CN-370000-HW680-DC08BCO1.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|HW680|454e104ae8fbcb5641ac6acc30583968
Contract number
HW680
Issued by
Florida

About this file

Task Assignment Change Order Summary

This is a Task Assignment Change Order (TACO) DC008B-1 for Contract HW680 between the State of Florida Department of Environmental Protection (FDEP) and Arcadis U.S. Inc. The change order amends the original Task Assignment DC008B for groundwater monitoring services at Kathy's Cleaners facility located at 202 West Howard Street in Live Oak, Suwannee County, Florida. The project is identified as ERIC_5504. Key personnel include Theresa Pepe as FDEP Project Manager (850-245-8966) and Gus Suarez as Arcadis Contract Manager (813-205-4703).

The change order reduces the total Task Assignment value from $17,916.56 to $17,615.56, a cost reduction of $301.00. This reduction reflects two primary adjustments: backout of costs for two unsampled wells in Subtask 4 (Annual Groundwater Monitoring), where only 10 of the originally planned 12 samples were collected due to missing wells, and adjustments to Subtask 2 (PFAS Monitoring) subcontractor costs for Investigation Derived Waste (IDW) handling after an IDW drum was stolen from the site before pickup. The contractor charged only a mobilization fee rather than full disposal costs. The Task Assignment completion date remains unchanged at September 30, 2024. Arcadis may invoice according to the attached schedule: $7,471.82 upon FDEP approval of the PFAS monitoring email summary and $10,143.74 upon FDEP approval of the Annual Monitoring Report/Project Management deliverables.

View the file

Other files

File Type Posted
CN-370000-HW680-DC003B.pdf PDF
CN-370000-HW680-DC003C.pdf PDF
CN-370000-HW680-DC003D.pdf PDF
CN-370000-HW680-DC004C.pdf PDF
CN-370000-HW680-DC004ECO.pdf PDF
CN-370000-HW680-DC004F.pdf PDF
CN-370000-HW680-DC009B.pdf PDF
CN-370000-HW680-DC009C.pdf PDF
CN-370000-HW680-DC011C.pdf PDF
CN-370000-HW680-DC011D.pdf PDF
CN-370000-HW680-DC013A.pdf PDF
CN-370000-HW680-DC013B.pdf PDF
CN-370000-HW680-DC014C.pdf PDF
CN-370000-HW680-DC015A.pdf PDF
CN-370000-HW680-DC016C.pdf PDF
CN-370000-HW680-DC016F.pdf PDF
CN-370000-HW680-DC019C.pdf PDF
CN-370000-HW680-DC01ACO1.pdf PDF
CN-370000-HW680-DC020B.pdf PDF
CN-370000-HW680-DC020C.pdf PDF
CN-370000-HW680-DC021B.pdf PDF
CN-370000-HW680-DC022B.pdf PDF
CN-370000-HW680-DC023B.pdf PDF
CN-370000-HW680-DC024A.pdf PDF
CN-370000-HW680-DC025A.pdf PDF
CN-370000-HW680-DC026B.pdf PDF
CN-370000-HW680-DC029A.pdf PDF
CN-370000-HW680-DC031A.pdf PDF
CN-370000-HW680-DC032C.pdf PDF
CN-370000-HW680-DC034C.pdf PDF
CN-370000-HW680-DC035A.pdf PDF
CN-370000-HW680-DC036A.pdf PDF
CN-370000-HW680-DC037A.pdf PDF
CN-370000-HW680-DC037B.pdf PDF
CN-370000-HW680-DC037C.pdf PDF
CN-370000-HW680-DC038B.pdf PDF
CN-370000-HW680-DC03ACO1.pdf PDF
CN-370000-HW680-DC040B.pdf PDF
CN-370000-HW680-DC045A.pdf PDF
CN-370000-HW680-DC048A.pdf PDF
CN-370000-HW680-DC050A.pdf PDF
CN-370000-HW680-DC051A.pdf PDF
CN-370000-HW680-DC052A.pdf PDF
CN-370000-HW680-DC053B.pdf PDF
CN-370000-HW680-DC054A.pdf PDF
CN-370000-HW680-DC06BCO2.pdf PDF
CN-370000-HW680-DC07ACO1.pdf PDF
CN-370000-HW680-DC07ACO2.pdf PDF
CN-370000-HW680-DC09BCO2.pdf PDF
CN-370000-HW680-DC09CCO1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection

(Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title:

Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

DC008B 1 HW680

This change order reduces costs for wells not sampled and adjusts subcontractor costs for IDW.

