date: October 8, 2025 Subject: Natural Attenuation Monitoring Proposal

Former Imperial Laundry and Drycleaners 901 West Fairbanks Avenue Winter Park, Florida

Dear Ms. Pepe, Arcadis U.S., Inc. (Arcadis) is pleased to submit to the Florida Department of Environmental Protection (FDEP) the following proposal for Natural Attenuation Monitoring (NAM) activities at the Former Imperial Laundry and Drycleaners (Site), located in Winter Park, Florida. This proposal includes background information, a description of the proposed scope of work (SOW), and an estimated cost and schedule for their completion.

Site Background Arcadis completed Task Assignment (TA) #DC041B, which included the 2025 annual NAM sampling event (July 2025) and associated reporting. The City of Winter Park constructed a turn on the eastern portion of the former dry cleaning parcel in 2024. The Site was used to stage equipment and materials for construction activities. All of the monitor wells except MW005, were damaged and covered by restoration activities following construction of the turn lane. A professional surveyor staked the well locations and Arcadis personnel uncovered the wells on January 8, 2025. Monitor wells MW004, MW005, and MW008 were determined to be the only viable wells.

Based on observed damage to existing monitor wells from construction activities, monitoring wells MW007 and MW013 were destroyed and monitor wells MW001, MW002, MW003, MW009, and MW012 were abandoned by licensed driller Preferred Drilling Solutions Inc. on June 30, 2025. The same day, monitor wells MW001R and MW002R were installed to replace damaged and abandoned monitoring wells MW001 and MW002, and MW004 and MW008 were redeveloped.

The 2025 Annual NAM Report was submitted on August 8, 2025. Tetrachloroethene (PCE) was detected above the FDEP GCTL in the sample collected from monitor well MW002R (7.0 μg/L). Arcadis recommended continued monitoring of MW001R and MW002R. The FDEP reviewed the report and concurred with the recommendations in an email dated September 8, 2025.

Ms. Theresa Pepe Florida Department of Environmental Protection October 8, 2025 www.arcadis.com

2025.10 - Imperial NAM Proposal

2/3

Scope of Work

Task 1: Project Management This task consists of project management activities and health and safety efforts in relation to the completion of Tasks 2 through 4.

Task 2: NAM Field Event Q1

The proposed groundwater NAM program includes depth-to-water measurements and the sampling of two shallow monitoring wells. Depth-to-water measurements will be collected from all accessible site monitor wells and samples will be collected from MW001R and MW002R. The groundwater sampling activities will be performed per the FDEP standard operating procedures (SOP) (DEP-SOP-001/01).

Samples will be shipped to Eurofins located in Altamonte Springs, Florida, and analyzed for CVOCs by United States Environmental Protection Agency (USEPA) Method 8260. In accordance with FDEP guidance, the IDW generated during sampling activities will be containerized on-site and removed for transportation and disposal by a licensed waste hauler (Erwin Remediation Inc.) following receipt of the laboratory analytical report from the second quarterly monitoring event.

Task 3: NAM Field Event Q2

Arcadis will complete an additional monitoring event with the same scope as Task 2.

Task 4: NAM Reporting

A NAM Report will be submitted to the FDEP within 60 days of receipt of the laboratory analytical report from the second quarter of monitoring activities. The Report will contain tables and figures summarizing the results of the two quarterly NAM events and include conclusions and recommendations based upon findings.

Cost Estimate

Arcadis will schedule the field activities following receipt of a TA from the FDEP. The CEF/LOE is included as Attachment 1. The total cost to complete this scope of work is $10,822.52 (Attachment 1). Arcadis proposes the following invoicing schedule:

Completion of NAM field event Q1 $3,163.55 Completion of NAM field event Q2 $3,301.05 NAM Report submittal and PM $4,357.92

Ms. Theresa Pepe Florida Department of Environmental Protection October 8, 2025 www.arcadis.com

2025.10 - Imperial NAM Proposal

3/3

Closing Remarks Arcadis appreciates the opportunity to assist the FDEP at this Site. If you have any questions or wish to discuss this proposal, please do not hesitate to contact us.

Sincerely, Arcadis U.S., Inc.

Chad Hanna Gus Suarez, P.E.

Senior Environmental Specialist Project Manager Email: Chad.hanna@arcadis.com Email: Gus.suarez@arcadis.com Phone: 813.353.5765 Phone: 813.353.5778