This evaluation document pertains to the Arizona Department of Transportation's (ADOT) solicitation BPM005628 for On-Call Pipelining and Drainage Repair Services. The Department sought services including pipelining installation, drainage excavation, hydrovac services, jetting, drilling, and related repair work to be performed at multiple locations throughout Arizona. Electronic notification of the solicitation was sent to 232 prospective suppliers on September 12, 2023, with a pre-offer conference held on September 20, 2023. Five solicitation amendments were issued between September 14 and October 10, 2023, extending the due date and revising requirements. Two responses were received and opened on October 19, 2023: Granite Construction Company and Southwest Siteworks LLC. The contract is structured as a multi-term on-call agreement with an anticipated five-year term including four one-year renewal periods with maximum price increase allowances of 5%, 10%, 15%, and 20% respectively.
The evaluation committee, comprising Jon Fell, Michael Culp, and Thomas Eckler Jr., scored proposals based on methodology approach (40%), qualifications and experience (30%), capacity (20%), and price (10%). Granite Construction Company received an initial evaluation score of 82.80 and a best and final offer (BAFO) score of 84.80, while Southwest Siteworks LLC scored 65.90 initially and 74.50 on BAFO. Following negotiations conducted in November and December 2023, the evaluation committee recommended a multiple award to both companies to ensure adequate statewide capacity for simultaneous service delivery. The Department anticipated annual costs of approximately $1.2 million based on FY 2023 spending, with pricing structured as not-to-exceed unit rates across seven geographic districts including mobilization charges. Granite Construction Company demonstrated superior scores through extensive remote area experience, larger operational capacity with 360 personnel and 200 pieces of equipment, and established relationships with ADOT dating to 2016, while Southwest Siteworks LLC, though newer with only three years of operations, was deemed capable of supplementing service coverage with five dedicated crews and competitive pricing in select categories.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Executive Summary
ARIZONA DEPARTMENT OF TRANSPORTATION
1655 W. Jackson St. | MD 100P | Phoenix, AZ 85007 | azdot.gov
Rev. 03/2021
Procurement Katie Hobbs, Governor Jennifer Toth, Director
BPM005628
On-Call Pipelining and Drainage Repair Services
Pre-Solicitation Activities
The solicitation package (including: Procurement Request form and Scope of Work) was received from Transportation Systems Management & Operations (Systems Management Contracts Services) on July 27, 2023. In accordance with A.R.S. §41-2546, agency spend and usage reports were analyzed to identify that estimated requirements are reasonable and continuing during the term of the anticipated contract. It is expected that a multi-term contract will serve the best interest of the State by encouraging competition.
Solicitation Process
On September 12, 2023, electronic notification of the solicitation was sent to 232 prospective suppliers who were registered on Arizona Procurement Portal (APP) for Commodity Codes: 70171705 and . The solicitation was formally advertised in the Arizona Republic in accordance with A.R.S. § 41-2534(C) and A.A.C. R2-7- C301(B).
A pre-offer conference was conducted on September 20, 2023 via Google Meets. The conference was attended by 7 people representing the Department and 7 people representing 3 suppliers.
Solicitation Amendment Number One (1) was issued on September 14, 2023 to revise the Procurement Officer’s contact information. Solicitation Amendment Number Two (2) was issued on September 27, 2023 to extend solicitation due date to October 11, 2023, revise the Solicitation Requirements, and revise Attachment 9 Price Sheet. Solicitation Amendment Number Three (3) was issued on October 4, 2023 to revise Attachment 9 Price Sheet. Solicitation Amendment Number Four (4) was issued on October 10, 2023 to extend solicitation due date to October 17, 2023. Solicitation Amendment Number Five (5) was issued on October 13, 2023 to extend solicitation due date to October 19, 2023.
Evaluation Process
Two (2) responses were received, opened and recorded in APP on October 19, 2023 at 3:01 P.M in accordance with A.R.S. § 41-2534(D) and A.A.C. R2-7-C306. Offers were evaluated in accordance with A.R.S. § 41-2534 and A.A.C. R2-7-C316 by the ADOT Evaluation Committee.
Responses were received from:
Granite Construction Company
Southwest Siteworks LLC
DocuSign Envelope ID: 7D36FB17-4456-4A3B-8E9A-DC3D413695BF
An ADOT Evaluation Committee was assembled, comprised of individuals determined to have the qualifications and expertise needed who participated in the evaluation. Committee members were:
Jon Fell from Southwest Infrastructure Delivery & Operations
Michael Culp from Central Infrastructure Delivery & Operations
Thomas Eckler Jr. from Northcentral Infrastructure Delivery & Operations
The following people participated in the evaluation as non-voting technical experts:
Jerry James from ADOT Systems Management
The Procurement Officer facilitated the evaluation process as a non-voting committee member. The committee evaluations were concluded on Dec ember 14, 2023.
Recommendation for Award
In accordance with A.R.S. § 41-2534(G) and A.A.C. R2-7-C317 the solicitation shall be awarded to the responsible offeror whose offer is determined to be most advantageous to the state based on the evaluation factors set forth in the solicitation. The ADOT Procurement Officer recommends the following award:
Granite Construction Company
Southwest Siteworks LLC
Date:
Danyelle Ellington Procurement Officer
DocuSign Envelope ID: 7D36FB17-4456-4A3B-8E9A-DC3D413695BF
12/20/2023
Rating Scale Formula used:
5 = 100 4.5 = 90 Rating x Weight = Weighted Score
4 = 80 3.5 = 70 3 = 60 2.5 = 50 2 = 40 1.5 = 30 1 = 20 0.5 = 10
COMMITTEE EVALUATION SCORES 0 = 0
Firm Name Total Score
Evaluation Criteria Weight Rating Weighted
Score Comment Rating
Weighted Score
Comment
1. Proposal Requirements for Method of Approach 40.00%
Method of Approach - Pipe The Offeror shall provide a brief narrative on the entire process of a pipelining project from start to finish. Response should not exceed one (1) page.
10.00%
4 8.00
The Offeror provided their step by step process of how they install the pipelining. In their offer they detailed how they lay sticks. They also mentioned removal and cleanup. However there was no mention regarding safety, job hazard analysis, or confined space requirements in this process.
4 8.00
The Offeror provided their step by step procedure of a pipelining project from start to finish. In their response they provided an in-depth description of bulkhead construction and grouting. They also mentioned removal and cleanup. However there was no mention regarding safety, job hazard analysis, or confined space requirements in this process.
Method of Approach - Drainage Excavation The Offeror shall provide a brief narrative on the entire process of a drainage excavation project from start to finish. Response should not exceed one (1) page.
10.00%
4 8.00
The Offeror provided their step by step process of a drainage excavation project from start to finish. Their offer detailed how they identify existing utilities and utilize the site walk to identify scope of work locations; access requirements and restrictions; locate water source and dump sites; and discuss traffic control. However there was no mention regarding safety, job hazard analysis, or confined space requirements in this process. 0 0.00
The Offeror did not provide a brief narrative on the entire process of a drainage excavation project from start to finish.
Method of Approach - Remote Areas Provide your company’s method of approach for working in remote areas. At a minimum include the number of hours per day your company would be working and how soon your company would arrive on site before work is to commence.
Response should not exceed one (1) page.
20.00%
4 16.00
The Offeror's approach stated they could increase their work schedules if needed from four days a week to six. They also discussed performing a job hazard analysis and site walks for safety.
4 16.00
The Offeror's approach discussed how they will utilize a site visit to determine how personnel and equipment can be transported to the site. They also plan on identifying the nearest hospitals in case of an emergency, as well as the nearest material/water suppliers. The Offeror also stated they could work Fridays, if needed.
2. Proposal Requirements for Qualifications and Experience 30.00% Experience in Remote Areas Provide a narrative of offeror’s experience providing service to remote areas. Include in the narrative at least three (3) past projects of similar size and scope. In describing each project, include innovative approaches, lessons learned, and how project challenges were addressed within the given project scope and budget. Response should not exceed three
(3) pages.
18.00%
4 14.40
The Offeror provided three past projects of similar size and scope as the solicitation, in remote areas. Their innovative approaches included reducing fleet to keep mobilization costs down and creating a self winching system. Renting a long stick excavator was a lesson learned demonstrated in their offer.
2.5 9.00
The Offeror provide a narrative of their experience providing service to remote areas. However, two of the three projects listed were not of similar size and scope to the solicitation.
Company History Describe your company history, experience and expertise in providing the same or similar services as required in the solicitation, to the same or similar customers as the Arizona Department of Transportation. Response should not exceed one (1) page.
12.00%
4.5 10.80
The Offeror's Arizona Region has been providing construction services to Arizona since 1980. Their response stated that they have experience in remote areas and have worked with the same or similar customers since 2016.
3.5 8.40
The Offeror demonstrated that they have experience working on tribal lands and have worked on multiple sized pipes. Their proposal stated that for the last 24 months they have worked on projects that are the same or similar to the solicitation.