Theresa Pepe 850-245-8966 Arcadis U.S. Inc.

Gus Suarez 813-205-4703

ERIC_5504

Kathy's Cleaners

$ 17,615.56 $ 17,916.56

$ 17,615.56 $ 17,916.56

09/30/2024 09/30/2024 0

1 1 1

Arcadis U.S. Inc.

Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2024.09.17 09:41:28 -04'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2024.09.16 17:22:09 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center

2600 Blair Stone Road Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Interim Secretary

Memorandum

TO: Negotiation File Kathy’s Cleaners

FACID NO. 61-9500991; ERIC_5504

Live Oak, Suwannee County FROM: Theresa C. Pepe, Project Manager SUBJECT: Task Assignment Change Order DC008B-1 (HW680) DATE: September 13, 2024

This change order reduces costs for wells not sampled and adjusts subcontractor costs for Investigation Derived Waste (IDW). For additional information, see the September 12, 2024, change order memo from Mike O’Sullivan of Arcadis.

The original task assignment equaled $17,916.56. This change order deletes $301.00 for a new total of $17,615.56. There is no time change to the task assignment. Arcadis may invoice according to the attached schedule.

Clarifications to the affected subtasks are described below.

Subtask 2: PFAS Monitoring The IDW drum was stolen from the site before pickup. Therefore, the subcontractor charged only a mobilization fee but not the remaining costs. Costs are included in the attached documentation. One drum is removed from equipment charges. Appropriate handling fees per the approved HW680 contract are also adjusted.

Subtask 4: Annual Groundwater Monitoring The original task assignment included costs for twelve samples. Due to missing wells, only ten samples were collected. This subtask backs out the unused costs.

FDEP COST ESTIMATE

$85.87 Project Manager Suarez, Gus (GS)

$60.88 Principal Scientist O'Sullivan, Michael (MOS)

$28.94 Scientist Martineau, Duncan (DM)

$39.67 Drafter/Designer Oliva, Brian (BO)

$37.25 Project Assistant Cruz, Michele (MC)

79.00%

36.00%

37.10%

SITE : Kathy's Cleaners SUBTASK 2: PFAS Monitoring

DATE: 3/14/2024

LABOR CATEGORY

STAFF-TITLE WORK DESCRIPTION HOURS

Principal Scientist Property owners verification, notification and site access agreement updates, analyze data, PG field support 12

Scientist Mob/demob, prepare sampling kits/equipment, DTW/field measurements, purge and sample 7 MWs. Pack and ship samples, search/recover missing wells 18

Project Assistant Sample container ordering, preparation, electronic transcriptions of field data 8

TOTAL LABOR 38

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 2 $240.00 $240.00

TOTAL VEHICLE $240.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

Per Day $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

IDW Drum Transportation and Disposal IDW $125.00 Per Drum 0 $0.00

Mobilization Fee $75.00 Lump Sum 1 $75.00

Handling Fee 10% 1 $7.50

Total Services: $82.50

TOTAL $82.50

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $73.00 1.00 0 $0.00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $150.00

TOTAL LAB $150.00

EQUIPMENT

Expendables

Miscellaneous Expendables $40.00 Per Day 2 $80.00

Total Expendables: $80.00

Equipment Items

Tubing, Poly/HDPE $0.30 Per Foot 380 $114.00

55-gallon Drum $100.00 Each 0 $0.00

Total Equipment Items: $114.00

Equipment Kits

Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00

Deep Groundwater Sampling Kit $415.00 Day 1 $415.00

Total Equipment Kits: $705.00

TOTAL EQUIPMENT $899.00

SUBTASK 4: VOH Monitoring

DATE: 3/14/2024

LABOR CATEGORY

STAFF-TITLE WORK DESCRIPTION HOURS

Principal Scientist Property owners notification and site access agreement updates, analyze data, PG field support 0

Scientist Mob/demob, prepare sampling kits/equipment, DTW/field measurements, purge and sample 12 MWs. Pack and ship samples. Manage IDW 0

