CN-370000-HW680-DC022A.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|HW680|454e104ae8fbcb5641ac6acc30583968
Contract number
HW680
Issued by
Florida

About this file

This is a Task Assignment (TA) document under Contract Number HW680 between the State of Florida Department of Environmental Protection (FDEP) and Arcadis U.S. Inc. for environmental remediation services at the former Dry Clean USA site located at 10333 Royal Palm Boulevard, Coral Springs, Broward County, Florida (Facility ID ERIC_4193). The task assignment is identified as DC022A with a completion date of February 10, 2023. The Department Project Manager is Theresa Pepe (850-245-8966), and the Contractor's Project Manager is Gus Suarez (813-205-4703).

Arcadis will conduct annual groundwater monitoring from select wells at the site according to the May 6, 2022 Work Plan. The scope of work consists of three subtasks: Project Management (calculated as a percentage of total labor); Annual Groundwater Monitoring (sampling thirty wells for drycleaning solvents and six wells for UIC parameters, with IDW disposal); and Reporting (preparation and submission of an Annual Monitoring Report with recommendations). The total Task Assignment value is $19,660.44 on a fixed unit rate basis. Payment is contingent upon FDEP approval of the Annual Monitoring Report, IDW manifest, and Project Management deliverables, with a due date of January 6, 2023. The cost estimate breaks down as follows: Subtask 1 (Project Management) at $1,466.75, Subtask 2 (Annual Groundwater Monitoring) at $13,171.77, and Subtask 3 (Reporting) at $5,021.92, including labor, travel, laboratory analytical costs, equipment, and completion fees. The task assignment was signed on May 12, 2022.

View the file

Other files

File Type Posted
CN-370000-HW680-DC001B.pdf PDF
CN-370000-HW680-DC001E.pdf PDF
CN-370000-HW680-DC001F.pdf PDF
CN-370000-HW680-DC005A.pdf PDF
CN-370000-HW680-DC005B.pdf PDF
CN-370000-HW680-DC006C.pdf PDF
CN-370000-HW680-DC007C.pdf PDF
CN-370000-HW680-DC008C.pdf PDF
CN-370000-HW680-DC009A.pdf PDF
CN-370000-HW680-DC009D.pdf PDF
CN-370000-HW680-DC010A.pdf PDF
CN-370000-HW680-DC010B.pdf PDF
CN-370000-HW680-DC011A.pdf PDF
CN-370000-HW680-DC012A.pdf PDF
CN-370000-HW680-DC014D.pdf PDF
CN-370000-HW680-DC015F.pdf PDF
CN-370000-HW680-DC016A.pdf PDF
CN-370000-HW680-DC017A.pdf PDF
CN-370000-HW680-DC017D.pdf PDF
CN-370000-HW680-DC019A.pdf PDF
CN-370000-HW680-DC019B.pdf PDF
CN-370000-HW680-DC020D.pdf PDF
CN-370000-HW680-DC021A.pdf PDF
CN-370000-HW680-DC026D.pdf PDF
CN-370000-HW680-DC029B.pdf PDF
CN-370000-HW680-DC030A.pdf PDF
CN-370000-HW680-DC033A.pdf PDF
CN-370000-HW680-DC034A.pdf PDF
CN-370000-HW680-DC039B.pdf PDF
CN-370000-HW680-DC03BCO1.pdf PDF
CN-370000-HW680-DC03DCO1.pdf PDF
CN-370000-HW680-DC03DCO2.pdf PDF
CN-370000-HW680-DC040A.pdf PDF
CN-370000-HW680-DC041B.pdf PDF
CN-370000-HW680-DC041C.pdf PDF
CN-370000-HW680-DC046B.pdf PDF
CN-370000-HW680-DC047B.pdf PDF
CN-370000-HW680-DC048B.pdf PDF
CN-370000-HW680-DC049A.pdf PDF
CN-370000-HW680-DC050B.pdf PDF
CN-370000-HW680-DC051B.pdf PDF
CN-370000-HW680-DC07BCO1.pdf PDF
CN-370000-HW680-DC07CCO1.pdf PDF
CN-370000-HW680-DC09ACO1.pdf PDF
CN-370000-HW680-DC10ACO1.pdf PDF
CN-370000-HW680-DC10BCO2.pdf PDF
CN-370000-HW680-DC10BCO3.pdf PDF
CN-370000-HW680-DC11BCO1.pdf PDF
CN-370000-HW680-DC13DC01.pdf PDF
CN-370000-HW680-DC14BC11.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW680

DC022A Completion February 10, 2023

Arcadis will conduct annual groundwater monitoring from select wells at the site. All activities will be performed according to the May 6, 2022, Work Plan submitted by Arcadis.