However, the company has only been established for three years.
3. Proposal Requirements for Capacity 20.00% 0 0 Operations Capacity Describe how you would promote the effective and uninterrupted operations of any resulting contract at a minimum for the following areas:
-What do you do when you have sick personnel?
-What do you do when there is not enough labor?
- How are equipment breakdowns handled?
Response should not exceed three (3) pages.
7.00%
4 5.60
The Offeror stated that they can pull resources when they need it, as they have 200 pieces of equipment and 360 personnel. They also mentioned that they have heavy equipment mechanics across the state to handle any breakdowns. To mitigate labor shortages they have a certified in house training apprenticeship program.
3.5 4.90
The Offeror stated they have a certified CAT mechanic to handle equipment breakdowns. They mentioned that if one of their subcontracts is unavailable to complete a project, they have another subcontract that they can utilize. While the subcontractor is performing work the Offeror will have a full-time supervisor present to ensure uninterrupted operations.
However, the Offeror's response doesn't clearly describe how labor will be brought in if shortfalls arrive.
Evaluation Committee -
RFP NO. BPM005628
On-Call Pipelining and Drainage Repair Services
Granite Construction Company
82.80 65.90
Southwest Siteworks LLC
Procurement
DocuSign Envelope ID: B5655C1D-DB1D-4BEF-8A26-61A2AD0F5AF1
Firm Name Total Score
Evaluation Criteria Weight Rating Weighted
Score Comment Rating
Weighted Score
Comment
Granite Construction Company
82.80 65.90
Southwest Siteworks LLC
Project Team In one page or less, Offerors shall list the project team who will be committed to any resulting contract(s), along with their individual responsibilities. Also, how many crews would the offeror have dedicated to any resultant contract.
Demonstrate the experience your On-Site Supervisors have.
No more than one page may be submitted for each on-site supervisor.
6.00%
4 4.80
The proposed Project Team includes three on-site supervisors.
Every member on the Project team has over a decade of experience with several projects that are same or similar to the solicitation. In the response to the Equipment List narrative the Offeror stated that they have over 20 separate crews proficient at performing the work covered by this contract.
4 4.80
The proposed Project Team includes three project staff with over a decade of experience. The Project Team has at least five years of experience with projects that are the same or similar to the solicitation. The Offeror stated they have the capability of running a total of 5 independent crews at any given time.
Equipment List Download the attached document. Complete and upload the completed attachment as part of your response.
Provide a narrative demonstrating the offeror’s approach to assuring their capacity to service multiple jobs in several different areas. How many units of equipment will be dedicated to the contract? Do you have the capabilities to handle multiple site task orders. Response should not exceed one (1) page.
3.00%
4 2.40
The Offeror's equipment list demonstrated that they have a large fleet and the ability to transport pieces of equipment. A majority of the equipment is owned in-house and they also included a remote control skid steer on their equipment list.
The Offeror stated that they would prioritize the use of their equipment for ADOT projects. However, some pieces of equipment are singular in quantity and it is unclear how they would perform work on multiple jobs simultaneously.
3.5 2.10
The Offeror stated that their equipment is held at either our Tucson, AZ yard or our Flagstaff, AZ yard to allow for full coverage of the state. They also indicated that the majority of their equipment is owned in-house, they have rental options, and access to a low profile skid steer. However, some pieces of equipment are singular in quantity and it is unclear how they would perform work on multiple jobs simultaneously.
Ordering and Maintaining Materials Describe your company's approach to ordering and maintaining materials (metal pipes and High density polyethylene). At minimum describe your company's ordering process and describe some products that your company keeps in stock for possible projects. Response should not exceed one (1) page.
4.00%
3.5 2.80
The Offeror's response indicated that they have a process in place for ordering materials, national team that maintains purchasing agreements. They also stated that they will maintain all cut off pieces of pipe over six feet that can be incorporated into future task orders reducing the material needs for subsequent work.
4.5 3.60
The Offeror's response indicated that they keep rip rap and aggregate in stock for small drainage repairs. They also stated that they are willing to expedited all non-stock pipe orders and aggregate as needed.
4. Proposal Requirements for Price 10.00% 100 10.00 91 9.10
COMMITTEE RECOMMENDATION
Granite Construction Company Southwest Siteworks LLC
Jon Fell, Assistant District Engineer/ Southwest District Date
Michael Culp, Operations Supervisor/ Central District Date
Thomas Eckler, Maintenance Superintendent/ Northcentral District Date
The members of the evaluation committee have completed their review of the proposals received in response to the ADOT solicitation referenced above, and have reached consensus. To request Best and Final Offer(s) from the following:
As a participating member of the evaluation committee, I agree with the information provided in this document and concur that the consensus scoring is a complete and accurate reflection of the committee's agreement regarding the evaluation of the proposals received.
DocuSign Envelope ID: B5655C1D-DB1D-4BEF-8A26-61A2AD0F5AF1
11/9/2023
11/9/2023
11/9/2023
Item # Description Quantity UOM Unit Price ($) Extended Price ($) Unit Price ($) Extended Price ($)
1 HDPE ‐ Circular, 12" 40 LF $122.00 4,880.00$ 300.00$ 12,000.00$
