BPM005628 Revised Price Sheet Southwest Siteworks 12.4.23.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- On-Call Pipelining and Drainage Repair Services
- Solicitation number
- BPM005628
- Issued by
- Arizona
About this file
This is a revised price sheet for On-Call Pipelining and Drainage Repair Services provided by Southwest Siteworks for the State of Arizona Department of Transportation. The document outlines comprehensive statewide pricing for HDPE piping materials in various configurations and drainage work services. HDPE pipe products are listed in circular and oval formats ranging from 12 inches to 78 inches in diameter, with annual estimated quantities varying from 20 to 2,240 linear feet depending on the specific size and configuration. Additional line items include drainage work such as bank protection using dumped rip rap, wire-tied rip rap, and soil-cement; rail bank protection for drainage ways and abutments; jetting and drilling services; drainage excavation; and ditch regrading work with and without surplus material. Specialized services encompassed in the price sheet include hydrovac services, robotic inspection crawler CCTV camera inspection, and emergency call-out labor.
The price sheet includes traffic management and safety equipment rental items such as traffic cones, flashing arrow panels, signs, barricades, warning lights, and certified civilian flaggers, along with provisions for DPS law enforcement officers and off-duty local law enforcement personnel. Mobilization costs are specified by district, with rates ranging from $70 to $300 per mile depending on the geographic district served, including Central, Northcentral, Northeast, Northwest, Southwest, Southcentral, and Southeast districts. The current not-to-exceed unit prices and revised not-to-exceed unit prices are identical across all 71 line items, indicating no price adjustments were made in this revision dated December 4, 2023. All pricing remains fixed at the stated rates, with units of measure specified as linear feet, cubic yards, hours, days, each-day, or miles as applicable to each service category.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statewide
| Line Item | Description | UOM (unit of Measure) | Statewide ANNUAL Estimated Quantities | Current Not-to-Exceed Unit Price | Revised Not-to-Exceed Unit Price |
| 1 | HDPE - Circular, 12" | L. Ft. | 360 | $300.00 | $300.00 |
| 2 | HDPE - Oval, 12" | L. Ft. | 120 | $400.00 | $400.00 |
| 3 | HDPE - Circular, 15" | L. Ft. | 120 | $350.00 | $350.00 |
| 4 | HDPE - Oval, 15" | L. Ft. | 20 | $500.00 | $500.00 |
| 5 | HDPE - Circular, 18" | L. Ft. | 1,450 | $350.00 | $350.00 |
| 6 | HDPE - Oval, 18" | L. Ft. | 220 | $450.00 | $450.00 |
| 7 | HDPE - Circular, 21" | L. Ft. | 360 | $350.00 | $350.00 |
| 8 | HDPE - Oval, 21" | L. Ft. | 200 | $450.00 | $450.00 |
| 9 | HDPE - Circular, 24" | L. Ft. | 2,240 | $350.00 | $350.00 |
| 10 | HDPE – Oval, 24" | L. Ft. | 520 | $450.00 | $450.00 |
| 11 | HDPE - Circular, 27" | L. Ft. | 760 | $400.00 | $400.00 |
| 12 | HDPE - Oval, 27" | L. Ft. | 200 | $500.00 | $500.00 |
| 13 | HDPE - Circular, 30" | L. Ft. | 1,300 | $400.00 | $400.00 |
| 14 | HDPE - Oval, 30" | L. Ft. | 330 | $500.00 | $500.00 |
| 15 | HDPE - Circular, 33" | L. Ft. | 820 | $450.00 | $450.00 |
| 16 | HDPE - Oval, 33" | L. Ft. | 300 | $550.00 | $550.00 |
| 17 | HDPE - Circular, 36" | L. Ft. | 1,110 | $450.00 | $450.00 |
| 18 | HDPE - Oval, 36" | L. Ft. | 490 | $550.00 | $550.00 |
| 19 | HDPE - Circular, 39" | L. Ft. | 820 | $500.00 | $500.00 |
| 20 | HDPE - Oval, 39" | L. Ft. | 200 | $600.00 | $600.00 |
| 21 | HDPE - Circular, 42" | L. Ft. | 960 | $650.00 | $650.00 |
| 22 | HDPE - Oval, 42" | L. Ft. | 120 | $750.00 | $750.00 |
| 23 | HDPE - Circular, 48" | L. Ft. | 1,160 | $700.00 | $700.00 |