Theresa Pepe 850-245-8966 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Arcadis U.S. Inc.

Arcadis U.S. Inc.

Gus Suarez 813-205-4703

ERIC_4193

10333 Royal Palm Blvd, Coral Springs, Broward County

Dry Clean USA

✔ $ 19,660.44

$ 19,660.44

Scope of Work

Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2022.05.12 15:33:07 -04'00'

William E. Burns, Jr.

William E. Burns, Jr. Digitally signed by William E. Burns, Jr.

Date: 2022.05.12 14:57:36 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Annual Monitoring Report/IDW manifest/Project Management 01/06/2023

FDEP approval of Annual Monitoring Report/IDW manifest/Project Management $ 19,660.44

$ 19,660.44

HW680

DC022A

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez

Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: Negotiation File Dry Clean USA

FACID NO. 06-9502279; ERIC_4193

Coral Springs, Broward County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC022A (HW680) DATE: May 12, 2022

Arcadis U.S. Inc. will perform annual groundwater monitoring from select wells at the site. Groundwater monitoring will ensure that bioremediation of contaminants continues to occur. All activities will be conducted in accordance with the May 6, 2022, Work Plan submitted by Doug McGlone of Arcadis.

The final task assignment total is $19,660.44. Arcadis may invoice according to the attached schedule.

Specific negotiated subtasks are as follows:

Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.

Subtask 2: Annual Groundwater Monitoring Arcadis will sample thirty wells for drycleaning solvents based on recommendations from the previous monitoring report. Additionally, six wells will be sampled for UIC parameters due to the prior bioremediation injections. IDW will be drummed and disposed by a licensed waste hauler per FDEP’s preference. Note: This will be the first annual sampling event after the bio injections; therefore, the high number of wells sampled is justified. Total number of wells sampled is expected to come down as remediation progresses.

Subtask 3: Reporting An Annual Monitoring Report including recommendations for additional actions will be submitted as the final Deliverable.

Hours and costs are comparable to past task assignments of similar scope.

FDEP COST ESTIMATE

Contractor: Arcadis, U.S., Inc.

Date: 4/5/2022

Task #: SubTask 1 Project Management

Site: Dryclean USA Coral Springs SubTask 2 Groundwater Monitoring

Activity/Phase: Monitoring SubTask 3 Reporting

Project Manager: Doug McGlone SubTask 4

SubTask 5

Totals 1 2 3 4 5

Labor Rate Category

$61.38 Project Manager McGlone, Douglas (DMc) 9 8.6

$96.76 Principal Engineer Bedessem, Jim (JMB) 0 0 0 0 0

$61.69 Principal Scientist Burke, Brian (BRB) 0 0 0 0 0

$61.38 Principal Scientist McGlone, Douglas (DMc) 9 4 5 0 0

$39.34 Staff Scientist Riley, Joel (JR) 73 48 25 0 0

$39.67 Drafter/Designer Oliva, Brian (BO) 10 0 10 0 0

$30.96 Project Assistant McLemore, Michele (MMc) 8 4 4 0 0

Total Hours 109 9 56 44 0 0

Direct Labor $4,597.54 $528.92 $2,257.68 $1,810.94 $0.00 $0.00

Overhead 79.00% $3,632.06 $417.85 $1,783.57 $1,430.64 $0.00 $0.00

Gen & Admin 36.00% $1,655.11 $190.41 $812.76 $651.94 $0.00 $0.00

Fringe 37.10% $1,705.69 $196.23 $837.60 $671.86 $0.00 $0.00

Total Labor $11,590.40 $1,333.41 $5,691.61 $4,565.38 $0.00 $0.00

Travel

Vehicle Rental $480.00 $480.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00