2 HDPE ‐ Oval, 12" 0 LF $375.00 $375.00 ‐$ ‐$
3 HDPE ‐ Circular, 15" 40 LF $150.00 6,000.00$ 325.00$ 13,000.00$
4 HDPE ‐ Oval, 15" 20 LF $600.00 12,000.00$ 500.00$ 10,000.00$
5 HDPE ‐ Circular, 18" 150 LF $200.00 30,000.00$ 250.00$ 37,500.00$
6 HDPE ‐ Oval, 18" 20 LF $425.00 8,500.00$ 500.00$ 10,000.00$
7 HDPE ‐ Circular, 21" 100 LF $250.00 25,000.00$ 300.00$ 30,000.00$
8 HDPE ‐ Oval, 21" 20 LF $565.00 11,300.00$ 500.00$ 10,000.00$
9 HDPE ‐ Circular, 24" 240 LF $300.00 72,000.00$ 300.00$ 72,000.00$
10 HDPE – Oval, 24" 20 LF $500.00 10,000.00$ 450.00$ 9,000.00$
11 HDPE ‐ Circular, 27" 240 LF $325.00 78,000.00$ 325.00$ 78,000.00$
12 HDPE ‐ Oval, 27" 20 LF $570.00 11,400.00$ 450.00$ 9,000.00$
13 HDPE ‐ Circular, 30" 300 LF $375.00 112,500.00$ 350.00$ 105,000.00$
14 HDPE ‐ Oval, 30" 20 LF $670.00 13,400.00$ 475.00$ 9,500.00$
15 HDPE ‐ Circular, 33" 240 LF $395.00 94,800.00$ 375.00$ 90,000.00$
16 HDPE ‐ Oval, 33" 20 LF $675.00 13,500.00$ 500.00$ 10,000.00$
17 HDPE ‐ Circular, 36" 240 LF $475.00 114,000.00$ 400.00$ 96,000.00$
18 HDPE ‐ Oval, 36" 20 LF $790.00 15,800.00$ 550.00$ 11,000.00$
19 HDPE ‐ Circular, 39" 240 LF $480.00 115,200.00$ 500.00$ 120,000.00$
20 HDPE ‐ Oval, 39" 20 LF $1,060.00 21,200.00$ 600.00$ 12,000.00$
21 HDPE ‐ Circular, 42" 240 LF $595.00 142,800.00$ 525.00$ 126,000.00$
22 HDPE ‐ Oval, 42" 20 LF $1,250.00 25,000.00$ 800.00$ 16,000.00$
23 HDPE ‐ Circular, 48" 240 LF $755.00 181,200.00$ 550.00$ 132,000.00$
24 HDPE ‐ Oval, 48" 20 LF $1,265.00 25,300.00$ 1,000.00$ 20,000.00$
25 HDPE ‐ Circular, 54" 120 LF $890.00 106,800.00$ 700.00$ 84,000.00$
26 HDPE ‐ Oval, 54" 0 LF $1,800.00 $1,800.00 ‐$ ‐$
27 HDPE ‐ Circular, 60" 0 LF $895.00 $895.00 ‐$ ‐$
28 HDPE ‐ Oval, 60" 0 LF $1,810.00 $1,810.00 ‐$ ‐$
29 HDPE ‐ Circular, 66" 80 LF $1,210.00 96,800.00$ 1,100.00$ 88,000.00$
30 HDPE ‐ Oval, 66" 0 LF $1,780.00 $1,780.00 ‐$ ‐$
31 HDPE ‐ Circular, 72" 80 LF $1,195.00 95,600.00$ 1,150.00$ 92,000.00$
32 HDPE ‐ Oval, 72" 0 LF $1,870.00 $1,870.00 ‐$ ‐$
33 HDPE ‐ Circular, 78" 80 LF $1,280.00 102,400.00$ 1,200.00$ 96,000.00$
34 HDPE ‐ Oval, 78" 0 LF $1,965.00 $1,965.00 ‐$ ‐$
35 Drainage Work ‐ Bank Protection, Dumped Rip Rap 100 CY $380.00 38,000.00$ 1,000.00$ 100,000.00$
36 Drainage Work ‐ Bank Protection, Wire Tied Rip Rap 100 CY $515.00 51,500.00$ 1,500.00$ 150,000.00$
37 Drainage Work ‐ Bank Protection, Soil‐Cement 100 CY $1,330.00 133,000.00$ 2,000.00$ 200,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 20 LF $870.00 17,400.00$ 1,250.00$ 25,000.00$
39 Drainage Work ‐ Rail Bank Protection, Rail Bank Protection at
Abutments, Type 4, 5, and 6 20 LF $690.00 13,800.00$ 1,500.00$ 30,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 20 LF $520.00 10,400.00$ 1,000.00$ 20,000.00$
41 Drainage Work ‐ Jetting 160 HR $400.00 64,000.00$ 130.00$ 20,800.00$
42 Drainage Work ‐ Drilling 0 FT $65.00 $65.00 ‐$ ‐$
43 Drainage Work ‐ Drainage Excavation 250 CY $26.00 6,500.00$ 100.00$ 25,000.00$
44 Drainage Work ‐ Regrading cut ditch, resulting with no surplus material 250 LF $4.00 1,000.00$ 10.00$ 2,500.00$
45 Drainage Work ‐ Regrading cut ditch, resulting with surplus material to haul 250 LF $25.00 6,250.00$ 15.00$ 3,750.00$
46 Hydrovac Services 160 HR $540.00 86,400.00$ 600.00$ 96,000.00$
47 Robotic Inspection Crawler CCTV Camera 40 HR $295.00 11,800.00$ 150.00$ 6,000.00$
48 Emergency Call Out Labor 40 HR $240.00 9,600.00$ 135.00$ 5,400.00$
49 Traffic Cones , 28”(height) Reflectorized 300 ED $9.00 2,700.00$ 1.00$ 300.00$
50 Flashing Arrow Panel 5 ED $48.00 240.00$ 50.00$ 250.00$
51 Signs over 36” (High Intensity Reflective Sheeting) 12 ED $10.00 120.00$ 6.00$ 72.00$
52 Sign Stand (Spring Type) 12 ED $10.00 120.00$ 2.00$ 24.00$
53 Pilot Vehicle with Driver 40 HR $80.00 3,200.00$ 60.00$ 2,400.00$
54 Variable Message Board 5 ED $85.00 425.00$ 50.00$ 250.00$
55 Type II Barricades 40 ED $10.00 400.00$ 0.50$ 20.00$
56 Warning Lights, Type A 40 ED $9.00 360.00$ 0.50$ 20.00$
57 Warning Lights, Type B 40 ED $11.00 440.00$ 2.00$ 80.00$
58 Warning Lights, Type C 40 ED $8.00 320.00$ 0.50$ 20.00$
59 Vertical Panels 80 ED $9.00 720.00$ 0.50$ 40.00$
PRICING EVALUATION
RFP NO. BPM005628
On‐Call Pipelining and Drainage Repair Services
Granite Construction Company Southwest Siteworks LLC
Central District
60 Flag Type High Level Warning Device 12 ED $9.00 108.00$ 8.56$ 102.72$
61 Certified Civilian Flaggers 80 HR $85.00 6,800.00$ 36.00$ 2,880.00$
62 DPS Law Enforcement Officers and Vehicles 40 HR $105.00 4,200.00$ 100.00$ 4,000.00$
63 Off‐Duty uniformed Local Law Enforcement Officer and vehicle 40 HR $125.00 5,000.00$ 100.00$ 4,000.00$
64 Light Plant, day is 8 hours 2 Day $220.00 440.00$ 50.00$ 100.00$
65 Mobilization ‐ Central District 150 Mile $65.00 9,750.00$ 150.00$ 22,500.00$
1 HDPE ‐ Circular, 12" 80 LF $122.00 9,760.00$ 250.00$ 20,000.00$
2 HDPE ‐ Oval, 12" 0 LF $375.00 $375.00 ‐$ ‐$
3 HDPE ‐ Circular, 15" 80 LF $150.00 12,000.00$ 260.00$ 20,800.00$
4 HDPE ‐ Oval, 15" 0 LF $600.00 $600.00 ‐$ ‐$
5 HDPE ‐ Circular, 18" 160 LF $200.00 32,000.00$ 250.00$ 40,000.00$
6 HDPE ‐ Oval, 18" 0 LF $425.00 $425.00 ‐$ ‐$
7 HDPE ‐ Circular, 21" 160 LF $250.00 40,000.00$ 300.00$ 48,000.00$
8 HDPE ‐ Oval, 21" 80 LF $565.00 45,200.00$ 500.00$ 40,000.00$
9 HDPE ‐ Circular, 24" 240 LF $300.00 72,000.00$ 300.00$ 72,000.00$
10 HDPE – Oval, 24" 80 LF $500.00 40,000.00$ 475.00$ 38,000.00$
11 HDPE ‐ Circular, 27" 240 LF $325.00 78,000.00$ 325.00$ 78,000.00$
12 HDPE ‐ Oval, 27" 80 LF $570.00 45,600.00$ 500.00$ 40,000.00$
13 HDPE ‐ Circular, 30" 320 LF $375.00 120,000.00$ 350.00$ 112,000.00$
14 HDPE ‐ Oval, 30" 80 LF $670.00 53,600.00$ 525.00$ 42,000.00$
15 HDPE ‐ Circular, 33" 240 LF $395.00 94,800.00$ 375.00$ 90,000.00$
16 HDPE ‐ Oval, 33" 80 LF $675.00 54,000.00$ 575.00$ 46,000.00$
17 HDPE ‐ Circular, 36" 240 LF $475.00 114,000.00$ 400.00$ 96,000.00$
18 HDPE ‐ Oval, 36" 80 LF $790.00 63,200.00$ 600.00$ 48,000.00$
19 HDPE ‐ Circular, 39" 240 LF $480.00 115,200.00$ 500.00$ 120,000.00$
20 HDPE ‐ Oval, 39" 80 LF $1,060.00 84,800.00$ 775.00$ 62,000.00$
