This Task Assignment (TA) DC003B is entered into between the State of Florida Department of Environmental Protection (FDEP) and Arcadis U.S. Inc. for environmental remediation services at the Former Silver Hanger Cleaners site located at 305 E Blanding Boulevard, Orange Park, Clay County, Florida (FDEP Facility ID: 10-9501908; ERIC_4265). The TA is issued under Contract Number HW680 and was executed on June 5, 2023, with a completion date of October 27, 2023. Theresa Pepe serves as the FDEP Project Manager, and Gus Suarez, P.E., serves as the Contractor's Project Manager. The task represents a continuation of natural attenuation monitoring activities at the site following the completion of active remediation efforts in 2020.
Arcadis will conduct annual groundwater monitoring from five select monitoring wells (MW001, MW003, MW005, MW007, and MW-009) and submit an Annual Monitoring Report including recommendations for additional actions, all performed according to the May 26, 2023 Work Plan. The contract is structured as a fixed unit rate contract with a Total TA Value of $5,068.14, composed of two subtasks: Subtask 1 (Project Management) at $435.77 and Subtask 2 (Annual Monitoring & Reporting) at $4,632.37. Groundwater samples will be analyzed for volatile organic halocarbons per USEPA Method 8260, with sampling activities performed in accordance with FDEP Standard Operating Procedure DEP-SOP-001/01. Costs include direct labor, overhead, general and administrative expenses, fringe benefits, vehicle rental, laboratory analysis, and waste disposal services through EnviroServe. The single deliverable (Annual Monitoring Report/IDW manifest/Project Management) is due September 29, 2023, with invoice payment due upon FDEP approval of the deliverables.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW680
DC003B Completion October 27, 2023
Arcadis will conduct annual groundwater monitoring from select wells at the site. All activities will be performed according to the May 26, 2023, Work Plan submitted by Arcadis.
Theresa Pepe 850-245-8966 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
Arcadis U.S. Inc.
Arcadis U.S. Inc.
Gus Suarez 813-205-4703
ERIC_4265
305-E Blanding Blvd, Orange Park, Clay County
Silver Hanger Cleaners
✔ $ 5,068.14
$ 5,068.14
Scope of Work
Gus Suarez
Contract Manager
Gus Suarez, P.E. Digitally signed by Gus Suarez, P.E.
Date: 2023.06.05 16:02:14 -04'00'
Kelly Crain
Kelly Crain Digitally signed by Kelly Crain Date: 2023.06.05 15:38:09 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Annual Monitoring Report/IDW manifest/Project Management 09/29/2023
FDEP approval of Annual Monitoring Report/IDW manifest/Project Management $ 5,068.14
$ 5,068.14
HW680
DC003B
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
Memorandum
TO: Negotiation File Silver Hanger Cleaners
FACID NO. 10-9501908; ERIC_4265
Orange Park, Clay County FROM: Theresa Pepe, Project Manager SUBJECT: Task Assignment DC003B (HW680) DATE: June 2, 2023
Arcadis U.S. Inc. will perform annual groundwater monitoring from select wells at the site. Groundwater monitoring will ensure that natural attenuation of contaminants continues to occur. Natural attenuation is expected to bring the site to unconditional closure. All activities will be conducted in accordance with the May 26, 2023, Work Plan submitted by Gus Suarez of Arcadis.
The final task assignment total is $5,068.14. Arcadis may invoice according to the attached schedule.
Specific negotiated subtasks are as follows:
Subtask 1: Project Management Project Management is automatically calculated as a percentage of total labor.
Subtask 2: Annual Monitoring & Reporting The Waste Site Cleanup Section obtained a signed site access form from the present owner on May 25, 2023.
Arcadis will sample five wells for drycleaning solvents based on recommendations from the previous monitoring report. IDW will be drummed and disposed by a licensed waste hauler per FDEP’s preference. An Annual Monitoring Report including recommendations for additional actions will be provided under this subtask.
Hours and costs are comparable to past task assignments of similar scope.
FDEP COST ESTIMATEContractor: Arcadis, U.S., Inc.
