BPM005628 Revised Price Sheet Southwest Siteworks 12.12.23.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- On-Call Pipelining and Drainage Repair Services
- Solicitation number
- BPM005628
- Issued by
- Arizona
About this file
This is a revised price sheet for On-Call Pipelining and Drainage Repair Services submitted by Southwest Siteworks for the State of Arizona Department of Transportation (ADOT). The price sheet establishes not-to-exceed unit prices for a comprehensive array of drainage and pipelining materials and services across Arizona's seven transportation districts. Line items encompass HDPE pipe in circular and oval configurations ranging from 12 inches to 78 inches in diameter, with annual estimated quantities varying from 20 to 3,000 linear feet depending on size and type. Additional services include drainage work such as bank protection with dumped rip rap, wire-tied rip rap, and soil-cement applications; rail bank protection at drainage ways and abutments; jetting, drilling, and drainage excavation; hydrovac services; and robotic inspection crawler CCTV camera services. Traffic control and safety items are included, such as traffic cones, flashing arrow panels, signs, barricades, warning lights, and certified civilian flaggers. Mobilization costs are stratified by district, ranging from the Central District at $150 per mile to the Southcentral District at $300 per mile.
All current and revised not-to-exceed unit prices in the price sheet remain unchanged from the original submission, indicating no price adjustments in this revision. HDPE circular pipes range in price from $300 to $1,100 per linear foot, while oval configurations range from $400 to $1,400 per linear foot, with pricing generally increasing with diameter. Drainage work services vary significantly, with dumped rip rap at $1,000 per cubic yard, wire-tied rip rap at $1,500 per cubic yard, and soil-cement at $2,000 per cubic yard. Labor-intensive services such as hydrovac services are priced at $650 per hour, emergency call-out labor at $150 per hour, and certified civilian flaggers at $36 per hour. This on-call contract structure allows ADOT to procure these services as needed across its statewide operations without requiring individual competitive procurements for each project.
View the file
Other files
Show 40 more
Latest 50 of 66 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statewide
| Line Item | Description | UOM (unit of Measure) | Statewide ANNUAL Estimated Quantities | Current Not-to-Exceed Unit Price | Revised Not-to-Exceed Unit Price |
| 1 | HDPE - Circular, 12" | L. Ft. | 360 | $300.00 | $300.00 |
| 2 | HDPE - Oval, 12" | L. Ft. | 120 | $400.00 | $400.00 |
| 3 | HDPE - Circular, 15" | L. Ft. | 120 | $350.00 | $350.00 |
| 4 | HDPE - Oval, 15" | L. Ft. | 20 | $500.00 | $500.00 |
| 5 | HDPE - Circular, 18" | L. Ft. | 1,450 | $350.00 | $350.00 |
| 6 | HDPE - Oval, 18" | L. Ft. | 220 | $450.00 | $450.00 |
| 7 | HDPE - Circular, 21" | L. Ft. | 360 | $350.00 | $350.00 |
| 8 | HDPE - Oval, 21" | L. Ft. | 200 | $450.00 | $450.00 |
| 9 | HDPE - Circular, 24" | L. Ft. | 2,240 | $350.00 | $350.00 |
| 10 | HDPE – Oval, 24" | L. Ft. | 520 | $450.00 | $450.00 |
| 11 | HDPE - Circular, 27" | L. Ft. | 760 | $400.00 | $400.00 |
| 12 | HDPE - Oval, 27" | L. Ft. | 200 | $500.00 | $500.00 |
| 13 | HDPE - Circular, 30" | L. Ft. | 1,300 | $400.00 | $400.00 |
| 14 | HDPE - Oval, 30" | L. Ft. | 330 | $500.00 | $500.00 |
| 15 | HDPE - Circular, 33" | L. Ft. | 820 | $450.00 | $450.00 |
| 16 | HDPE - Oval, 33" | L. Ft. | 300 | $550.00 | $550.00 |
| 17 | HDPE - Circular, 36" | L. Ft. | 1,110 | $450.00 | $450.00 |
| 18 | HDPE - Oval, 36" | L. Ft. | 490 | $550.00 | $550.00 |
| 19 | HDPE - Circular, 39" | L. Ft. | 820 | $500.00 | $500.00 |
| 20 | HDPE - Oval, 39" | L. Ft. | 200 | $600.00 | $600.00 |
| 21 | HDPE - Circular, 42" | L. Ft. | 960 | $650.00 | $650.00 |