21 HDPE ‐ Circular, 42" 240 LF $595.00 142,800.00$ 525.00$ 126,000.00$
22 HDPE ‐ Oval, 42" 0 LF $1,250.00 $1,250.00 ‐$ ‐$
23 HDPE ‐ Circular, 48" 240 LF $755.00 181,200.00$ 550.00$ 132,000.00$
24 HDPE ‐ Oval, 48" 0 LF $1,265.00 $1,265.00 ‐$ ‐$
25 HDPE ‐ Circular, 54" 160 LF $890.00 142,400.00$ 700.00$ 112,000.00$
26 HDPE ‐ Oval, 54" 0 LF $1,800.00 $1,800.00 ‐$ ‐$
27 HDPE ‐ Circular, 60" 80 LF $895.00 71,600.00$ 850.00$ 68,000.00$
28 HDPE ‐ Oval, 60" 0 LF $1,810.00 $1,810.00 ‐$ ‐$
29 HDPE ‐ Circular, 66" 80 LF $1,210.00 96,800.00$ 950.00$ 76,000.00$
30 HDPE ‐ Oval, 66" 0 LF $1,780.00 $1,780.00 ‐$ ‐$
31 HDPE ‐ Circular, 72" 80 LF $1,195.00 95,600.00$ 1,050.00$ 84,000.00$
32 HDPE ‐ Oval, 72" 0 LF $1,870.00 $1,870.00 ‐$ ‐$
33 HDPE ‐ Circular, 78" 80 LF $1,280.00 102,400.00$ 1,150.00$ 92,000.00$
34 HDPE ‐ Oval, 78" 0 LF $1,965.00 $1,965.00 ‐$ ‐$
35 Drainage Work ‐ Bank Protection, Dumped Rip Rap 500 CY $380.00 190,000.00$ 1,000.00$ 500,000.00$
36 Drainage Work ‐ Bank Protection, Wire Tied Rip Rap 125 CY $515.00 64,375.00$ 1,500.00$ 187,500.00$
37 Drainage Work ‐ Bank Protection, Soil‐Cement 125 CY $1,330.00 166,250.00$ 2,000.00$ 250,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 500 LF $870.00 435,000.00$ 1,000.00$ 500,000.00$
39 Drainage Work ‐ Rail Bank Protection, Rail Bank Protection at
Abutments, Type 4, 5, and 6 500 LF $690.00 345,000.00$ 1,500.00$ 750,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 500 LF $520.00 260,000.00$ 650.00$ 325,000.00$
41 Drainage Work ‐ Jetting 30 HR $400.00 12,000.00$ 130.00$ 3,900.00$
42 Drainage Work ‐ Drilling 300 FT $65.00 19,500.00$ 100.00$ 30,000.00$
43 Drainage Work ‐ Drainage Excavation 300 CY $26.00 7,800.00$ 100.00$ 30,000.00$
44 Drainage Work ‐ Regrading cut ditch, resulting with no surplus material 6,000 LF $4.00 24,000.00$ 10.00$ 60,000.00$
45 Drainage Work ‐ Regrading cut ditch, resulting with surplus material to haul 6,000 LF $25.00 150,000.00$ 15.00$ 90,000.00$
46 Hydrovac Services 120 HR $540.00 64,800.00$ 600.00$ 72,000.00$
47 Robotic Inspection Crawler CCTV Camera 40 HR $295.00 11,800.00$ 150.00$ 6,000.00$
48 Emergency Call Out Labor 40 HR $240.00 9,600.00$ 135.00$ 5,400.00$
49 Traffic Cones , 28”(height) Reflectorized 200 ED $9.00 1,800.00$ 1.00$ 200.00$
50 Flashing Arrow Panel 2 ED $48.00 96.00$ 50.00$ 100.00$
51 Signs over 36” (High Intensity Reflective Sheeting) 12 ED $10.00 120.00$ 6.00$ 72.00$
52 Sign Stand (Spring Type) 12 ED $10.00 120.00$ 2.00$ 24.00$
53 Pilot Vehicle with Driver 40 HR $80.00 3,200.00$ 60.00$ 2,400.00$
54 Variable Message Board 2 ED $85.00 170.00$ 50.00$ 100.00$
55 Type II Barricades 20 ED $10.00 200.00$ 0.50$ 10.00$
56 Warning Lights, Type A 20 ED $9.00 180.00$ 0.50$ 10.00$
57 Warning Lights, Type B 20 ED $11.00 220.00$ 2.00$ 40.00$
58 Warning Lights, Type C 20 ED $8.00 160.00$ 0.50$ 10.00$
59 Vertical Panels 40 ED $9.00 360.00$ 0.50$ 20.00$
60 Flag Type High Level Warning Device 12 ED $9.00 108.00$ 9.00$ 108.00$
61 Certified Civilian Flaggers 80 HR $85.00 6,800.00$ 36.00$ 2,880.00$
62 DPS Law Enforcement Officers and Vehicles 40 HR $105.00 4,200.00$ 100.00$ 4,000.00$
63 Off‐Duty uniformed Local Law Enforcement Officer and vehicle 40 HR $125.00 5,000.00$ 100.00$ 4,000.00$
64 Light Plant, day is 8 hours 2 Day $220.00 440.00$ 50.00$ 100.00$
Northcentral District
65 Mobilization ‐ Northcentral District 1,800 Mile $65.00 117,000.00$ 70.00$ 126,000.00$
1 HDPE ‐ Circular, 12" 120 LF $122.00 14,640.00$ 250.00$ 30,000.00$
2 HDPE ‐ Oval, 12" 0 LF $375.00 $375.00 ‐$ ‐$
3 HDPE ‐ Circular, 15" 0 LF $150.00 $150.00 ‐$ ‐$
4 HDPE ‐ Oval, 15" 0 LF $600.00 $600.00 ‐$ ‐$
5 HDPE ‐ Circular, 18" 160 LF $200.00 32,000.00$ 250.00$ 40,000.00$
6 HDPE ‐ Oval, 18" 0 LF $425.00 $425.00 ‐$ ‐$
7 HDPE ‐ Circular, 21" 0 LF $250.00 $250.00 ‐$ ‐$
8 HDPE ‐ Oval, 21" 0 LF $565.00 $565.00 ‐$ ‐$
9 HDPE ‐ Circular, 24" 800 LF $300.00 240,000.00$ 300.00$ 240,000.00$
10 HDPE – Oval, 24" 120 LF $500.00 60,000.00$ 400.00$ 48,000.00$
11 HDPE ‐ Circular, 27" 40 LF $325.00 13,000.00$ 400.00$ 16,000.00$
12 HDPE ‐ Oval, 27" 0 LF $570.00 $570.00 ‐$ ‐$
13 HDPE ‐ Circular, 30" 120 LF $375.00 45,000.00$ 350.00$ 42,000.00$
14 HDPE ‐ Oval, 30" 40 LF $670.00 26,800.00$ 500.00$ 20,000.00$
15 HDPE ‐ Circular, 33" 0 LF $395.00 $395.00 ‐$ ‐$
16 HDPE ‐ Oval, 33" 0 LF $675.00 $675.00 ‐$ ‐$
17 HDPE ‐ Circular, 36" 40 LF $475.00 19,000.00$ 450.00$ 18,000.00$
18 HDPE ‐ Oval, 36" 40 LF $790.00 31,600.00$ 600.00$ 24,000.00$
19 HDPE ‐ Circular, 39" 0 LF $480.00 $480.00 ‐$ ‐$
20 HDPE ‐ Oval, 39" 0 LF $1,060.00 $1,060.00 ‐$ ‐$
21 HDPE ‐ Circular, 42" 0 LF $595.00 $595.00 ‐$ ‐$
22 HDPE ‐ Oval, 42" 0 LF $1,250.00 $1,250.00 ‐$ ‐$
23 HDPE ‐ Circular, 48" 80 LF $755.00 60,400.00$ 550.00$ 44,000.00$
24 HDPE ‐ Oval, 48" 80 LF $1,265.00 101,200.00$ ‐$ ‐$
25 HDPE ‐ Circular, 54" 0 LF $890.00 $890.00 700.00$ ‐$
26 HDPE ‐ Oval, 54" 0 LF $1,800.00 $1,800.00 ‐$ ‐$
27 HDPE ‐ Circular, 60" 120 LF $895.00 107,400.00$ 800.00$ 96,000.00$
28 HDPE ‐ Oval, 60" 0 LF $1,810.00 $1,810.00 ‐$ ‐$
29 HDPE ‐ Circular, 66" 80 LF $1,210.00 96,800.00$ 825.00$ 66,000.00$
30 HDPE ‐ Oval, 66" 0 LF $1,780.00 $1,780.00 ‐$ ‐$
31 HDPE ‐ Circular, 72" 80 LF $1,195.00 95,600.00$ 900.00$ 72,000.00$
32 HDPE ‐ Oval, 72" 0 LF $1,870.00 $1,870.00 ‐$ ‐$
33 HDPE ‐ Circular, 78" 80 LF $1,280.00 102,400.00$ 1,000.00$ 80,000.00$
34 HDPE ‐ Oval, 78" 0 LF $1,965.00 $1,965.00 ‐$ ‐$
35 Drainage Work ‐ Bank Protection, Dumped Rip Rap 250 CY $380.00 95,000.00$ 1,000.00$ 250,000.00$
36 Drainage Work ‐ Bank Protection, Wire Tied Rip Rap 125 CY $515.00 64,375.00$ 1,500.00$ 187,500.00$
37 Drainage Work ‐ Bank Protection, Soil‐Cement 125 CY $1,330.00 166,250.00$ 2,000.00$ 250,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 1 LF $870.00 870.00$ 1,000.00$ 1,000.00$
39 Drainage Work ‐ Rail Bank Protection, Rail Bank Protection at
Abutments, Type 4, 5, and 6 1 LF $690.00 690.00$ 1,500.00$ 1,500.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 1 LF $520.00 520.00$ 650.00$ 650.00$
41 Drainage Work ‐ Jetting 80 HR $400.00 32,000.00$ 130.00$ 10,400.00$