Date: 5/26/2023
Task #: SubTask 1 Project Management Site: Silver Hanger Cleaners SubTask 2 Annual NAM Sampling and Reporting
Activity/Phase: Annual NAM 2023 SubTask 3 Project Manager: Gus Suarez SubTask 4
SubTask 5
Totals 1 2 3 4 5 Labor Rate Category
$85.87 Project Manager Suarez, Gus (GS) 2 1.8 $85.87 Principal Engineer Suarez, Gus (GS) 4 4 0 0 0 $67.07 Principal Scientist Burke, Brian (BRB) 0 0 0 0 0 $50.00 Senior Engineer Hanna, Chad (CH) 0 0 0 0 0 $44.00 Project Engineer Romero Cotrino, Camilo (CR) 5 5 0 0 0 $28.94 Scientist Brooks, Eric (EAB) 5 5 0 0 0 $33.40 Technician Dankerl, David (DJD) 11 11 0 0 0$30.80 Technician Fortner, Kendrix (KLF) 0 0 0 0 0 $39.67 Drafter/Designer Oliva, Brian (BO) 0 0 0 0 0 $34.40 Drafter/Designer Berndgen, Wendy (WDB) 3 3 0 0 0 $35.00 Document Technician Ballheim, Debra (DJB) 0 0 0 0 0 $30.00 Document Technician Embras, Susan (SRE) 1 1 0 0 0 $37.25 Project Assistant Cruz, Michele (MC) 0 0 0 0 0
Total Hours 31 2 29 0 0 0
Direct Labor $1,365.92 $157.14 $1,208.78 $0.00 $0.00 $0.00
Overhead 79.00% $1,079.08 $124.14 $954.94 $0.00 $0.00 $0.00 Gen & Admin 36.00% $491.73 $56.57 $435.16 $0.00 $0.00 $0.00 Fringe 37.10% $506.76 $58.30 $448.46 $0.00 $0.00 $0.00 Total Labor $3,443.49 $396.15 $3,047.34 $0.00 $0.00 $0.00
Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 IDW EnviroServe $198.00 $198.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $198.00 $198.00 $0.00 $0.00 $0.00 Handling Fee $19.80 $19.80 $0.00 $0.00 $0.00 Total Subcontractor Cost $217.80 $217.80 $0.00 $0.00 $0.00
Laboratory Analytical Costs $365.00 $365.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $110.00 $110.00 $0.00 $0.00 $0.00 Total Laboratory $475.00 $475.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $37.50 $37.50 $0.00 $0.00 $0.00 Equipment (IDW related) $100.00 $100.00 $0.00 $0.00 $0.00 Equipment (Other) $290.00 $290.00 $0.00 $0.00 $0.00 Total Field Expenses $467.50 $467.50 $0.00 $0.00 $0.00
Subtotal $4,723.79 $396.15 $4,327.64 $0.00 $0.00 $0.00 Completion Fee $344.35 $39.62 $304.73 $0.00 $0.00 $0.00
Total Estimated Cost $5,068.14 $435.77 $4,632.37 $0.00 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
SITE : Silver Hanger Cleaners SUBTASK 2: Annual NAM Sampling and Reporting
DATE:
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
GW sampling
Principal (GS) PE field support 1
Project (CR) IDW management and field support 2
Technician (DJD) Preparation(1), Mobilization/demob (5 hrs), GW sampling (5 hrs) 11
Reporting Principal (GS) PE Analysis/certification 3
Project (CR) Report validation 3
Scientist (EB) Report Prep- Tables, Text, Figures 5
Drafter (WDB) Figures 3
Document Technician (SRE) Database management 1
TOTAL LABOR 29
VEHICLE TYPE RATE UNIT USEAGE
Automobile $80.00 Per Day 0 $0.00 $0.00 Van/Truck $120.00 Per Day 1 $120.00 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
Meals Category/Staff Rate Unit Usage Totals
$36.00 Per Day 0 $0.00 $36.00 Per Day 0 $0.00
Hotel Category/Staff Rate Unit Usage Totals
$150.00 Per Day 0 $0.00 $150.00 Per Day 0 $0.00
Total Meal/Hotel: $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
Equipment Procurement
Name Equipment Rate Units Usage Totals $0.00 Per Day 1 $0.00
