This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S. Inc. for environmental remediation services at the Kathy's Cleaners facility located at 202 West Howard Street, Live Oak, Suwannee County, Florida. The task assignment is numbered DC008C under Contract HW680 and represents a specific scope of work derived from the underlying indefinite delivery contract. The FDEP project manager is Theresa Pepe, and the contractor's project manager is Gus Suarez. This document is effective through the completion date of September 30, 2025.
The task assignment requires Arcadis to conduct annual groundwater monitoring including sampling for PFAS compounds from select wells at the site, all activities to be performed according to the March 24, 2025 Work Plan submitted by Arcadis. The scope includes four subtasks: Project Management (automatically calculated as a percentage of total labor); PFAS sampling from two wells using FDEP's laboratory; Annual Groundwater Monitoring for volatile organic hydrocarbons (VOHs) from ten wells; and Reporting, which includes delivery of an Annual Monitoring Report with recommendations for additional actions. The total task assignment value is $15,506.83, comprising $3,388.12 for PFAS sampling (due upon FDEP approval by July 31, 2025) and $12,118.71 for Annual Monitoring Report/IDW manifest/Project Management (due upon FDEP approval by August 29, 2025). This represents a reduction from the original proposal cost of $18,078.82, achieved through negotiation that reduced the number of wells sampled from twelve to ten and total labor hours from 40 to 33 for field activities and from 42 to 32 for reporting activities.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
HW680
DC008C Completion September 30, 2025
Arcadis will conduct annual groundwater monitoring including sampling for PFAS compounds from select wells at the site. All activities will be performed according to the March 24, 2025, Work Plan submitted by Arcadis.
Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor
Contractor Gus Suarez Contractor 813-205-4703
ERIC_5504
202 West Howard Street, Live Oak, Suwannee County
Kathy's Cleaners
Contractor Contractor
✔ $ 15,506.83
$ 15,506.83
Scope of Work
Arcadis U.S. Inc.
Contractor Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2025.04.03 16:34:45 -04'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2025.04.03 15:36:03 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Annual Monitoring Report/IDW manifest/Project Management 08/29/2025
PFAS sampling 07/31/2025
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management $ 12,118.71
FDEP approval of PFAS sampling $ 3,388.12
$ 15,506.83
HW680
DC008C
FFLORIDA DEPARTMENT OF
EEnvironmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
AAlexis A. Lambert
Secretary
Memorandum
TO: Negotiation File Kathy’s Cleaners
FACID NO. 61-9500991; ERIC_5504
Live Oak, Suwannee County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC008C (HW680) DATE: April 3, 2025
Arcadis U.S. Inc. will perform annual groundwater monitoring from select wells at the site. Groundwater monitoring will ensure that natural attenuation of contaminants continues to occur. Additionally, select wells will be sampled for PFAS compounds. All activities will be conducted in accordance with the March 24, 2025, Work Plan submitted by Mike O’Sullivan of Arcadis.
The cost on the original proposal equaled $18,078.82. The final negotiated task assignment total is $15,506.83. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.
Subtask 2: PFAS sampling Arcadis will sample two wells for PFAS compounds using FDEP’s laboratory in Tallahassee. The wells have been chosen based on prior PFAS results and FDEP’s new guidance/flow chart.
Subtask 3: Annual Groundwater Monitoring Arcadis will sample ten wells for drycleaning solvents based on recommendations from the previous monitoring report. IDW will be removed by a licensed waste hauler.
Kathy’s Cleaners
ERIC_5504
The final TA reduced the number of wells sampled from 12 to 10 and total hours from 40 to 33.
Subtask 4: Reporting An Annual Monitoring Report including recommendations for additional actions will be provided under this subtask. The DEP project manager reduced total reporting hours from 42 to 32.
FDEP COST ESTIMATE
Contractor: Arcadis, U.S., Inc.