42 Drainage Work ‐ Drilling 400 FT $65.00 26,000.00$ 100.00$ 40,000.00$
43 Drainage Work ‐ Drainage Excavation 450 CY $26.00 11,700.00$ 100.00$ 45,000.00$
44 Drainage Work ‐ Regrading cut ditch, resulting with no surplus material 1 LF $4.00 4.00$ 10.00$ 10.00$
45 Drainage Work ‐ Regrading cut ditch, resulting with surplus material to haul 1 LF $25.00 25.00$ 15.00$ 15.00$
46 Hydrovac Services 120 HR $540.00 64,800.00$ 600.00$ 72,000.00$
47 Robotic Inspection Crawler CCTV Camera 4 HR $295.00 1,180.00$ 150.00$ 600.00$
48 Emergency Call Out Labor 40 HR $240.00 9,600.00$ 135.00$ 5,400.00$
49 Traffic Cones , 28”(height) Reflectorized 20 ED $9.00 180.00$ 1.00$ 20.00$
50 Flashing Arrow Panel 2 ED $48.00 96.00$ 50.00$ 100.00$
51 Signs over 36” (High Intensity Reflective Sheeting) 12 ED $10.00 120.00$ 6.00$ 72.00$
52 Sign Stand (Spring Type) 12 ED $10.00 120.00$ 2.00$ 24.00$
53 Pilot Vehicle with Driver 40 HR $80.00 3,200.00$ 60.00$ 2,400.00$
54 Variable Message Board 2 ED $85.00 170.00$ 50.00$ 100.00$
55 Type II Barricades 20 ED $10.00 200.00$ 0.50$ 10.00$
56 Warning Lights, Type A 20 ED $9.00 180.00$ 0.50$ 10.00$
57 Warning Lights, Type B 20 ED $11.00 220.00$ 2.00$ 40.00$
58 Warning Lights, Type C 20 ED $8.00 160.00$ 0.50$ 10.00$
59 Vertical Panels 40 ED $9.00 360.00$ 0.50$ 20.00$
60 Flag Type High Level Warning Device 12 ED $9.00 108.00$ 9.00$ 108.00$
61 Certified Civilian Flaggers 80 HR $85.00 6,800.00$ 36.00$ 2,880.00$
62 DPS Law Enforcement Officers and Vehicles 40 HR $105.00 4,200.00$ 100.00$ 4,000.00$
63 Off‐Duty uniformed Local Law Enforcement Officer and vehicle 40 HR $125.00 5,000.00$ 100.00$ 4,000.00$
64 Light Plant, day is 8 hours 2 Day $220.00 440.00$ 50.00$ 100.00$
65 Mobilization ‐ Northeast District 3,000 Mile $65.00 195,000.00$ 70.00$ 210,000.00$
1 HDPE ‐ Circular, 12" 120 LF $122.00 14,640.00$ 200.00$ 24,000.00$
2 HDPE ‐ Oval, 12" 120 LF $375.00 45,000.00$ 250.00$ 30,000.00$
3 HDPE ‐ Circular, 15" 0 LF $150.00 $150.00 ‐$ ‐$
Northeast District
Northwest District
4 HDPE ‐ Oval, 15" 0 LF $600.00 $600.00 ‐$ ‐$
5 HDPE ‐ Circular, 18" 160 LF $200.00 32,000.00$ 250.00$ 40,000.00$
6 HDPE ‐ Oval, 18" 0 LF $425.00 $425.00 ‐$ ‐$
7 HDPE ‐ Circular, 21" 100 LF $250.00 25,000.00$ 300.00$ 30,000.00$
8 HDPE ‐ Oval, 21" 100 LF $565.00 56,500.00$ 400.00$ 40,000.00$
9 HDPE ‐ Circular, 24" 160 LF $300.00 48,000.00$ 300.00$ 48,000.00$
10 HDPE – Oval, 24" 100 LF $500.00 50,000.00$ 450.00$ 45,000.00$
11 HDPE ‐ Circular, 27" 0 LF $325.00 $325.00 ‐$ ‐$
12 HDPE ‐ Oval, 27" 0 LF $570.00 $570.00 ‐$ ‐$
13 HDPE ‐ Circular, 30" 100 LF $375.00 37,500.00$ 325.00$ 32,500.00$
14 HDPE ‐ Oval, 30" 50 LF $670.00 33,500.00$ 500.00$ 25,000.00$
15 HDPE ‐ Circular, 33" 100 LF $395.00 39,500.00$ 350.00$ 35,000.00$
16 HDPE ‐ Oval, 33" 100 LF $675.00 67,500.00$ 525.00$ 52,500.00$
17 HDPE ‐ Circular, 36" 100 LF $475.00 47,500.00$ 375.00$ 37,500.00$
18 HDPE ‐ Oval, 36" 100 LF $790.00 79,000.00$ 600.00$ 60,000.00$
19 HDPE ‐ Circular, 39" 100 LF $480.00 48,000.00$ 400.00$ 40,000.00$
20 HDPE ‐ Oval, 39" 0 LF $1,060.00 $1,060.00 ‐$ ‐$
21 HDPE ‐ Circular, 42" 100 LF $595.00 59,500.00$ 500.00$ 50,000.00$
22 HDPE ‐ Oval, 42" 0 LF $1,250.00 $1,250.00 ‐$ ‐$
23 HDPE ‐ Circular, 48" 100 LF $755.00 75,500.00$ 550.00$ 55,000.00$
24 HDPE ‐ Oval, 48" 0 LF $1,265.00 $1,265.00 ‐$ ‐$
25 HDPE ‐ Circular, 54" 100 LF $890.00 89,000.00$ 700.00$ 70,000.00$
26 HDPE ‐ Oval, 54" 0 LF $1,800.00 $1,800.00 ‐$ ‐$
27 HDPE ‐ Circular, 60" 80 LF $895.00 71,600.00$ 750.00$ 60,000.00$
28 HDPE ‐ Oval, 60" 0 LF $1,810.00 $1,810.00 ‐$ ‐$
29 HDPE ‐ Circular, 66" 80 LF $1,210.00 96,800.00$ 800.00$ 64,000.00$
30 HDPE ‐ Oval, 66" 0 LF $1,780.00 $1,780.00 ‐$ ‐$
31 HDPE ‐ Circular, 72" 80 LF $1,195.00 95,600.00$ 900.00$ 72,000.00$
32 HDPE ‐ Oval, 72" 0 LF $1,870.00 $1,870.00 ‐$ ‐$
33 HDPE ‐ Circular, 78" 80 LF $1,280.00 102,400.00$ 1,000.00$ 80,000.00$
34 HDPE ‐ Oval, 78" 0 LF $1,965.00 $1,965.00 ‐$ ‐$
35 Drainage Work ‐ Bank Protection, Dumped Rip Rap 200 CY $380.00 76,000.00$ 1,000.00$ 200,000.00$
36 Drainage Work ‐ Bank Protection, Wire Tied Rip Rap 100 CY $515.00 51,500.00$ 1,500.00$ 150,000.00$
37 Drainage Work ‐ Bank Protection, Soil‐Cement 100 CY $1,330.00 133,000.00$ 2,000.00$ 200,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 1,000 LF $870.00 870,000.00$ 1,000.00$ 1,000,000.00$
39 Drainage Work ‐ Rail Bank Protection, Rail Bank Protection at
Abutments, Type 4, 5, and 6 1,000 LF $690.00 690,000.00$ 1,500.00$ 1,500,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 1,000 LF $520.00 520,000.00$ 650.00$ 650,000.00$
41 Drainage Work ‐ Jetting 80 HR $400.00 32,000.00$ 130.00$ 10,400.00$
42 Drainage Work ‐ Drilling 250 FT $65.00 16,250.00$ 100.00$ 25,000.00$
43 Drainage Work ‐ Drainage Excavation 200 CY $26.00 5,200.00$ 100.00$ 20,000.00$
44 Drainage Work ‐ Regrading cut ditch, resulting with no surplus material 10,560 LF $4.00 42,240.00$ 10.00$ 105,600.00$
45 Drainage Work ‐ Regrading cut ditch, resulting with surplus material to haul 5,280 LF $25.00 132,000.00$ 15.00$ 79,200.00$
46 Hydrovac Services 80 HR $540.00 43,200.00$ 600.00$ 48,000.00$
47 Robotic Inspection Crawler CCTV Camera 4 HR $295.00 1,180.00$ 150.00$ 600.00$
48 Emergency Call Out Labor 40 HR $240.00 9,600.00$ 135.00$ 5,400.00$
49 Traffic Cones , 28”(height) Reflectorized 52 ED $9.00 468.00$ 1.00$ 52.00$
50 Flashing Arrow Panel 2 ED $48.00 96.00$ 50.00$ 100.00$
51 Signs over 36” (High Intensity Reflective Sheeting) 12 ED $10.00 120.00$ 6.00$ 72.00$
52 Sign Stand (Spring Type) 12 ED $10.00 120.00$ 2.00$ 24.00$
53 Pilot Vehicle with Driver 40 HR $80.00 3,200.00$ 60.00$ 2,400.00$
54 Variable Message Board 2 ED $85.00 170.00$ 50.00$ 100.00$
55 Type II Barricades 20 ED $10.00 200.00$ 0.50$ 10.00$
56 Warning Lights, Type A 20 ED $9.00 180.00$ 0.50$ 10.00$
57 Warning Lights, Type B 20 ED $11.00 220.00$ 2.00$ 40.00$
58 Warning Lights, Type C 20 ED $8.00 160.00$ 0.50$ 10.00$
59 Vertical Panels 40 ED $9.00 360.00$ 0.50$ 20.00$
60 Flag Type High Level Warning Device 12 ED $9.00 108.00$ 9.00$ 108.00$
61 Certified Civilian Flaggers 40 HR $85.00 3,400.00$ 36.00$ 1,440.00$