Total Equip.: $0.00 Services Procurement
Name Purpose Rate Units Usage Totals NAME OF COMPANY Direct-push services $0.00 Lump Sum 0 $0.00 NAME OF COMPANY Drilling services (DPT, MAG wells, SBs, VPs) $0.00 Lump Sum 0 $0.00 EnviroServe IDW $198.00 Drum 1 $198.00
Handling Fee $0.00 Per Month 0 $0.00
Total Services: $198.00
TOTAL $198.00
LABORATORY COSTS
Analytical Costs Parameter Method Media Rate Turn Around Total Samples Totals
VOC (Halocarbons only) 8260 Aqueous $73.00 1.00 5 $365.00Dissolved Solids, Total SM2540 C Aqueous $16.00 1.00 0 $0.00 Priority Pollutant Organics Full Suite Aqueous $735.00 1.00 0 $0.00
TAT 24-hr=110% (2.1) 3-day=65% (1.65) 1-week=20% (1.20) Total Lab: $365.00
Rate Units Usage Shipping - Large (25 to 50 lbs.) --- --- $150.00 Per Cooler 0 $0.00 Shipping - Small (0 to 25 lbs.) --- --- $110.00 Per cooler 1 $110.00
Total Shipping: $110.00
TOTAL LAB $475.00
EQUIPMENT
Personal Protection
Item Rate Unit Usage Totals Total PPE: $0.00
Expendables Miscellaneous Expendables $40.00 Per Day 1 $40.00
Total Expendables: $40.00 Equipment Items Tubing, Poly/HDPE $0.30 Per Foot 75 $22.50 Tubing, Silicon 3/16x3/8 $3.00 Per Foot 5 $15.00 55-gallon Drum $100.00 Each 1 $100.00
Total Equipment Items: $137.50 Equipment KitsSite Reconnaissance Kit $150.00 Day 0 $0.00 Shallow Groundwater Sampling Kit $290.00 Day 1 $290.00Deep Groundwater Sampling Kit $415.00 Day 0 $0.00
Total Equipment Kits: $290.00
TOTAL EQUIPMENT $467.50
Arcadis U.S., Inc.
4300 West Cypress Street Suite 450 Tampa Florida 33607 Phone: 813 903 3100 Fax: 813 903 9115 www.arcadis.com
FL Engineering License #7917 FL Geology License #GB564 FL Surveying License #LB7062
1/2
Ms. Theresa Pepe Florida Department of Environmental Protection Waste Site Cleanup Section 2600 Blairstone Road, MS 4520 Tallahassee, FL 32399-2400
Date: May 26, 2023 Our Ref: 30019405 Subject: Natural Attenuation Monitoring Proposal Former Silver Hanger Cleaners 305 E Blanding Boulevard Orange Park, Florida FDEP Facility ID: 10/9501908 ERIC_4265 Contract No.: HW557
Dear Ms. Pepe, Arcadis U.S., Inc. (Arcadis) is pleased to submit to the Florida Department of Environmental Protection (FDEP) the following proposal to continue the Natural Attenuation Monitoring (NAM) Program at the Former Silver Hanger Cleaners (Site), located in Orange Park, Florida. This proposal includes background information, a description of the proposed scope of work (SOW), and an estimated cost and schedule for their completion.
Site Background
The Site is located within the Tuesday Morning Shopping Plaza on Blanding Boulevard just north of Cleveland Avenue in Clay County. The current owner of the Site is Khazaal Investment Group LLC. The Site consists of one unit within the shopping plaza and is currently operating as a Liquor Store.
Following the completion of active remediation efforts in 2020, the site entered into a semi-annual NAM program that continued throughout 2021. On February 8, 2022, the FDEP issued a TA to continue the NAM activities at the Site on an annual basis. As the subject property was recently sold, a new site access agreement was required. Arcadis submitted a new site access agreement via certified mail and email to the property owner.