Project Assistant Sample container ordering, preparation, electronic transcriptions of field data 0

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 0 $0.00 $0.00

TOTAL VEHICLE $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

$0.00 Lump Sum $0.00

$0.00 Per Day $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

Erwin Remediation IDW Drum Transportation and Disposal $125.00 Per Drum 0 $0.00

Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $73.00 1.00 10 $730.00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $730.00

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB $730.00

EQUIPMENT

Expendables

Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00

Equipment Items

Tubing, Poly/HDPE $0.30 Per Foot 0 $0.00

Total Equipment Items: $0.00

Equipment Kits

Shallow Groundwater Sampling Kit $290.00 Day 0 $0.00

Deep Groundwater Sampling Kit $415.00 Day 0 $0.00

Total Equipment Kits: $0.00

TOTAL EQUIPMENT $0.00

Contractor: Arcadis, U.S., Inc.

Date: 3/14/2024

Task #: SubTask 1 Project Management Site: Kathy's Cleaners SubTask 2 PFAS Monitoring

Activity/Phase: Monitoring SubTask 3 PFAS Reporting Project Manager: Gus Suarez SubTask 4 VOH Monitoring

SubTask 5 VOH Reporting

Totals 1 2 3 4 5

Labor Rate Category

$85.87 Project Manager Suarez, Gus (GS) 0 0.0

$60.88 Principal Scientist O'Sullivan, Michael (MOS) 0 0 0 0 0

$28.94 Scientist Martineau, Duncan (DM) 0 0 0 0 0

$39.67 Drafter/Designer Oliva, Brian (BO) 0 0 0 0 0

$37.25 Project Assistant Cruz, Michele (MC) 0 0 0 0 0

Total Hours 0 0 0 0 0 0

Direct Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 79.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Gen & Admin 36.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 37.10% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel

Vehicle Rental $0.00 $0.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00

Total Travel $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW - T&D - Erwin Remediation ($50.00) ($50.00) $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal ($50.00) ($50.00) $0.00 $0.00 $0.00

Handling Fee ($5.00) ($5.00) $0.00 $0.00 $0.00

Total Subcontractor Cost ($55.00) ($55.00) $0.00 $0.00 $0.00

Laboratory

Analytical Costs ($146.00) $0.00 $0.00 ($146.00) $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $0.00 $0.00 $0.00 $0.00 $0.00

Total Laboratory ($146.00) $0.00 $0.00 ($146.00) $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (IDW related) ($100.00) ($100.00) $0.00 $0.00 $0.00

Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses ($100.00) ($100.00) $0.00 $0.00 $0.00

Subtotal ($301.00) $0.00 ($155.00) $0.00 ($146.00) $0.00

Completion Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost ($301.00) $0.00 ($155.00) $0.00 ($146.00) $0.00

REV: 02/03 CEF ARCADIS Page 1

DATE: 3/14/2024

LABOR CATEGORY

STAFF-TITLE WORK DESCRIPTION HOURS

Principal Scientist Property owners verification, notification and site access agreement updates, analyze data, PG field support 0

Scientist Mob/demob, prepare sampling kits/equipment, DTW/field measurements, purge and sample 7 MWs. Pack and ship samples, search/recover missing wells 0

Project Assistant Sample container ordering, preparation, electronic transcriptions of field data 0

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 0 $0.00 $0.00

TOTAL VEHICLE $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

$0.00 Lump Sum $0.00

$0.00 Per Day $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

Erwin Remediation IDW Drum Transportation and Disposal $125.00 Per Drum -1 ($125.00)

Handling Fee 10% -1 ($12.50)

Mobilization Fee $75.00 1 $75.00

Handling Fee 10% 1 $7.50

Total Services: ($55.00)

TOTAL ($55.00)

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $73.00 1.00 0 $0.00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB $0.00

EQUIPMENT

Expendables

Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00

Equipment Items

Tubing, Poly/HDPE $0.30 Per Foot 0 $0.00

55-gallon Drum $100.00 Each -1 ($100.00)

Total Equipment Items: ($100.00)

Equipment Kits

Shallow Groundwater Sampling Kit $290.00 Day 0 $0.00

Deep Groundwater Sampling Kit $415.00 Day 0 $0.00

TOTAL EQUIPMENT ($100.00)