62 DPS Law Enforcement Officers and Vehicles 40 HR $105.00 4,200.00$ 100.00$ 4,000.00$
63 Off‐Duty uniformed Local Law Enforcement Officer and vehicle 40 HR $125.00 5,000.00$ 100.00$ 4,000.00$
64 Light Plant, day is 8 hours 2 Day $220.00 440.00$ 50.00$ 100.00$
65 Mobilization ‐ Northwest District 260 Mile $65.00 16,900.00$ 70.00$ 18,200.00$
1 HDPE ‐ Circular, 12" 0 LF $122.00 $122.00 ‐$ ‐$
2 HDPE ‐ Oval, 12" 0 LF $375.00 $375.00 ‐$ ‐$
3 HDPE ‐ Circular, 15" 0 LF $150.00 $150.00 ‐$ ‐$
4 HDPE ‐ Oval, 15" 0 LF $600.00 $600.00 ‐$ ‐$
5 HDPE ‐ Circular, 18" 200 LF $200.00 40,000.00$ 250.00$ 50,000.00$
6 HDPE ‐ Oval, 18" 100 LF $425.00 42,500.00$ 500.00$ 50,000.00$
7 HDPE ‐ Circular, 21" 0 LF $250.00 $250.00 ‐$ ‐$
8 HDPE ‐ Oval, 21" 0 LF $565.00 $565.00 ‐$ ‐$
Southwest District
9 HDPE ‐ Circular, 24" 240 LF $300.00 72,000.00$ 300.00$ 72,000.00$
10 HDPE – Oval, 24" 100 LF $500.00 50,000.00$ 450.00$ 45,000.00$
11 HDPE ‐ Circular, 27" 240 LF $325.00 78,000.00$ 325.00$ 78,000.00$
12 HDPE ‐ Oval, 27" 100 LF $570.00 57,000.00$ 450.00$ 45,000.00$
13 HDPE ‐ Circular, 30" 240 LF $375.00 90,000.00$ 350.00$ 84,000.00$
14 HDPE ‐ Oval, 30" 100 LF $670.00 67,000.00$ 475.00$ 47,500.00$
15 HDPE ‐ Circular, 33" 240 LF $395.00 94,800.00$ 375.00$ 90,000.00$
16 HDPE ‐ Oval, 33" 100 LF $675.00 67,500.00$ 500.00$ 50,000.00$
17 HDPE ‐ Circular, 36" 240 LF $475.00 114,000.00$ 400.00$ 96,000.00$
18 HDPE ‐ Oval, 36" 100 LF $790.00 79,000.00$ 550.00$ 55,000.00$
19 HDPE ‐ Circular, 39" 240 LF $480.00 115,200.00$ 410.00$ 98,400.00$
20 HDPE ‐ Oval, 39" 100 LF $1,060.00 106,000.00$ 500.00$ 50,000.00$
21 HDPE ‐ Circular, 42" 240 LF $595.00 142,800.00$ 500.00$ 120,000.00$
22 HDPE ‐ Oval, 42" 100 LF $1,250.00 125,000.00$ 550.00$ 55,000.00$
23 HDPE ‐ Circular, 48" 240 LF $755.00 181,200.00$ 600.00$ 144,000.00$
24 HDPE ‐ Oval, 48" 100 LF $1,265.00 126,500.00$ 650.00$ 65,000.00$
25 HDPE ‐ Circular, 54" 240 LF $890.00 213,600.00$ 700.00$ 168,000.00$
26 HDPE ‐ Oval, 54" 100 LF $1,800.00 180,000.00$ 750.00$ 75,000.00$
27 HDPE ‐ Circular, 60" 240 LF $895.00 214,800.00$ 800.00$ 192,000.00$
28 HDPE ‐ Oval, 60" 100 LF $1,810.00 181,000.00$ 850.00$ 85,000.00$
29 HDPE ‐ Circular, 66" 240 LF $1,210.00 290,400.00$ 1,050.00$ 252,000.00$
30 HDPE ‐ Oval, 66" 100 LF $1,780.00 178,000.00$ 1,100.00$ 110,000.00$
31 HDPE ‐ Circular, 72" 240 LF $1,195.00 286,800.00$ 1,100.00$ 264,000.00$
32 HDPE ‐ Oval, 72" 100 LF $1,870.00 187,000.00$ 1,200.00$ 120,000.00$
33 HDPE ‐ Circular, 78" 240 LF $1,280.00 307,200.00$ 1,200.00$ 288,000.00$
34 HDPE ‐ Oval, 78" 100 LF $1,965.00 196,500.00$ 1,300.00$ 130,000.00$
35 Drainage Work ‐ Bank Protection, Dumped Rip Rap 475 CY $380.00 180,500.00$ 1,000.00$ 475,000.00$
36 Drainage Work ‐ Bank Protection, Wire Tied Rip Rap 100 CY $515.00 51,500.00$ 1,500.00$ 150,000.00$
37 Drainage Work ‐ Bank Protection, Soil‐Cement 100 CY $1,330.00 133,000.00$ 2,000.00$ 200,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 100 LF $870.00 87,000.00$ 1,000.00$ 100,000.00$
39 Drainage Work ‐ Rail Bank Protection, Rail Bank Protection at
Abutments, Type 4, 5, and 6 100 LF $690.00 69,000.00$ 1,500.00$ 150,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 100 LF $520.00 52,000.00$ 750.00$ 75,000.00$
41 Drainage Work ‐ Jetting 40 HR $400.00 16,000.00$ 130.00$ 5,200.00$
42 Drainage Work ‐ Drilling 300 FT $65.00 19,500.00$ 100.00$ 30,000.00$
43 Drainage Work ‐ Drainage Excavation 250 CY $26.00 6,500.00$ 100.00$ 25,000.00$
44 Drainage Work ‐ Regrading cut ditch, resulting with no surplus material 250 LF $4.00 1,000.00$ 30.00$ 7,500.00$
45 Drainage Work ‐ Regrading cut ditch, resulting with surplus material to haul 500 LF $25.00 12,500.00$ 50.00$ 25,000.00$
46 Hydrovac Services 120 HR $540.00 64,800.00$ 600.00$ 72,000.00$
47 Robotic Inspection Crawler CCTV Camera 6 HR $295.00 1,770.00$ 150.00$ 900.00$
48 Emergency Call Out Labor 40 HR $240.00 9,600.00$ 135.00$ 5,400.00$
49 Traffic Cones , 28”(height) Reflectorized 200 ED $9.00 1,800.00$ 1.00$ 200.00$
50 Flashing Arrow Panel 4 ED $48.00 192.00$ 50.00$ 200.00$
51 Signs over 36” (High Intensity Reflective Sheeting) 24 ED $10.00 240.00$ 6.00$ 144.00$
52 Sign Stand (Spring Type) 24 ED $10.00 240.00$ 2.00$ 48.00$
53 Pilot Vehicle with Driver 40 HR $80.00 3,200.00$ 60.00$ 2,400.00$
54 Variable Message Board 20 ED $85.00 1,700.00$ 50.00$ 1,000.00$
55 Type II Barricades 2 ED $10.00 20.00$ 0.50$ 1.00$
56 Warning Lights, Type A 20 ED $9.00 180.00$ 0.50$ 10.00$
57 Warning Lights, Type B 20 ED $11.00 220.00$ 2.00$ 40.00$
58 Warning Lights, Type C 20 ED $8.00 160.00$ 0.50$ 10.00$
59 Vertical Panels 40 ED $9.00 360.00$ 0.50$ 20.00$
60 Flag Type High Level Warning Device 10 ED $9.00 90.00$ 9.00$ 90.00$
61 Certified Civilian Flaggers 80 HR $85.00 6,800.00$ 36.00$ 2,880.00$
62 DPS Law Enforcement Officers and Vehicles 40 HR $105.00 4,200.00$ 100.00$ 4,000.00$
63 Off‐Duty uniformed Local Law Enforcement Officer and vehicle 40 HR $125.00 5,000.00$ 100.00$ 4,000.00$
64 Light Plant, day is 8 hours 4 Day $220.00 880.00$ 50.00$ 200.00$
65 Mobilization ‐ Southwest District 280 Mile $65.00 18,200.00$ 175.00$ 49,000.00$
1 HDPE ‐ Circular, 12" 0 LF $122.00 $122.00 ‐$ ‐$
2 HDPE ‐ Oval, 12" 0 LF $375.00 $375.00 ‐$ ‐$
3 HDPE ‐ Circular, 15" 0 LF $150.00 $150.00 ‐$ ‐$
4 HDPE ‐ Oval, 15" 0 LF $600.00 $600.00 ‐$ ‐$
5 HDPE ‐ Circular, 18" 100 LF $200.00 20,000.00$ 100.00$ 10,000.00$
6 HDPE ‐ Oval, 18" 0 LF $425.00 $425.00 ‐$ ‐$
7 HDPE ‐ Circular, 21" 0 LF $250.00 $250.00 ‐$ ‐$
8 HDPE ‐ Oval, 21" 0 LF $565.00 $565.00 ‐$ ‐$
9 HDPE ‐ Circular, 24" 120 LF $300.00 36,000.00$ 300.00$ 36,000.00$
10 HDPE – Oval, 24" 0 LF $500.00 $500.00 ‐$ ‐$
11 HDPE ‐ Circular, 27" 0 LF $325.00 $325.00 ‐$ ‐$
12 HDPE ‐ Oval, 27" 0 LF $570.00 $570.00 ‐$ ‐$
13 HDPE ‐ Circular, 30" 100 LF $375.00 37,500.00$ 400.00$ 40,000.00$
Southcentral District
14 HDPE ‐ Oval, 30" 0 LF $670.00 $670.00 ‐$ ‐$
15 HDPE ‐ Circular, 33" 0 LF $395.00 $395.00 ‐$ ‐$
16 HDPE ‐ Oval, 33" 0 LF $675.00 $675.00 ‐$ ‐$
17 HDPE ‐ Circular, 36" 100 LF $475.00 47,500.00$ 450.00$ 45,000.00$
