About this file

This is a Task Assignment (TA) document issued by the State of Florida Department of Environmental Protection (FDEP) to Arcadis U.S. Inc. for work at the Devonaire Cleaners site located at 12205 SW 112th Street, Miami, Miami-Dade County. The Task Assignment is issued under Contract Number HW680 and is designated as TA Number DC054A. The Department Project Manager is Theresa Pepe (850-245-8966), and the Contractor's Project Manager is Gus Suarez (813-205-4703). The assignment became effective on February 19, 2026, with a completion date of June 12, 2026.

Arcadis U.S. Inc. is authorized to generate a Site Assessment Work Plan (SAWP) for the Devonaire Cleaners facility in accordance with the attached SAWP Task List. The compensation structure is a fixed unit rate of $5,000.00, with a total Task Assignment value of $5,000.00. The single deliverable is the Initial Site Assessment Work Plan, due on March 31, 2026. Invoice payment of the full $5,000.00 is contingent upon FDEP approval of the Initial Site Assessment Work Plan. The SAWP must include site review documentation, site visit findings, a completed drycleaning site visit checklist, site summary narrative with conceptual site model, figures depicting site features and proposed sampling locations, a sampling plan/checklist, proposed schedule for completion through Site Assessment Report submittal, and cost estimate/level of effort worksheets. The work scope explicitly excludes documents available in ERIC or HASPs, EDR or ESA-like reports, offsite property surveys, potable well surveys, but must include PFAS screening as specified in guidance documentation.

View the file

Other files

File Type Posted
CN-370000-HW680-DC001B.pdf PDF
CN-370000-HW680-DC001E.pdf PDF
CN-370000-HW680-DC001F.pdf PDF
CN-370000-HW680-DC005A.pdf PDF
CN-370000-HW680-DC005B.pdf PDF
CN-370000-HW680-DC006C.pdf PDF
CN-370000-HW680-DC007C.pdf PDF
CN-370000-HW680-DC008C.pdf PDF
CN-370000-HW680-DC009A.pdf PDF
CN-370000-HW680-DC009D.pdf PDF
CN-370000-HW680-DC010A.pdf PDF
CN-370000-HW680-DC010B.pdf PDF
CN-370000-HW680-DC011A.pdf PDF
CN-370000-HW680-DC012A.pdf PDF
CN-370000-HW680-DC014D.pdf PDF
CN-370000-HW680-DC015F.pdf PDF
CN-370000-HW680-DC016A.pdf PDF
CN-370000-HW680-DC017A.pdf PDF
CN-370000-HW680-DC017D.pdf PDF
CN-370000-HW680-DC019A.pdf PDF
CN-370000-HW680-DC019B.pdf PDF
CN-370000-HW680-DC020D.pdf PDF
CN-370000-HW680-DC021A.pdf PDF
CN-370000-HW680-DC022A.pdf PDF
CN-370000-HW680-DC026D.pdf PDF
CN-370000-HW680-DC029B.pdf PDF
CN-370000-HW680-DC030A.pdf PDF
CN-370000-HW680-DC033A.pdf PDF
CN-370000-HW680-DC034A.pdf PDF
CN-370000-HW680-DC039B.pdf PDF
CN-370000-HW680-DC03BCO1.pdf PDF
CN-370000-HW680-DC03DCO1.pdf PDF
CN-370000-HW680-DC03DCO2.pdf PDF
CN-370000-HW680-DC040A.pdf PDF
CN-370000-HW680-DC041B.pdf PDF
CN-370000-HW680-DC041C.pdf PDF
CN-370000-HW680-DC046B.pdf PDF
CN-370000-HW680-DC047B.pdf PDF
CN-370000-HW680-DC048B.pdf PDF
CN-370000-HW680-DC049A.pdf PDF
CN-370000-HW680-DC050B.pdf PDF
CN-370000-HW680-DC051B.pdf PDF
CN-370000-HW680-DC07BCO1.pdf PDF
CN-370000-HW680-DC07CCO1.pdf PDF
CN-370000-HW680-DC09ACO1.pdf PDF
CN-370000-HW680-DC10ACO1.pdf PDF
CN-370000-HW680-DC10BCO2.pdf PDF
CN-370000-HW680-DC10BCO3.pdf PDF
CN-370000-HW680-DC11BCO1.pdf PDF
CN-370000-HW680-DC13DC01.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/26/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .

