6-Experience in Remote Areas.pdf

PDF 139 KB Posted

Attached to
On-Call Pipelining and Drainage Repair Services
Solicitation number
BPM005628
Issued by
Arizona

About this file

This is a qualifications document highlighting Southwest Siteworks' (SWSW) experience in remote area construction, relevant to the State of Arizona Department of Transportation's on-call pipelining and drainage repair services contract. The document showcases three completed projects demonstrating SWSW's expertise in isolated locations across Arizona, New Mexico, and West Texas. The FY 23 Statewide Pipeline Project ($1.3 million) involved hydrovac work and pipe installation at ten locations across Arizona with 550 linear feet of railbank installation. The Rodeo Ranch Project ($1.55 million) in Pecos, Texas, comprised civil grading and drainage installation on a 20-acre battery energy storage system, located 45 miles from the nearest town. The SCAT Land Clearing and Grading Project ($2.2 million) in Bylas, Arizona, involved land clearing, grading, and drainage work across 1,200 acres of new farm fields on tribal land.

SWSW demonstrated innovative problem-solving and adaptive management across all projects. On the statewide pipeline project, the firm installed custom-built pipe trailers and CB radio communication systems to overcome cellular service limitations in remote areas. For the Rodeo Ranch Project, SWSW constructed a 4-mile, 24-inch HDPE water line to address water unavailability and coordinated the hauling of over 50,000 tons of base course from 90 miles away. On the tribal land project, SWSW addressed vandalism through 24/7 cellular security cameras and mitigated labor shortages by training local tribal laborers to safely operate heavy equipment. These projects demonstrate the firm's capability to manage material procurement, workforce development, and operational challenges inherent to remote construction environments.

View the file

Other files

File Type Posted
BPM005628_Solicitation_Amendment_Summary_Two__2_.pdf PDF
BPM005628_Solicitation_Requirements_per_Amendment_Two__2_.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Four__4_.pdf PDF
BPM005628_Award_Documents.pdf PDF
BPM005628_Solicitation_Instructions.pdf PDF
Method of Approach - Drainage Excavation 11.20.23.pdf PDF
BPM005628 Revised Price Sheet_GCC 11.20.23.xlsx XLSX spreadsheet
BPM005628 Revised Price Sheet GCC 12.11.23.xlsx XLSX spreadsheet
6-4_BPM005628_Subcontractors_and_Suppliers.pdf PDF
6-Ordering and Maintaining Materials.pdf PDF
6-Method of Approach Pipe.pdf PDF
Method of Approach Drainage Excavation 11.20.23.pdf PDF
Experience in Remote Areas 11.20.23.pdf PDF
6-Method of Approach Remote Areas.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Three__3_.pdf PDF
6-Project Team.pdf PDF
Equipment Write up - Combined 11.20.23.pdf PDF
6-Method of Approach - Remote Areas.pdf PDF
BPM005628 Summary of Negotiations - GCC 12.1.23.pdf PDF
BPM005628 Revised Price Sheet GCC 12.1.23.xlsx XLSX spreadsheet
6-5_BPM005628_References.pdf PDF
BPM005628 Request for BAFO - GCC 12.11.23.pdf PDF
6-3_BPM005628_SPO_Form_205_-_Forced_Labor_of_Ethnic_Uyghurs_Ban.pdf PDF
6-6_BPM005628_Confidentiality_and_Trade_Secrets.pdf PDF
6-8_BPM005628_Price_Increase_Percentages.pdf PDF
BPM005628 Revised Price Sheet Southwest Siteworks 12.12.23.xlsx XLSX spreadsheet
Mobilization Narrative 12.4.23.pdf PDF
BPM005628 Summary of Negotiations - SWSW.pdf PDF
BPM005628 Summary of Negotiations - SWSW 11.20.23.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 2 BPM005628 Boycott of Israel Disclosure.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 4 BPM005628 Subcontractors and Suppliers.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 6 BPM005628 Confidentiality and Trade Secrets.pdf PDF
BPM005628_Pre-Solicitation_Documents.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Five__5_.pdf PDF
BPM005628_Solicitation_Amendment_Summary_One__1_.pdf PDF
6-Operations Capacity.pdf PDF
6-Company History.pdf PDF
6-Method of Approach - Pipe.pdf PDF
6-2_BPM005628_Boycott_of_Israel_Disclosure.pdf PDF
6-9_BPM005628_Price_Sheet_Amendment_Three__3_Granite.xlsx XLSX spreadsheet
6-1_BPM005628_Offer_and_Acceptance.pdf PDF
6-Project Team .pdf PDF
SWSW Mob Cost Breakdown 12.4.23.pdf PDF
BPM005628 Revised Price Sheet Southwest Siteworks 12.4.23.xlsx XLSX spreadsheet
6-[On-Call Pipelining and Drainage Repair Services] 5 BPM005628 References.pdf PDF
Equipment List 11.20.23.pdf PDF
Method of Approach Pipe 11.20.23.pdf PDF
BPM005628 Revised Price Sheet 11.20.23.xlsx XLSX spreadsheet
6-[On-Call Pipelining and Drainage Repair Services] 3 BPM005628 SPO Form 205 - Forced Labor of Ethnic Uyghurs Ban.pdf PDF
6-Method of Approach Pipe_1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Experience in Remote Areas