18 HDPE ‐ Oval, 36" 0 LF $790.00 $790.00 ‐$ ‐$
19 HDPE ‐ Circular, 39" 0 LF $480.00 $480.00 ‐$ ‐$
20 HDPE ‐ Oval, 39" 0 LF $1,060.00 $1,060.00 ‐$ ‐$
21 HDPE ‐ Circular, 42" 0 LF $595.00 $595.00 ‐$ ‐$
22 HDPE ‐ Oval, 42" 0 LF $1,250.00 $1,250.00 ‐$ ‐$
23 HDPE ‐ Circular, 48" 120 LF $755.00 90,600.00$ 700.00$ 84,000.00$
24 HDPE ‐ Oval, 48" 0 LF $1,265.00 $1,265.00 ‐$ ‐$
25 HDPE ‐ Circular, 54" 0 LF $890.00 $890.00 ‐$ ‐$
26 HDPE ‐ Oval, 54" 0 LF $1,800.00 $1,800.00 ‐$ ‐$
27 HDPE ‐ Circular, 60" 100 LF $895.00 89,500.00$ 800.00$ 80,000.00$
28 HDPE ‐ Oval, 60" 0 LF $1,810.00 $1,810.00 ‐$ ‐$
29 HDPE ‐ Circular, 66" 0 LF $1,210.00 $1,210.00 ‐$ ‐$
30 HDPE ‐ Oval, 66" 0 LF $1,780.00 $1,780.00 ‐$ ‐$
31 HDPE ‐ Circular, 72" 0 LF $1,195.00 $1,195.00 ‐$ ‐$
32 HDPE ‐ Oval, 72" 0 LF $1,870.00 $1,870.00 ‐$ ‐$
33 HDPE ‐ Circular, 78" 0 LF $1,280.00 $1,280.00 ‐$ ‐$
34 HDPE ‐ Oval, 78" 0 LF $1,965.00 $1,965.00 ‐$ ‐$
35 Drainage Work ‐ Bank Protection, Dumped Rip Rap 200 CY $380.00 76,000.00$ 1,000.00$ 200,000.00$
36 Drainage Work ‐ Bank Protection, Wire Tied Rip Rap 100 CY $515.00 51,500.00$ 1,500.00$ 150,000.00$
37 Drainage Work ‐ Bank Protection, Soil‐Cement 100 CY $1,330.00 133,000.00$ 2,000.00$ 200,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 60 LF $870.00 52,200.00$ 1,200.00$ 72,000.00$
39 Drainage Work ‐ Rail Bank Protection, Rail Bank Protection at
Abutments, Type 4, 5, and 6 60 LF $690.00 41,400.00$ 1,600.00$ 96,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 60 LF $520.00 31,200.00$ 800.00$ 48,000.00$
41 Drainage Work ‐ Jetting 40 HR $400.00 16,000.00$ 130.00$ 5,200.00$
42 Drainage Work ‐ Drilling 300 FT $65.00 19,500.00$ 100.00$ 30,000.00$
43 Drainage Work ‐ Drainage Excavation 300 CY $26.00 7,800.00$ 100.00$ 30,000.00$
44 Drainage Work ‐ Regrading cut ditch, resulting with no surplus material 250 LF $4.00 1,000.00$ 30.00$ 7,500.00$
45 Drainage Work ‐ Regrading cut ditch, resulting with surplus material to haul 250 LF $25.00 6,250.00$ 50.00$ 12,500.00$
46 Hydrovac Services 120 HR $540.00 64,800.00$ 600.00$ 72,000.00$
47 Robotic Inspection Crawler CCTV Camera 3 HR $295.00 885.00$ 150.00$ 450.00$
48 Emergency Call Out Labor 40 HR $240.00 9,600.00$ 135.00$ 5,400.00$
49 Traffic Cones , 28”(height) Reflectorized 40 ED $9.00 360.00$ 10.00$ 400.00$
50 Flashing Arrow Panel 2 ED $48.00 96.00$ 50.00$ 100.00$
51 Signs over 36” (High Intensity Reflective Sheeting) 12 ED $10.00 120.00$ 6.00$ 72.00$
52 Sign Stand (Spring Type) 12 ED $10.00 120.00$ 2.00$ 24.00$
53 Pilot Vehicle with Driver 40 HR $80.00 3,200.00$ 60.00$ 2,400.00$
54 Variable Message Board 2 ED $85.00 170.00$ 50.00$ 100.00$
55 Type II Barricades 20 ED $10.00 200.00$ 0.50$ 10.00$
56 Warning Lights, Type A 20 ED $9.00 180.00$ 0.50$ 10.00$
57 Warning Lights, Type B 20 ED $11.00 220.00$ 2.00$ 40.00$
58 Warning Lights, Type C 20 ED $8.00 160.00$ 0.50$ 10.00$
59 Vertical Panels 40 ED $9.00 360.00$ 0.50$ 20.00$
60 Flag Type High Level Warning Device 12 ED $9.00 108.00$ 9.00$ 108.00$
61 Certified Civilian Flaggers 80 HR $85.00 6,800.00$ 36.00$ 2,880.00$
62 DPS Law Enforcement Officers and Vehicles 40 HR $105.00 4,200.00$ 100.00$ 4,000.00$
63 Off‐Duty uniformed Local Law Enforcement Officer and vehicle 40 HR $125.00 5,000.00$ 100.00$ 4,000.00$
64 Light Plant, day is 8 hours 8 Day $220.00 1,760.00$ 50.00$ 400.00$
65 Mobilization ‐ Southcentral District 280 Mile $65.00 18,200.00$ 300.00$ 84,000.00$
1 HDPE ‐ Circular, 12" 0 LF $122.00 $122.00 ‐$ ‐$
2 HDPE ‐ Oval, 12" 0 LF $375.00 $375.00 ‐$ ‐$
3 HDPE ‐ Circular, 15" 0 LF $150.00 $150.00 ‐$ ‐$
4 HDPE ‐ Oval, 15" 0 LF $600.00 $600.00 ‐$ ‐$
5 HDPE ‐ Circular, 18" 520 LF $200.00 104,000.00$ 250.00$ 130,000.00$
6 HDPE ‐ Oval, 18" 100 LF $425.00 42,500.00$ 450.00$ 45,000.00$
7 HDPE ‐ Circular, 21" 0 LF $250.00 $250.00 ‐$ ‐$
8 HDPE ‐ Oval, 21" 0 LF $565.00 $565.00 ‐$ ‐$
9 HDPE ‐ Circular, 24" 440 LF $300.00 132,000.00$ 260.00$ 114,400.00$
10 HDPE – Oval, 24" 100 LF $500.00 50,000.00$ 500.00$ 50,000.00$
11 HDPE ‐ Circular, 27" 0 LF $325.00 $325.00 ‐$ ‐$
12 HDPE ‐ Oval, 27" 0 LF $570.00 $570.00 ‐$ ‐$
13 HDPE ‐ Circular, 30" 120 LF $375.00 45,000.00$ 350.00$ 42,000.00$
14 HDPE ‐ Oval, 30" 40 LF $670.00 26,800.00$ 525.00$ 21,000.00$
15 HDPE ‐ Circular, 33" 0 LF $395.00 $395.00 ‐$ ‐$
16 HDPE ‐ Oval, 33" 0 LF $675.00 $675.00 ‐$ ‐$
17 HDPE ‐ Circular, 36" 150 LF $475.00 71,250.00$ 400.00$ 60,000.00$
18 HDPE ‐ Oval, 36" 150 LF $790.00 118,500.00$ 550.00$ 82,500.00$
Southeast District
19 HDPE ‐ Circular, 39" 0 LF $480.00 $480.00 ‐$ ‐$
20 HDPE ‐ Oval, 39" 0 LF $1,060.00 $1,060.00 ‐$ ‐$
21 HDPE ‐ Circular, 42" 140 LF $595.00 83,300.00$ 525.00$ 73,500.00$
22 HDPE ‐ Oval, 42" 0 LF $1,250.00 $1,250.00 ‐$ ‐$
23 HDPE ‐ Circular, 48" 140 LF $755.00 105,700.00$ 600.00$ 84,000.00$
24 HDPE ‐ Oval, 48" 0 LF $1,265.00 $1,265.00 ‐$ ‐$
25 HDPE ‐ Circular, 54" 160 LF $890.00 142,400.00$ 725.00$ 116,000.00$
26 HDPE ‐ Oval, 54" 0 LF $1,800.00 $1,800.00 ‐$ ‐$
27 HDPE ‐ Circular, 60" 140 LF $895.00 125,300.00$ 800.00$ 112,000.00$
28 HDPE ‐ Oval, 60" 0 LF $1,810.00 $1,810.00 ‐$ ‐$
29 HDPE ‐ Circular, 66" 0 LF $1,210.00 $1,210.00 ‐$ ‐$
30 HDPE ‐ Oval, 66" 0 LF $1,780.00 $1,780.00 ‐$ ‐$
31 HDPE ‐ Circular, 72" 40 LF $1,195.00 47,800.00$ 1,200.00$ 48,000.00$
32 HDPE ‐ Oval, 72" 0 LF $1,870.00 $1,870.00 ‐$ ‐$
33 HDPE ‐ Circular, 78" 0 LF $1,280.00 $1,280.00 ‐$ ‐$
34 HDPE ‐ Oval, 78" 0 LF $1,965.00 $1,965.00 ‐$ ‐$
35 Drainage Work ‐ Bank Protection, Dumped Rip Rap 400 CY $380.00 152,000.00$ 1,000.00$ 400,000.00$
36 Drainage Work ‐ Bank Protection, Wire Tied Rip Rap 200 CY $515.00 103,000.00$ 1,500.00$ 300,000.00$
37 Drainage Work ‐ Bank Protection, Soil‐Cement 300 CY $1,330.00 399,000.00$ 2,000.00$ 600,000.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 1 LF $870.00 870.00$ 1,000.00$ 1,000.00$
39 Drainage Work ‐ Rail Bank Protection, Rail Bank Protection at
Abutments, Type 4, 5, and 6 1 LF $690.00 690.00$ 1,500.00$ 1,500.00$
Drainage Work ‐ Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 1 LF $520.00 520.00$ 750.00$ 750.00$
41 Drainage Work ‐ Jetting 30 HR $400.00 12,000.00$ 130.00$ 3,900.00$