DATE: 3/14/2024

LABOR CATEGORY

STAFF-TITLE WORK DESCRIPTION HOURS

Principal Scientist Property owners notification and site access agreement updates, analyze data, PG field support 0

Scientist Mob/demob, prepare sampling kits/equipment, DTW/field measurements, purge and sample 12 MWs. Pack and ship samples. Manage IDW 0

Project Assistant Sample container ordering, preparation, electronic transcriptions of field data 0

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 0 $0.00 $0.00

TOTAL VEHICLE $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

$0.00 Lump Sum $0.00

$0.00 Per Day $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

Erwin Remediation IDW Drum Transportation and Disposal $125.00 Per Drum 0 $0.00

Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $73.00 1.00 -2 ($146.00)

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: ($146.00)

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $0.00

TOTAL LAB ($146.00)

EQUIPMENT

Expendables

Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00

Equipment Items

Tubing, Poly/HDPE $0.30 Per Foot 0 $0.00

Total Equipment Items: $0.00

Equipment Kits

Shallow Groundwater Sampling Kit $290.00 Day 0 $0.00

Deep Groundwater Sampling Kit $415.00 Day 0 $0.00

TOTAL EQUIPMENT $0.00

Contractor: Arcadis, U.S., Inc.

Date: 3/14/2024

Task #: SubTask 1 Project Management Site: Kathy's Cleaners SubTask 2 PFAS Monitoring

Activity/Phase: Monitoring SubTask 3 PFAS Reporting Project Manager: Gus Suarez SubTask 4 VOH Monitoring

SubTask 5 VOH Reporting

Totals 1 2 3 4 5

Labor Rate Category

$85.87 Project Manager Suarez, Gus (GS) 7 6.9

$60.88 Principal Scientist O'Sullivan, Michael (MOS) 34 12 4 6 12

$28.94 Scientist Martineau, Duncan (DM) 52 18 6 26 2

$39.67 Drafter/Designer Oliva, Brian (BO) 8 0 4 0 4

$37.25 Project Assistant Cruz, Michele (MC) 18 8 2 4 4

Total Hours 119 7 38 16 36 22

Direct Labor $5,155.81 $593.15 $1,549.48 $650.34 $1,266.72 $1,096.12

Overhead 79.00% $4,073.09 $468.59 $1,224.09 $513.77 $1,000.71 $865.93

Gen & Admin 36.00% $1,856.08 $213.53 $557.81 $234.12 $456.02 $394.60

Fringe 37.10% $1,912.81 $220.06 $574.86 $241.28 $469.95 $406.66

Total Labor $12,997.79 $1,495.33 $3,906.24 $1,639.51 $3,193.40 $2,763.31

Travel

Vehicle Rental $240.00 $240.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00

Total Travel $240.00 $240.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00

IDW - T&D - Erwin Remediation $125.00 $125.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $125.00 $125.00 $0.00 $0.00 $0.00

Handling Fee $12.50 $12.50 $0.00 $0.00 $0.00

Total Subcontractor Cost $137.50 $137.50 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $876.00 $0.00 $0.00 $876.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $300.00 $150.00 $0.00 $150.00 $0.00

Total Laboratory $1,176.00 $150.00 $0.00 $1,026.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $80.00 $80.00 $0.00 $0.00 $0.00

Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $475.50 $114.00 $0.00 $361.50 $0.00

Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00

Equipment (Other) $1,410.00 $705.00 $0.00 $705.00 $0.00

Total Field Expenses $2,065.50 $999.00 $0.00 $1,066.50 $0.00

Subtotal $16,616.79 $1,495.33 $5,432.74 $1,639.51 $5,285.90 $2,763.31

Completion Fee $1,299.77 $149.53 $390.62 $163.95 $319.34 $276.33

Total Estimated Cost $17,916.56 $1,644.86 $5,823.36 $1,803.46 $5,605.24 $3,039.64

REV: 02/03 CEF ARCADIS Page 1

DATE: 3/14/2024

LABOR CATEGORY

STAFF-TITLE WORK DESCRIPTION HOURS

Principal Scientist Property owners verification, notification and site access agreement updates, analyze data, PG field support 12