| 24 | HDPE - Oval, 48" | L. Ft. | 200 | $800.00 | $800.00 |
| 25 | HDPE - Circular, 54" | L. Ft. | 780 | $750.00 | $750.00 |
| 26 | HDPE - Oval, 54" | L. Ft. | 100 | $850.00 | $850.00 |
| 27 | HDPE - Circular, 60" | L. Ft. | 760 | $800.00 | $800.00 |
| 28 | HDPE - Oval, 60" | L. Ft. | 100 | $900.00 | $900.00 |
| 29 | HDPE - Circular, 66" | L. Ft. | 560 | $1,050.00 | $1,050.00 |
| 30 | HDPE - Oval, 66" | L. Ft. | 100 | $1,200.00 | $1,200.00 |
| 31 | HDPE - Circular, 72" | L. Ft. | 600 | $1,100.00 | $1,100.00 |
| 32 | HDPE - Oval, 72" | L. Ft. | 100 | $1,300.00 | $1,300.00 |
| 33 | HDPE - Circular, 78" | L. Ft. | 560 | $1,200.00 | $1,200.00 |
| 34 | HDPE - Oval, 78" | L. Ft. | 100 | $1,400.00 | $1,400.00 |
| 35 | Drainage Work - Bank Protection, Dumped Rip Rap | CY | 2,125 | $1,000.00 | $1,000.00 |
| 36 | Drainage Work - Bank Protection, Wire Tied Rip Rap | CY | 850 | $1,500.00 | $1,500.00 |
| 37 | Drainage Work - Bank Protection, Soil-Cement | CY | 950 | $2,000.00 | $2,000.00 |
| 38 | Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 | L. Ft. | 1,682 | $1,000.00 | $1,000.00 |
| 39 | Drainage Work - Rail Bank Protection, Rail Bank Protection at Abutments, Type 4, 5, and 6 | L. Ft. | 1,682 | $1,500.00 | $1,500.00 |
| 40 | Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 | L. Ft. | 1,682 | $650.00 | $650.00 |
| 41 | Drainage Work - Jetting | Hr. | 460 | $130.00 | $130.00 |
| 42 | Drainage Work - Drilling | Ft. | 1,850 | $150.00 | $150.00 |
| 43 | Drainage Work - Drainage Excavation | CY | 2,050 | $100.00 | $100.00 |
| 44 | Drainage Work - Regrading cut ditch, resulting with no surplus material | L. Ft. | 17,561 | $10.00 | $10.00 |
| 45 | Drainage Work - Regrading cut ditch, resulting with surplus material to haul | L. Ft. | 12,531 | $26.00 | $26.00 |
| 46 | Hydrovac Services | Hour | 840 | $650.00 | $650.00 |
| 47 | Robotic Inspection Crawler CCTV Camera | Hour | 100 | $150.00 | $150.00 |
| 48 | Emergency Call Out Labor | Hour | 240 | $150.00 | $150.00 |
| 49 | Traffic Cones , 28”(height) Reflectorized | EACH-DAY | 1,062 | $1.00 | $1.00 |
| 50 | Flashing Arrow Panel | EACH DAY | 19 | $50.00 | $50.00 |
| 51 | Signs over 36” (High Intensity Reflective Sheeting) | EACH-DAY | 96 | $6.00 | $6.00 |
| 52 | Sign Stand (Spring Type) | EACH-DAY | 96 | $2.00 | $2.00 |
| 53 | Pilot Vehicle with Driver | HR | 280 | $60.00 | $60.00 |
| 54 | Variable Message Board | EACH DAY | 35 | $50.00 | $50.00 |
| 55 | Type II Barricades | EACH-DAY | 142 | $0.50 | $0.50 |
| 56 | Warning Lights, Type A | EACH-DAY | 160 | $0.50 | $0.50 |
| 57 | Warning Lights, Type B | EACH-DAY | 160 | $2.00 | $2.00 |
| 58 | Warning Lights, Type C | EACH-DAY | 160 | $0.50 | $0.50 |
| 59 | Vertical Panels | EACH-DAY | 320 | $0.50 | $0.50 |
| 60 | Flag Type High Level Warning Device | EACH-DAY | 80 | $9.00 | $9.00 |
| 61 | Certified Civilian Flaggers | HR | 520 | $36.00 | $36.00 |
| 62 | DPS Law Enforcement Officers and Vehicles | HR | 280 | $100.00 | $100.00 |
| 63 | Off-Duty uniformed Local Law Enforcement Officer and vehicle | HR | 280 | $100.00 | $100.00 |
| 64 | Light Plant, day is 8 hours | Day | 22 | $50.00 | $50.00 |
| 65 | Mobilization - Central District | Mile | 150 | $150.00 | $150.00 |
| 66 | Mobilization - Northcentral District | Mile | 1,800 | $70.00 | $70.00 |
| 67 | Mobilization - Northeast District | Mile | 3,000 | $70.00 | $70.00 |
| 68 | Mobilization - Northwest District | Mile | 260 | $70.00 | $70.00 |
| 69 | Mobilization - Southwest District | Mile | 280 | $175.00 | $175.00 |
| 70 | Mobilization - Southcentral District | Mile | 280 | $300.00 | $300.00 |
| 71 | Mobilization - Southeast District | Mile | 250 | $175.00 | $175.00 |
File details come from the government source that posted it. Updated .