Despite the multiple efforts made by Arcadis, the new property owner remained unresponsive, and a new access agreement was not secured. In October 2022, Arcadis was successful in obtaining new site access agreements from off-site properties located downgradient from the source area. In May 2023, FDEP secured the source property access agreement from the new owner.
Scope Of Work
This proposal includes Arcadis’ efforts to complete one annual NAM event at the Site and submit one NAM report as summarized below.
Ms. Theresa Pepe Florida Department of Environmental Protection May 26, 2023 www.arcadis.com 20230506.Silver Hanger Cleaners NAM Proposal
2/2
Task 1: Project Management
This task consists of project management activities and health and safety efforts in relation to the completion of Task 2.
Task 2: Annual Natural Attenuation Monitoring and Reporting
Arcadis will conduct one annual NAM event at the Site. The event will consist of the collection of groundwater samples from five monitoring wells (MW001, MW003, MW005, MW007, and MW-009). Samples will be analyzed for volatile organic halocarbons (VOHs) per United States Environmental Protection Agency (USEPA) Method 8260. Groundwater sampling activities will be performed in adherence to the FDEP Standard Operating Procedure (SOP), DEP-SOP-001/01, effective April 16, 2018. Arcadis will prepare a NAM report summarizing the groundwater sampling results. The report will include appropriate tables, figures and recommendations.
Cost Estimate
A CEF and a LOE Form are attached for the above scope of work. The total cost to complete this scope of work is $5,070.34 (Attachment 1). Arcadis proposes the following invoicing schedule:
Invoice Amount Milestone
$5,070.34 Submittal of annual NAM report (includes PM)
Closing Remarks
Arcadis appreciates the opportunity to continue to assist the FDEP on this site. If you have any questions or wish to discuss this proposal further, please do not hesitate to contact us.
Sincerely, Arcadis U.S., Inc.
Gus Suarez, P.E.
Project Manager
Email: Gus.suarez@aracdis.com Direct Line: 813-353-5778 Mobile: 813-205-4703
Enclosures:
Attachment 1: CEF and a LOF Form
09/07/2022 03:24 PM PAGE 1 OF 7
Scope of Work
Blanket Quote based on one drum T&D , for service site specific quote - disposal approval required
TCLP Benzene and 4 Metals with Completed Profile required for each site
Drum Pickup /Transportation/Disposal
Drums south of Miami not included (Keys) additional costs apply
755 PRARIE INDUSTRIAL PKWY,
MULBERRY, FLORIDA, 33860
QUOTE #: 0030388
DATE: 09/07/2022 PROJECT PROPOSAL
CLIENT
DOUGLAS MALONE
ARCADIS
1500 GATEWAY BLVD, SUITE 200, BOYTON BEACH, FLORIDA,
33426
P: (561) 662-7978
PROJECT DESCRIPTION
DRUM PICKUP
VARIOUS SITES SOUTH FLORIDA
THE FOLLOWING DESCRIBES OUR UNDERSTANDING OF THE SCOPE OF SERVICES TO BE PERFORMED BY ENVIROSERVE, FOR THE
CLIENT, AT THE ABOVE REFERENCED LOCATION KNOWN AS THE JOB SITE.
FEE STRUCTURE
TRANSPORTATION
ITEM EST.QTY. UNIT PRICE UNIT TOTAL
TRANSPORTATION 55 GAL DRUMS
NOTES:SUBJECT TO FUEL SURCHARGE,
1.00 $50.00 DRUM $50.00
STOP FEE 6 DRUMS OR LESS PICKUP 1.00 $50.00 EACH $50.00
TRANSPORTATION SUBTOTAL: $100.00
DISPOSAL
ITEM EST.QTY. UNIT PRICE UNIT TOTAL
55 GALLON NON HAZ DRUM
NOTES: Drum DOT Shippable Drum accessible on hard Surface
1.00 $80.00 EACH $80.00
ENERGY SURCHARGE 10% INVOICE TOTAL 1.00 $18.00 EACH $18.00
DISPOSAL SUBTOTAL: $98.00
TOTAL JOB ESTIMATE: $198.00