Scientist Mob/demob, prepare sampling kits/equipment, DTW/field measurements, purge and sample 7 MWs. Pack and ship samples, search/recover missing wells 18

Project Assistant Sample container ordering, preparation, electronic transcriptions of field data 8

TOTAL LABOR 38

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 2 $240.00 $240.00

TOTAL VEHICLE $240.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

$0.00 Lump Sum $0.00

$0.00 Per Day $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

Erwin Remediation IDW Drum Transportation and Disposal $125.00 Per Drum 1 $125.00

Handling Fee 10% 1 $12.50

Total Services: $137.50

TOTAL $137.50

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $73.00 1.00 0 $0.00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $0.00

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $150.00

TOTAL LAB $150.00

EQUIPMENT

Expendables

Miscellaneous Expendables $40.00 Per Day 2 $80.00

Total Expendables: $80.00

Equipment Items

Tubing, Poly/HDPE $0.30 Per Foot 380 $114.00

55-gallon Drum $100.00 Each 1 $100.00

Total Equipment Items: $214.00

Equipment Kits

Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00

Deep Groundwater Sampling Kit $415.00 Day 1 $415.00

TOTAL EQUIPMENT $999.00

SUBTASK 3: PFAS Reporting

DATE: 3/14/2024

LABOR CATEGORY

STAFF-TITLE WORK DESCRIPTION HOURS

Principal Scientist Data evaluation and preparation of deliverable 4

Scientist Prepare and submit field notes, sample forms, lab report and figure. 6

Drafter / BO Figures production for report 4

Project Asst - MMc Process field notes, submittals 2

TOTAL LABOR 16

DATE: 3/14/2024

LABOR CATEGORY

STAFF-TITLE WORK DESCRIPTION HOURS

Principal Scientist Property owners notification and site access agreement updates, analyze data, PG field support 6

Scientist Mob/demob, prepare sampling kits/equipment, DTW/field measurements, purge and sample 12 MWs. Pack and ship samples. Manage IDW 26

Project Assistant Sample container ordering, preparation, electronic transcriptions of field data 4

TOTAL LABOR 36

VEHICLE TYPE RATE UNIT USEAGE

Automobile $80.00 Per Day 0 $0.00 $0.00

Van/Truck $120.00 Per Day 0 $0.00 $0.00

TOTAL VEHICLE $0.00

SUBCONTRACTOR COSTS

Equipment Procurement

Name Equipment Rate Units Usage Totals

$0.00 Lump Sum $0.00

$0.00 Per Day $0.00

Total Equip.: $0.00

Services Procurement

Name Purpose Rate Units Usage Totals

Erwin Remediation IDW Drum Transportation and Disposal $125.00 Per Drum 0 $0.00

Total Services: $0.00

TOTAL $0.00

LABORATORY COSTS

Analytical Costs

Parameter Method Media Rate Turn Around Total Samples Totals

VOC (Halocarbons Only) 8260C Aqueous $73.00 1.00 12 $876.00

TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $876.00

Rate Units Usage

Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 1 $150.00

Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 0 $0.00

Total Shipping: $150.00

TOTAL LAB $1,026.00

EQUIPMENT

Expendables

Miscellaneous Expendables $40.00 Per Day 0 $0.00

Total Expendables: $0.00

Equipment Items

Tubing, Poly/HDPE $0.30 Per Foot 1205 $361.50

Total Equipment Items: $361.50

Equipment Kits

Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00

Deep Groundwater Sampling Kit $415.00 Day 1 $415.00

TOTAL EQUIPMENT $1,066.50

SUBTASK 5: VOH Reporting

DATE: 3/14/2024

LABOR CATEGORY

STAFF-TITLE WORK DESCRIPTION HOURS

Principal Scientist Data evaluation, preparation of a text, tables, and figures for report. PG certification of report. 12

Scientist Summarize Data 2

Drafter / BO Figure generation, ADaPT database entry 4

Project Asst - MMc Report assembly and submittal 4

TOTAL LABOR 22

From: OSullivan, Mike To: Pepe, Theresa Subject: Re: Annual Monitoring Report, Kathy’s Cleaners (ERIC_5504) - TA DC008B Date: Thursday, September 12, 2024 11:00:55 AM Attachments: image002.png image003.png image004.png image005.png image006.png Outlook-u0k0mhes.png Outlook-A picture .png Outlook-Shape Des.png Outlook-Shape Des.png Outlook-Shape Des.png HW680 CEF (ARC)_2024_Kathys PFAS & VOH GWM 2024 - Final.xlsx HW680 CEF (ARC)_2024_Kathys PFAS & VOH GWM 2024.xlsm HW680 CEF (ARC)_2024_Kathys PFAS & VOH GWM 2024 - Delta.xlsm

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Theresa, Please see attached.

