This document comprises two Task Assignment Change Orders (TACO 1 and TACO 2) issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S. Inc. for environmental services at the J & D Cleaners facility (ERIC_5422) located in Milton, Santa Rosa County, Florida. The contract is identified as HW680, with Task Assignment DC010B. Theresa Pepe serves as FDEP's Project Manager, while Gus Suarez represents Arcadis U.S. Inc. as the Contractor's Project Manager.
TACO 1, effective December 15, 2023, authorizes a 70-day time extension for obtaining site access, extending the completion date from January 12, 2024, to March 22, 2024, with no cost adjustment. TACO 2, effective March 4, 2024, provides an additional 110-day time extension for site access due to a change in property ownership, extending the completion date to July 10, 2024, also with no cost change. Both change orders maintain the total task assignment value of $12,214.75 on a fixed unit rate basis. The deliverable for both periods is an Annual Monitoring Report/IDW manifest/Project Management, with invoice authorization contingent upon FDEP approval. Under TACO 1, invoicing was scheduled for February 23, 2024; under TACO 2, invoicing is scheduled for May 31, 2024.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
DC010B 2 HW680
This change order authorizes a time extension of 110 days for obtaining site access.
Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor
Contractor Gus Suarez Contractor 813-205-4703
ERIC_5422
J & D Cleaners (former)
✔ $ 12,214.75 $ 12,214.75
$ 12,214.75 $ 12,214.75 Completion
✔ Completion 03/22/2024 07/10/2024 110
✔ 1 1 2
Arcadis U.S. Inc.
Contractor Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2024.03.04 14:12:37 -05'00'
Jennifer Farrell
Digitally signed by Jennifer Farrell Date: 2024.03.04 12:34:38 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW680
DC010B
$ 12,214.75
Annual Monitoring Report/IDW manifest/Project Management
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management
05/31/2024
$ 12,214.75
FFLORIDA DEPARTMENT OF
EEnvironmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette NNuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File J & D Cleaners Facility ID No. 57-9808602; ERIC_5422 Milton, Santa Rosa County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment Change Order DC010B-2 (HW680) DATE: March 1, 2024
The property has changed hands since the last fieldwork event. A time extension of one hundred ten days is added to obtain site access from the new property owner.
This change order adds 110 days to the completion date. There is no cost change to the task assignment. Arcadis may invoice according to the attached schedule.
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/17/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:
1. TA Number: TACO Number: Contract Number:
TACO Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department’s Project Manager: Department’s Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number) Project Name:
4. There are no changes to the TA compensation.
The compensation of the TA is changed to the amounts indicated below:
Amended Price Price Prior to TACO Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. There are no changes to the TA Expiration Date.
The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).
6. There are no changes to the Attachments.
Attachment ___ is replaced with Attachment -____.
7. No Additional Changes.
Additional Changes:
8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.
IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
Additional signatures attached on separate page.
DC010B 1 HW680
This change order authorizes a time extension of 70 days for obtaining site access.
Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor
Contractor Gus Suarez Contractor 813-205-4703
ERIC_5422
J & D Cleaners (former)
$ 0.00 $ 0.00 Completion
✔ Completion 01/12/2024 03/22/2024 70
✔ 1 1 1
Arcadis U.S. Inc.
Contractor Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2023.12.15 16:40:16 -05'00'
Kelly Crain
Kelly Crain Digitally signed by Kelly Crain Date: 2023.12.15 15:29:28 -05'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
HW680
DC010B
$ 12,214.75
Annual Monitoring Report/IDW manifest/Project Management
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management
02/23/2024
$ 12,214.75