Total Travel $480.00 $480.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW $150.00 $150.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $150.00 $150.00 $0.00 $0.00 $0.00

Handling Fee $15.00 $15.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $165.00 $165.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $3,546.00 $3,546.00 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $450.00 $450.00 $0.00 $0.00 $0.00

Total Laboratory $3,996.00 $3,996.00 $0.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $160.00 $160.00 $0.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $2,010.00 $2,010.00 $0.00 $0.00 $0.00

Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00

Equipment (Other- MAGS, recon, etc.) $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $2,270.00 $2,270.00 $0.00 $0.00 $0.00

Subtotal $18,501.40 $1,333.41 $12,602.61 $4,565.38 $0.00 $0.00

Completion Fee $1,159.04 $133.34 $569.16 $456.54 $0.00 $0.00

Total Estimated Cost $19,660.44 $1,466.75 $13,171.77 $5,021.92 $0.00 $0.00

REV: 02/03 CEF ARCADIS Page 1

SITE : Dryclean USA Coral Springs SUBTASK 2: Groundwater Monitoring

DATE: 4/5/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Groundwater Monitoring Pricipal / DMc Owner/property mgr interaction & access; correspondence with FDEP and field crew 4 Staff Scientist / JR Prep for fieldwork (1 hr), mob/demob (3 hrs); round of WLs (4 hrs), purge & sample 30 wells, pack ship (40 hrs) 48 Project Asst - MMc Field notes processing, sample tracking 4

TOTAL LABOR 56

VEHICLE TYPE RATE UNIT USEAGE

Van/Truck $120.00 Per Day 4 $480.00 $480.00

TOTAL VEHICLE $480.00

SUBCONTRACTOR COSTS

Services Procurement

Name Purpose Rate Units Usage Totals Lump Sum $0.00

Clark IDW $150.00 Drum 1 $150.00

Total Services: $150.00

TOTAL $150.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260 Aqueous $73.00 1.00 30 $2,190.00 Methane, ethane, ethene RSK175 Aquesus $180.00 1.00 6 $1,080.00 Total organic carbon EPA 9060 Aquesous $30.00 1.00 6 $180.00 Total dissolved solids SM 2540 Aqueous $16.00 1.00 6 $96.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $3,546.00

Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 3 $450.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $450.00

TOTAL LAB $3,996.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals Total PPE: $0.00

Expendables Miscellaneous Expendables $40.00 Per Day 4 $160.00

Total Expendables: $160.00 Equipment ItemsPID/FID Combo or FID $125.00 Per Day 0 $0.00 Tubing, Poly/HDPE $0.30 Per Foot 1800 $540.00 Tubing, Silicon 3/16x3/8 $3.00 Per Foot 20 $60.00 55-gallon Drum $100.00 Each 1 $100.00

Total Equipment Items: $700.00 Equipment KitsMonitor Well Installation Kit $325.00 Day 0 $0.00 Shallow Groundwater Sampling Kit $290.00 Day 2 $580.00 Deep Groundwater Sampling Kit $415.00 Day 2 $830.00

Total Equipment Kits: $1,410.00

TOTAL EQUIPMENT $2,270.00

SITE : Dryclean USA Coral Springs SUBTASK 3: Reporting

DATE: 4/5/2022

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Data Evaluation and Letter Report Principal / DMc Technical review; sign and seal report 5 Staff Scientist / JR Data evaluation and preparation of report 25 Drafter / BO Figures production for report 10 Project Asst - MMc Process field notes, report assembly, submittals, ADaPT processing/upload 4

TOTAL LABOR 44

VEHICLE TYPE RATE UNIT USEAGE

Van/Truck $120.00 Per Day 0 $0.00 $0.00

TOTAL VEHICLE $0.00

SUBCONTRACTOR COSTS

Services Procurement

Name Purpose Rate Units Usage Totals Drum $0.00

Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260 Aqueous $73.00 1.00 0 $0.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00

Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB $0.00

EQUIPMENT

Personal Protection

Item Rate Unit Usage Totals Total PPE: $0.00

Expendables Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 0 $0.00

Total Equipment Items: $0.00 Equipment Kits Deep Groundwater Sampling Kit $415.00 Day 0 $0.00

Total Equipment Kits: $0.00

TOTAL EQUIPMENT $0.00

Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.