Thanks, Mike

Mike O’Sullivan PG Principal Geologist Arcadis U.S., Inc.

1705 Metropolitan Boulevard Tallahassee, FL | 32308 | USA T +1 850 895 4739 M +1 850 491 2346 www.arcadis.com

Professional Geologist / PG-FL, 2468

From: Pepe, Theresa <Theresa.Pepe@FloridaDEP.gov> Sent: Friday, September 6, 2024 3:01 PM To: OSullivan, Mike <Mike.OSullivan@arcadis.com> Subject: RE: Annual Monitoring Report, Kathy’s Cleaners (ERIC_5504) - TA DC008B

Arcadis Warning: Exercise caution with email messages from external sources such as this message. Always verify the sender and avoid clicking on links or scanning QR codes unless certain of their authenticity.

Good afternoon Mike, The Waste Site Cleanup Section has reviewed the Kathy’s annual report. We concur with continued annual monitoring for drycleaning solvents. We also concur with confirming

PFAS in MW008 and MW009.

The TA included costs for 12 samples. Some wells could not be located and only 10 samples (including IDW) were received by the lab. Please submit a TACO to backout the 2 unused samples. Also include the difference in IDW costs since the drum was stolen from the site.

Please contact me with any questions. Thank you.

Theresa C. Pepe, FCCM Environmental Consultant Florida Department of Environmental Protection Waste Management/Waste Site Cleanup Section Theresa.Pepe@FloridaDEP.gov 2600 Blairstone Rd. MS 4520 Tallahassee, FL 32399-2400 Office: 850-245-8705 Direct: 850-245-8966

From: OSullivan, Mike <Mike.OSullivan@arcadis.com> Sent: Tuesday, August 6, 2024 9:19 AM To: Pepe, Theresa <Theresa.Pepe@FloridaDEP.gov> Subject: Annual Monitoring Report, Kathy’s Cleaners (ERIC_5504) - TA DC008B

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Theresa, Please see the attached Annual Monitoring Report summarizing groundwater monitoring activities conducted at the Kathy’s Cleaners facility located at 202 West Howard Street in Live Oak, Florida. This report is intended to meet the deliverable requirements of Florida Department of Environmental Protection (FDEP) Task Assignment DC008B.

Thank you, Mike

Mike O’Sullivan PG Principal Geologist Arcadis U.S., Inc.

1705 Metropolitan Boulevard Tallahassee, FL | 32308 | USA T +1 850 895 4739 M +1 850 491 2346 www.arcadis.com

Professional Geologist / PG-FL, 2468

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor�st �s Project Manager: ontractor�s t�s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

HW680

DC008B Completion September 30, 2024

Arcadis will conduct annual groundwater monitoring from select wells. This monitoring event also includes PFAS delineation. All activities will be performed according to the March 14, 2024, Work Plan submitted by Arcadis.

Theresa Pepe 850-245-8966 Contractor Arcadis U.S. Inc. Contractor

Contractor Gus Suarez Contractor 813-205-4703

ERIC_5504

202 West Howard Street, Live Oak, Suwannee County

Kathy's Cleaners

Contractor Contractor

$ 17,916.56

$ 17,916.56

Scope of Work

Arcadis U.S. Inc.

Contractor

Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2024.03.20 11:58:56 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2024.03.19 16:16:45 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WC TAFORM

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

PFAS monitoring email summary 07/19/2024

Annual Monitoring Report/IDW manifest/Project Management 08/16/2024

FDEP approval of PFAS monitoring email summary $ 7,626.82

FDEP approval of Annual Monitoring Report/IDW manifest/Project Management $ 10,289.74

$ 17,916.56

HW680

DC008B