| 22 | HDPE - Oval, 42" | L. Ft. | 120 | $750.00 | $750.00 |
| 23 | HDPE - Circular, 48" | L. Ft. | 1,160 | $700.00 | $700.00 |
| 24 | HDPE - Oval, 48" | L. Ft. | 200 | $800.00 | $800.00 |
| 25 | HDPE - Circular, 54" | L. Ft. | 780 | $750.00 | $750.00 |
| 26 | HDPE - Oval, 54" | L. Ft. | 100 | $850.00 | $850.00 |
| 27 | HDPE - Circular, 60" | L. Ft. | 760 | $800.00 | $800.00 |
| 28 | HDPE - Oval, 60" | L. Ft. | 100 | $900.00 | $900.00 |
| 29 | HDPE - Circular, 66" | L. Ft. | 560 | $1,050.00 | $1,050.00 |
| 30 | HDPE - Oval, 66" | L. Ft. | 100 | $1,200.00 | $1,200.00 |
| 31 | HDPE - Circular, 72" | L. Ft. | 600 | $1,100.00 | $1,100.00 |
| 32 | HDPE - Oval, 72" | L. Ft. | 100 | $1,300.00 | $1,300.00 |
| 33 | HDPE - Circular, 78" | L. Ft. | 560 | $1,200.00 | $1,200.00 |
| 34 | HDPE - Oval, 78" | L. Ft. | 100 | $1,400.00 | $1,400.00 |
| 35 | Drainage Work - Bank Protection, Dumped Rip Rap | CY | 2,125 | $1,000.00 | $1,000.00 |
| 36 | Drainage Work - Bank Protection, Wire Tied Rip Rap | CY | 850 | $1,500.00 | $1,500.00 |
| 37 | Drainage Work - Bank Protection, Soil-Cement | CY | 950 | $2,000.00 | $2,000.00 |
| 38 | Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 | L. Ft. | 1,682 | $1,000.00 | $1,000.00 |
| 39 | Drainage Work - Rail Bank Protection, Rail Bank Protection at Abutments, Type 4, 5, and 6 | L. Ft. | 1,682 | $1,500.00 | $1,500.00 |
| 40 | Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 | L. Ft. | 1,682 | $650.00 | $650.00 |
| 41 | Drainage Work - Jetting | Hr. | 460 | $130.00 | $130.00 |
| 42 | Drainage Work - Drilling | Ft. | 1,850 | $150.00 | $150.00 |
| 43 | Drainage Work - Drainage Excavation | CY | 2,050 | $100.00 | $100.00 |
| 44 | Drainage Work - Regrading cut ditch, resulting with no surplus material | L. Ft. | 17,561 | $10.00 | $10.00 |
| 45 | Drainage Work - Regrading cut ditch, resulting with surplus material to haul | L. Ft. | 12,531 | $26.00 | $26.00 |
| 46 | Hydrovac Services | Hour | 840 | $650.00 | $650.00 |
| 47 | Robotic Inspection Crawler CCTV Camera | Hour | 100 | $150.00 | $150.00 |
| 48 | Emergency Call Out Labor | Hour | 240 | $150.00 | $150.00 |
| 49 | Traffic Cones , 28”(height) Reflectorized | EACH-DAY | 1,062 | $1.00 | $1.00 |
| 50 | Flashing Arrow Panel | EACH DAY | 19 | $50.00 | $50.00 |
| 51 | Signs over 36” (High Intensity Reflective Sheeting) | EACH-DAY | 96 | $6.00 | $6.00 |
| 52 | Sign Stand (Spring Type) | EACH-DAY | 96 | $2.00 | $2.00 |
| 53 | Pilot Vehicle with Driver | HR | 280 | $60.00 | $60.00 |
| 54 | Variable Message Board | EACH DAY | 35 | $50.00 | $50.00 |
| 55 | Type II Barricades | EACH-DAY | 142 | $0.50 | $0.50 |
| 56 | Warning Lights, Type A | EACH-DAY | 160 | $0.50 | $0.50 |
| 57 | Warning Lights, Type B | EACH-DAY | 160 | $2.00 | $2.00 |
| 58 | Warning Lights, Type C | EACH-DAY | 160 | $0.50 | $0.50 |
| 59 | Vertical Panels | EACH-DAY | 320 | $0.50 | $0.50 |
| 60 | Flag Type High Level Warning Device | EACH-DAY | 80 | $9.00 | $9.00 |
| 61 | Certified Civilian Flaggers | HR | 520 | $36.00 | $36.00 |
| 62 | DPS Law Enforcement Officers and Vehicles | HR | 280 | $100.00 | $100.00 |
| 63 | Off-Duty uniformed Local Law Enforcement Officer and vehicle | HR | 280 | $100.00 | $100.00 |
| 64 | Light Plant, day is 8 hours | Day | 22 | $50.00 | $50.00 |
| 65 | Mobilization - Central District | Mile | 150 | $150.00 | $150.00 |
| 66 | Mobilization - Northcentral District | Mile | 1,800 | $70.00 | $70.00 |
| 67 | Mobilization - Northeast District | Mile | 3,000 | $70.00 | $70.00 |
| 68 | Mobilization - Northwest District | Mile | 260 | $70.00 | $70.00 |
| 69 | Mobilization - Southwest District | Mile | 280 | $175.00 | $175.00 |
| 70 | Mobilization - Southcentral District | Mile | 280 | $300.00 | $300.00 |
| 71 | Mobilization - Southeast District | Mile | 250 | $175.00 | $175.00 |
File details come from the government source that posted it. Updated .