Arcadis U.S., Inc.

1500 Gateway Blvd

Suite 200

Boynton Beach

Florida 33426

Tel 561 697 7000

Fax 561 369 4731 www.arcadis.com

Page:

1/3

Ms. Theresa Pepe, Contract Manager Hazardous Waste Section Florida Department of Environmental Protection Bob Martinez Center, MS 4520 2600 Blair Stone Road Tallahassee, Florida 32399-2400

Subject:

Proposal for Annual Groundwater Monitoring and Reporting Former Dryclean USA Coral Springs Site (Facility ID ERIC_4193) 10333 Royal Palm Blvd., Coral Springs, Broward County, Florida

Dear Ms. Pepe:

Arcadis U.S., Inc. (Arcadis) is pleased to submit the following proposal/cost estimate for annual groundwater monitoring and reporting for the remaining drycleaner solvents in the groundwater at the subject site. This proposal includes a description of the proposed scope of services and an estimated cost and schedule for their completion.

SCOPE OF WORK

Task 1: Project Management

This task consists of project management-related activities in relation to the completion of Tasks 2 and 3.

Task 2: Groundwater Monitoring Event

In October 2022, groundwater samples from 17 intermediate-depth monitor wells

(MW001, MW002, MW003, MW004, MW010, MW011, MW012, MW-15, MW-18,

MW-25D, MW-26 (50’), MW-29 (55’), MW-30 (40’), MW-30 (55’), MW-31 (55’),

MW-32, MW-34 (55’)) and 13 deep-depth monitor wells (MW005, MW006, MW007, MW013, MW014, MW-23, MW-26 (70’), MW-26 (90’), MW-29 (70’), MW-30 (70’), MW-31 (70’), MW-31 (100’), MW-34 (70’) will be obtained and delivered to a NELAC-accredited laboratory for VOH analyses to determine the extent of the residual chlorinated solvent plume. Six wells (MW-18, MW-25D, ENVIRONMENT

Date:

May 6, 2022

Contact:

Doug McGlone

Phone:

561 662.7978

Email:

Douglas.mcglone@arcadis.c om

Our ref:

30056595

Florida License Numbers

Engineering

Geology

GB564

Surveying

LB7062

Use or disclosure of information contained on this sheet is subject to the restriction and disclaimer located on the signature page of this document.

arcadis.com C:\Users\Pepe_T\Desktop\DCUSA Coral Springs Annual Monitoring Proposal_050622.docx

Theresa Pepe 6 May 2022

Page:

2/3

MW-26 (50’), MW-26 (70’), MW-31 (55’), MW-31 (70’) will also be sampled for UIC parameters including dissolved gases (ethane, ethene, methane), TOC and TDS. A full round of water level measurements, and field water quality from the above-listed 30 monitor wells will be performed. Purge water will be containerized for offsite disposal.

Task 3: Annual Groundwater Monitoring Report

Upon completion of the field monitoring event and receipt of the sample analytical data, Arcadis will review/validate the data and prepare updated figures/tables and an Annual Groundwater Monitoring Report and submit to FDEP. This report will summarize the results of the monitoring activities completed at the site and include tables, figures and graphs of VOH concentrations, illustrate the treatment performance indicator parameters/trends, sample analytical reports, and recommendations.

SCHEDULE

Arcadis will coordinate the scope of work in October 2022, after receipt of a signed Task Assignment (TA). The Annual Groundwater Monitoring Report will be delivered within 60 days of completion of the groundwater monitoring event.

COST ESTIMATE

Level of Effort (LOE) Forms and a Cost Estimate Form (CEF) that present estimated project costs are enclosed.

CLOSING REMARKS

Arcadis appreciates the opportunity to continue to assist the FDEP in the closure of the remaining drycleaning solvents in the subsurface at the former Dryclean USA Coral Springs site. If you have any questions or wish to discuss this proposal, please contact the undersigned.