Date: 3/24/25
Task #: SubTask 1 Project Management Site: Kathy's Cleaner SubTask 2 Groundwater Monitoring (PFAS)
Activity/Phase: Monitoring SubTask 3 Groundwater Monitoring (VOHs) Project Manager: Mike O'Sullivan SubTask 4 Reporting (PFAS & VOHs)
SubTask 5
Totals 1 2 3 4 5 Labor Rate Category
$63.17 Project Manager O'Sullivan, Mike (MOS) 8 8.0 $63.17 Principal Scientist O'Sullivan, Mike (MOS) 25 6 5 14 0 $38.15 Staff Scientist Martineau, Duncan (DM) 38 10 22 6 0 $39.67 Drafter/Designer Oliva, Brian (BO) 6 0 0 6 0 $38.28 Project Assistant Cruz, Michele (MC) 13 4 6 3 0 $35.00 Document Technician Ballheim, Debra (DJB) 3 0 0 3 0
Total Hours 93 8 20 33 32 0
Direct Labor $4,372.66 $503.05 $913.64 $1,384.83 $1,571.14 $0.00
Overhead 79.00% $3,454.41 $397.41 $721.78 $1,094.02 $1,241.20 $0.00 Gen & Admin 36.00% $1,574.16 $181.10 $328.91 $498.54 $565.61 $0.00 Fringe 37.10% $1,622.25 $186.63 $338.96 $513.77 $582.89 $0.00 Total Labor $11,023.48 $1,268.19 $2,303.29 $3,491.16 $3,960.84 $0.00
Travel Vehicle Rental $360.00 $120.00 $240.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $360.00 $120.00 $240.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin Remediation $125.00 $125.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $125.00 $125.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $12.50 $0.00 $0.00 $0.00 Total Subcontractor Cost $137.50 $137.50 $0.00 $0.00 $0.00
Laboratory Analytical Costs $730.00 $0.00 $730.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $300.00 $0.00 $300.00 $0.00 $0.00 Total Laboratory $1,030.00 $0.00 $1,030.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $120.00 $40.00 $80.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical releated) $872.00 $42.00 $830.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 Equipment (Other) $761.50 $415.00 $346.50 $0.00 $0.00 Total Field Expenses $1,853.50 $597.00 $1,256.50 $0.00 $0.00
Subtotal $14,404.48 $1,268.19 $3,157.79 $6,017.66 $3,960.84 $0.00 Completion Fee $1,102.35 $126.82 $230.33 $349.12 $396.08 $0.00
Total Estimated Cost $15,506.83 $1,395.01 $3,388.12 $6,366.78 $4,356.92 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE : Kathy's Cleaner SUBTASK 2: Groundwater Monitoring (PFAS)
DATE: 3/24/25
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Annual Groundwater Monitoring Principal Scientist Property owners verification, notification and site access agreement updates. Lab coordination. Field personnel ovesight. Staffing. 6 Scientist Mob/demob, prepare sampling kits/equipment, DTW/field measurements, purge and sample MWs. Pack and ship samples 10 Project Assistant Sample container ordering, preparation, electronic transcriptions of field data 4
TOTAL LABOR 20
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 1 $120.00 $120.00
TOTAL VEHICLE $120.00
SUBCONTRACTOR COSTS
Services Procurement Name Purpose Rate Units Usage Totals
Erwin Remediation IDW T&D $125.00 Per Drum 1 $125.00 Handling Fee 10% 1 $12.50
Total Services: $137.50
TOTAL $137.50
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons Only) 8260C Aqueous $73.00 1.00 0 $0.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $0.00
TOTAL LAB $0.00
EQUIPMENT
Item Rate Unit Usage Totals Expendables Miscellaneous Expendables $40.00 Per Day 1 $40.00
Total Expendables: $40.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 140 $42.00 55-gallon Drum $100.00 Each 1 $100.00
Total Equipment Items: $142.00 Deep Groundwater Sampling Kit $415.00 Day 1 $415.00
Total Equipment Kits: $415.00
Total Equipment $597.00
SUBTASK 3: Groundwater Monitoring (VOHs)
DATE: 3/24/25
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Annual Groundwater Monitoring Principal Scientist Property owners verification, notification and site access agreement updates. Lab coordination. Field personnel ovesight. Staffing. 5 Scientist Mob/demob, prepare sampling kits/equipment, DTW/field measurements, purge and sample MWs. Pack and ship samples 22 Project Assistant Sample container ordering, preparation, electronic transcriptions of field data 6
TOTAL LABOR 33
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 2 $240.00 $240.00
TOTAL VEHICLE $240.00
SUBCONTRACTOR COSTS
Services Procurement Name Purpose Rate Units Usage Totals
Erwin Remediation IDW T&D $125.00 Per Drum 0 $0.00 Handling Fee 10% 0 $0.00
Total Services: $0.00
TOTAL $0.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons Only) 8260C Aqueous $73.00 1.00 10 $730.00 TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $730.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 2 $300.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00
Total Shipping: $300.00
TOTAL LAB $1,030.00
EQUIPMENT
Item Rate Unit Usage Totals Expendables Miscellaneous Expendables $40.00 Per Day 2 $80.00
Total Expendables: $80.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 1155 $346.50 55-gallon Drum $100.00 Each 0 $0.00
Total Equipment Items: $346.50 Deep Groundwater Sampling Kit $415.00 Day 2 $830.00
Total Equipment Kits: $830.00
Total Equipment $1,256.50
SUBTASK 4: Reporting (PFAS & VOHs)
DATE: 3/24/25
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Data Evaluation and Letter Report Principal Scientist Data evaluation. Preparation of an Annual GW Monitoring Report, sign and seal report 14 Scientist Data evaluation 6 Drafter Figures preparation 6 Document Technician Editing; Report preparation 3 Project Assistant Report editing/formatting, and report production/submittal/delivery 3
TOTAL LABOR 32
Arcadis U.S., Inc.