1. TA Number: TA Completion Date:

TA Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department Project Manager: Department Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Location(s):

Project Name:

4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:

☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:

Attachment 1:

☐ Additional Attachments (if necessary):

IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

HW680

DC054A Completion June 12, 2026

This Task Assignment authorizes Arcadis to generate a Site Assessment Work Plan for Devonaire Cleaners in accordance with the attached Site Assessment Work Plan Task List.

Theresa Pepe 850-245-8966 Contractor Contractor

Contractor Contractor

Contractor Contractor

Contractor

Arcadis U.S. Inc.

Arcadis U.S. Inc.

Gus Suarez 813-205-4703

ERIC_4485

12205 SW 112th St, Miami, Miami-Dade County

Devonaire Cleaners

✔ $ 5,000.00

$ 5,000.00

Scope of Work

Gus Suarez

Contract Manager

Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.

Date: 2026.02.23 09:04:24 -05'00'

Mubeen Darji

Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.

Date: 2026.02.19 15:08:00 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 04-2017

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

Initial Site Assessment Work Plan 03/31/2026

FDEP approval of Initial Site Assessment Work Plan $ 5,000.00

$ 5,000.00

HW680

DC054A

Site Assessment Work Plan (SAWP) Task List

Site Review:

1. Information Portal/ERIC/OCULUS Review

a. Review applicable documents

b. Application

c. Site Screening Report

d. Other assessment data

e. Permitting/Compliance/Enforcement history

2. Additional information as available and as needed

a. Google maps, aerial photographs, topographical maps, building/planning department records, land use maps, insurance maps

b. Other regulatory agency records

c. Contact DC operator for operations history. May be able to find operator even if DC is no longer operating

Site Visit:

1. Complete Drycleaning Site Visit Checklist

2. Verify Site Screening Report information, especially sample location(s)

3. Identify likely source/release areas (machine location, service door, floor drains, lint trap, sewer line, septic tank, dumpster, ASTs/USTs). Look for evidence on floors/walls for former machine location.

4. Identify above/below ground utilities and potential impediments to assessment activities

5. Verify accuracy of site map, revise as necessary

6. Interview operator/owner for site history

7. Discuss work plan elements with property owner and get direction regarding approach to tenants, and schedule.

SAWP:

1. Completed Drycleaning Site Visit Checklist

2. Site summary/narrative – Initial conceptual site model (brief text)

- Current status and history of DC operations

- Primary solvents used both prior to and after eligibility determination

- Owner/operator/tenant information

- Status of site structures (original, renovated, razed/redeveloped, vacant)

- Historical site assessment/remediation information

- Anticipated lithology, depth to water, and groundwater flow direction

- Known or anticipated source areas -Site Assessment Approach

3. Figures

- Topo

- Site features, aerial view, facility layout, waste storage areas, utilities, etc.

- Proposed sampling locations (soil, MAGS, DPT profiling, MWs, sediment, surface water, sewer/septic/lint trap)

4. Sampling Plan/Checklist (templated, see Word SAWP Summary Checklist) - Including proposed number of samples for soil, MAGs, groundwater, etc.

5. Proposed schedule from approval of SAWP to submittal of SAR

6. Cost Estimate (CE)/Level of Effort (LOE) Worksheets, including subcontractor quotes, as appropriate. The CE/LOE should be submitted upon approval of the SAWP and under separate cover.

Notes: 1) No documents that are available in ERIC or HASPs should be included with the SAWP, 2) No EDR or other ESA-like reports are required, 3) No offsite property owner/use or well survey information is required, 4) No potable well survey, 5) SOW should include PFAS screening (see guidance)

Peerless Cleaners #3416 Annual Monitoring Proposal 4-18-2022.pdf
Annual Groundwater Monitoring
Annual Groundwater Monitoring Report
Schedule
Cost Estimate
Closing Remarks