This proposal and its contents shall not be duplicated, used or disclosed — in whole or in part — for any purpose other than to evaluate the proposal. This proposal is not intended to be binding or form the terms of a contract. The scope and price of this proposal will be superseded by the contract. If this proposal is accepted and a contract is awarded to Arcadis as a result of — or in connection with — the submission of this proposal, Arcadis and/or the client shall have the right to make appropriate revisions of its terms, including scope and price, for purposes of the contract. Further, client shall have the right to duplicate, use or disclose the data contained in this proposal only to the extent provided in the resulting contract.

arcadis.com C:\Users\Pepe_T\Desktop\DCUSA Coral Springs Annual Monitoring Proposal_050622.docx

Theresa Pepe 6 May 2022

Page:

3/3

Sincerely, Arcadis U.S., Inc.

Douglas J. McGlone, P.G.

Senior Geologist

Attachments

CEF-LOE

6/9/2021 Clark Environmental Inc.: Quote Builder file:///C:/Users/channa/AppData/Local/Microsoft/Windows/INetCache/Content.Outlook/55TP28C8/Arcadis 1530 1st.html 1/2

Quote Number: 18737

QUOTE

QUOTED TO: Chad Hanna QUOTE DATE: 6/9/2021 COMPANY NAME: Arcadis QUOTED BY: Steve Harris PHONE NUMBER: 813-480-8498 Ext.

FAX NUMBER: email only PROJECT REFERENCE: Transportation and Disposal of Non Haz. Water Drum.

CUSTOMER PO:

CONTACT EMAIL:

SITE ADDRESS: 1530 1st Street Sarasota FL

CLARK ENVIRONMENTAL, INC. IS PLEASED TO PROVIDE THE

FOLLOWING COST ESTIMATE FOR THE SITE/ PROJECT LISTED

ABOVE.

DESCRIPTION PRICE QTY. UNIT TOTAL

NON HAZ. "WATER" DRUM DISPOSAL W/CUSTOMER SUPPLIED

ACCEPTABLE NON HAZ. ANALYTICAL AND PROFILE STATING SAME.

$60.00 1 55 GAL $60.00

DRUM TRANSPORTTATION <100 MILES FROM CLARK ENVIRONMENTAL

INC. DRUM LOCATED ON HARD BLACK TOP OR CONCRETE SURFACE

EASILY ACCESSIBLE WITH 53 FOOT TRACTOR TRAILER WITH

LIFTGATE NO CURBS, GRASS OR DIRT TO CROSS.

$40.00 1 55 GAL $40.00

DRUM LOW VOLUME STOP CHARGE FOR 5 DRUMS OR LESS. $50.00 1 FLAT RATE $50.00

TOTAL REQUIRED ITEMS $150.00

TOTAL OPTIONAL ITEMS $0.00

GRAND TOTAL $150.00

NOTES: Quote is based on acceptable customer supplied non haz. analyticals and matching profile. TCLP Metals and Volatiles Analitical Testing will be required .Quote based on DOT shippable drums from this location easily accessable with 53 foot tractor trailer with no grass, curbs or sand to cross.If Required, I will need a signed accepted quote with purchase order and non haz. profile. Please call with any questions. Thanks. Steve Harris 863-559-

This quote will remain valid for thirty (30) days from the date listed above except for transportation which is subject to weekly change and is based on upon payment in net 30 days. Quote based on an accepted and approved profile. Please sign and return to accept this quotation and by signing agree to all terms and conditions.

Peerless Cleaners #3416 Annual Monitoring Proposal 4-18-2022.pdf
Annual Groundwater Monitoring
Annual Groundwater Monitoring Report
Schedule
Cost Estimate
Closing Remarks
HW680_DC022A negsum.pdf
Subtask 1: Project Management
DCUSA Coral Springs Annual Monitoring Proposal_050622.pdf
Scope of Work
Task 1: Project Management
Task 2: Groundwater Monitoring Event
Task 3: Annual Groundwater Monitoring Report
Schedule
Cost Estimate
Closing Remarks