42 Drainage Work ‐ Drilling 300 FT $65.00 19,500.00$ 100.00$ 30,000.00$
43 Drainage Work ‐ Drainage Excavation 300 CY $26.00 7,800.00$ 100.00$ 30,000.00$
44 Drainage Work ‐ Regrading cut ditch, resulting with no surplus material 250 LF $4.00 1,000.00$ 30.00$ 7,500.00$
45 Drainage Work ‐ Regrading cut ditch, resulting with surplus material to haul 250 LF $25.00 6,250.00$ 50.00$ 12,500.00$
46 Hydrovac Services 120 HR $540.00 64,800.00$ 600.00$ 72,000.00$
47 Robotic Inspection Crawler CCTV Camera 3 HR $295.00 885.00$ 150.00$ 450.00$
48 Emergency Call Out Labor 0 HR $240.00 $240.00 135.00$ ‐$
49 Traffic Cones , 28”(height) Reflectorized 250 ED $9.00 2,250.00$ 1.00$ 250.00$
50 Flashing Arrow Panel 2 ED $48.00 96.00$ 50.00$ 100.00$
51 Signs over 36” (High Intensity Reflective Sheeting) 12 ED $10.00 120.00$ 6.00$ 72.00$
52 Sign Stand (Spring Type) 12 ED $10.00 120.00$ 2.00$ 24.00$
53 Pilot Vehicle with Driver 40 HR $80.00 3,200.00$ 60.00$ 2,400.00$
54 Variable Message Board 2 ED $85.00 170.00$ 50.00$ 100.00$
55 Type II Barricades 20 ED $10.00 200.00$ 0.50$ 10.00$
56 Warning Lights, Type A 20 ED $9.00 180.00$ 0.50$ 10.00$
57 Warning Lights, Type B 20 ED $11.00 220.00$ 2.00$ 40.00$
58 Warning Lights, Type C 20 ED $8.00 160.00$ 0.50$ 10.00$
59 Vertical Panels 40 ED $9.00 360.00$ 0.50$ 20.00$
60 Flag Type High Level Warning Device 10 ED $9.00 90.00$ 9.00$ 90.00$
61 Certified Civilian Flaggers 80 HR $85.00 6,800.00$ 36.00$ 2,880.00$
62 DPS Law Enforcement Officers and Vehicles 40 HR $105.00 4,200.00$ 100.00$ 4,000.00$
63 Off‐Duty uniformed Local Law Enforcement Officer and vehicle 40 HR $125.00 5,000.00$ 100.00$ 4,000.00$
64 Light Plant, day is 8 hours 2 Day $220.00 440.00$ 50.00$ 100.00$
65 Mobilization ‐ Southeast District 250 Mile $65.00 16,250.00$ 175.00$ 43,750.00$
Total 242,620.00$ 18,955,790.00$ 142,619.56$ 21,894,160.72$
Maximum Percentage Increase Evaluation Max %
Renewal Ext. Price
($) Max %
Renewal Ext. Price
Renewal Period 1 5.00% 19,903,579.50$ 3.00% 22,550,985.54$
Renewal Period 2 10.00% 20,851,369.00$ 4.00% 22,769,927.15$
Renewal Period 3 15.00% 21,799,158.50$ 6.00% 23,207,810.36$
Renewal Period 4 20.00% 22,746,948.00$ 8.00% 23,645,693.58$
Grand Total 104,256,845.00$ 114,068,577.35$
Max Pts 100 100 91
Formula used:
Points Awarded
Rating Scale Formula used:
5 = 100 4.5 = 90 Rating x Weight = Weighted Score
4 = 80 3.5 = 70
3 = 60 2.5 = 50
2 = 40 1.5 = 30
1 = 20 0.5 = 10
COMMITTEE EVALUATION SCORES 0 = 0
Firm Name
Total Score
Evaluation Criteria Weight Rating Weighted
Score Comment Rating
Weighted
Score Comment
1. Proposal Requirements for Method of Approach 40.00%
Method of Approach ‐ Pipe
The Offeror shall provide a brief narrative on the entire process of a pipelining project from start to finish. Response should not exceed two (2) pages.
10.00%
4.5 9.00
Offeror's revised response included how they would provide a job hazard analysis and conduct safety meetings daily, as well as when activities change. They also outline the STCKY items they focus on, which includes the eight primary safety categories for their industry. 4 8.00
The Offeror provided a revised response, there were no changes in strengths or weaknesses in their BAFO.
Method of Approach ‐ Drainage Excavation
The Offeror shall provide a brief narrative on the entire process of a drainage excavation project from start to finish. Response should not exceed two (2) pages.
10.00%
4.5 9.00
Offeror's revised response included how they would provide a job hazard analysis and conduct safety meetings daily, as well as when activities change. They also outline the STCKY items they focus on, which includes the eight primary safety categories for their industry.
3.5 7.00
The Offeror provided their step by step process of a drainage excavation project from start to finish. Their offer detailed how they identify existing utilities prior to excavation;
removal and cleanup; and demobilizing.
Method of Approach ‐ Remote Areas
Provide your company’s method of approach for working in remote areas. At a minimum include the number of hours per day your company would be working and how soon your company would arrive on site before work is to commence. Response should not exceed one (1) page.
20.00%
4 16.00
No changes in strengths or weaknesses in BAFO response.
4 16.00
No changes in strengths or weaknesses in BAFO response.
2. Proposal Requirements for Qualifications and Experience 30.00%
Experience in Remote Areas
Provide a narrative of offeror’s experience providing service to remote areas. Include in the narrative at least three (3) past projects of similar size and scope. In describing each project, include innovative approaches, lessons learned, and how project challenges were addressed within the given project scope and budget. Response should not exceed three (3) pages.
18.00%
4 14.40
No changes in strengths or weaknesses in BAFO response.
3 10.80
Offeror's revised response included additional past projects of similar size and scope as the solicitation in remote areas for pipelining.
Company History
Describe your company history, experience and expertise in providing the same or similar services as required in the solicitation, to the same or similar customers as the Arizona Department of Transportation. Response should not exceed one (1) page.
12.00%
4.5 10.80
No changes in strengths or weaknesses in BAFO response.
3.5 8.40
No changes in strengths or weaknesses in BAFO response.
3. Proposal Requirements for Capacity 20.00% 0 0
Operations Capacity
Describe how you would promote the effective and uninterrupted operations of any resulting contract at a minimum for the following areas:
‐What do you do when you have sick personnel?
‐What do you do when there is not enough labor?
‐ How are equipment breakdowns handled?
Response should not exceed three (3) pages.
7.00%
4 5.60
No changes in strengths or weaknesses in BAFO response.
3.5 4.90
No changes in strengths or weaknesses in BAFO response.
Project Team
In one page or less, Offerors shall list the project…