Southwest Siteworks specializes in civil construction focusing in rural and remote areas across the State of Arizona, New Mexico, and West Texas. SWSW crews are experts in building projects safely and to the highest quality in the most isolated locations. Below is a highlight of recent projects completed in remote areas.

Project Name: FY 23 Statewide Pipeline Project Owner: ADOT Year: 2023 Project Size: $1.3 mil Location: Numerous locations across the state of Arizona

Project Description: Hydrovac and line 10 locations of CMP pipe with HDPW liner and install 550lf of railbank Innovated Approaches: SWSW custom built a pipe trailer that holds all required material install liners as well as build bulkheads.

Lessons Learned: Cellphone service was an issue across all sites. SWSW had issues at first contacting concrete trucks that were on the road. SWSW install a CB radio to allow for communication with trucks and a smoother operation.

Project Challenges: Due to the wet winter, snow and water were an issue while installing pipes in the higher elevation. SWSW adjusted the project schedule to complete all higher elevation pipes in June and utilized trash pumps to dewater work zone.

Project Name: Rodeo Ranch Project Owner: Gridworks Year: 2023 Size: $1.55 mil Location: 45 miles south of the nearest town Pecos, TX

Project Description: SWSW performed the civil grading and drainage installation on a 20 acre BESS Innovated Approaches: SWSW utilized 36” snaptite pipe to reline an existing CMP in lieu of replacing it.

Lessons Learned: Due to the remoteness of the project, water was unavailable for the project. SWSW built a 4 mile 24” hdpe water line to provide water to the site.

Project Challenges: Material procurement was the biggest challenge for this project. Over 50,000 tons of base course had to be hauled in from over 90 miles away. SWSW was proactive with truck scheduling and coordination resulting in a flawless operation.

Project Name: SCAT land Clearing and Grading

Project Owner: San Carlos Apache Farm Year: 2023 Size: $$2.2 Million Location: Bylas, AZ

Project Description: SWSW performed land clearing, grading, and drainage on 1200 acres of new farm fields Innovated Approaches: SWSW custom built attachments to allow for quicker root removal saving two months of schedule.

Lessons Learned: Vandalism was a big issue at the beginning of the project because of the remoteness of the job. SWSW installed cellular security cameras with alarms to constantly monitor the site 24/7.

Project Challenges: Labor was the biggest challenge of the job. Due to being located on tribal land, SWSW was required to hire local labor. There were no available operators so SWSW experienced foreman’s trained local laborers to safely operate heavy equipment.

File details come from the government source that posted it. Updated .