1705 Metropolitan Boulevard Suite 101 Tallahassee Florida 32308 Phone: 850 422 2555 Fax: 850 668 0080 www.arcadis.com
FL Engineering License #7917 FL Geology License #GB564 FL Surveying License #LB7062
Ms. Theresa Pepe Bureau of Waste Cleanup Division of Waste Management Florida Department of Environmental Protection 2600 Blair Stone Road, M.S. 4520 Tallahassee, Florida 32399-2400
Date: March 24, 2025
Subject: Proposal for Annual Groundwater Monitoring at Kathy’s Cleaners, 202 West Howard Street, Live Oak, Florida, FDEP Facility Identification Number
ERIC_5504.
Dear Ms. Pepe, Arcadis U.S., Inc. (Arcadis) is pleased to submit this level of effort (LOE) and cost proposal for the annual groundwater monitoring activities at the Kathy’s Cleaners Facility located at 202 West Howard Street, Live Oak, Florida, (FDEP Facility Identification Number ERIC_5504; “the Site”). This proposal includes one groundwater monitoring event for PFAS, one groundwater monitoring event for VOHs, and one letter report summarizing both field activities and results. The FDEP cost estimating spreadsheets (Attachment A) and subcontractor quote (Attachment B) are attached.
SCOPE OF WORK
Subtask 1 - Project Management Subtask 1 is reserved for project management as specified by FDEP and is calculated automatically in the cost estimating form (Attachment A).
Subtask 2 - Groundwater Monitoring (PFAS) Arcadis proposes to mobilize to the Site to collect groundwater samples from two monitoring wells (MW008 and MW009) in accordance with FDEP SOPs. Monitoring well locations are shown on the attached figures. Samples will be submitted to FDEP’s Laboratory for PFAS analysis. Monitoring well purge water will be contained in 55-gallon drums, sampled for characterization, and disposed of properly.
Subtask 3 - Groundwater Monitoring (VOHs) Arcadis proposes to mobilize to the Site to collect groundwater samples from monitoring wells (MW001, MW002, MW005, MW006, MW008, MW009, MW010, MW011, MW012, MW013, MW014, and MW015) in accordance with FDEP SOPs. Monitoring well locations are shown on the attached figures. Samples will be submitted to a certified laboratory for analysis by EPA Method 8260C or equivalent (VOHs only). Monitoring well purge water will be contained in 55-gallon drums, sampled for characterization, and disposed of properly.
FDEP – Kathy’s Cleaner AGM Proposal 2025 www.arcadis.com _Kathys Cleaner GWM proposal_Mar2025
Subtask 5 - Reporting Arcadis will incorporate the data collected during the groundwater sampling events into a letter report summarizing the field activities. The report will include laboratory analytical data, figures presenting groundwater analytical data, a summary of the data, conclusions, and recommendations for future work at the Site.
SCHEDULE
Arrangements for groundwater sampling activities will be conducted upon receipt of a Task Assignment (TA) from the FDEP.
ESTIMATED COST
A Cost Estimate Form and Level of Effort forms (CEF/LOE) that present estimated project costs are included as
Attachment A.
Please contact me if you have any questions regarding this proposal.
Sincerely, Arcadis U.S., Inc.
Mike O’Sullivan, P.G.
Principal Geologist Email: mike.osullivan@arcadis.com Direct Line: 850.895.4739 Mobile: 850.491.2346
Attachment:
Figures Attachment A – Cost Estimate Form and Level of Effort forms Attachment B – Subcontractor quote