6-8_BPM005628_Price_Increase_Percentages.pdf

PDF 136 KB Posted

Attached to
On-Call Pipelining and Drainage Repair Services
Solicitation number
BPM005628
Issued by
Arizona

About this file

This attachment outlines price increase percentages for a solicitation issued by the State of Arizona Department of Transportation (ADOT) for On-Call Pipelining and Drainage Repair Services under Solicitation No. BPM005553. The document serves as a bidding form where offerors identify the maximum price increase percentages they may request during renewal periods if ADOT exercises its contractual renewal options. The contract structure includes four potential renewal periods, with offerors able to propose maximum increase percentages for each period: 5% for the first renewal, 10% for the second renewal, 15% for the third renewal, and 20% for the fourth renewal.

The pricing methodology requires that each renewal period's increase percentage be calculated against the original contract price rather than compounded against previous renewal prices. Offerors are cautioned that failure to provide information in the designated spaces will result in prices remaining unchanged from the original contract term. The State of Arizona emphasizes that price increases are not automatically granted upon contract renewal; any requested increase must be supported by documented justification provided at the time of renewal. This attachment ensures transparency in pricing structure and allows both the state and bidders to understand potential cost escalations throughout the contract term.

View the file

Other files

File Type Posted
BPM005628_Solicitation_Amendment_Summary_Two__2_.pdf PDF
BPM005628_Solicitation_Requirements_per_Amendment_Two__2_.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Four__4_.pdf PDF
BPM005628_Award_Documents.pdf PDF
BPM005628_Solicitation_Instructions.pdf PDF
Method of Approach - Drainage Excavation 11.20.23.pdf PDF
BPM005628 Revised Price Sheet_GCC 11.20.23.xlsx XLSX spreadsheet
BPM005628 Revised Price Sheet GCC 12.11.23.xlsx XLSX spreadsheet
6-Experience in Remote Areas.pdf PDF
6-4_BPM005628_Subcontractors_and_Suppliers.pdf PDF
6-Ordering and Maintaining Materials.pdf PDF
6-Method of Approach Pipe.pdf PDF
Method of Approach Drainage Excavation 11.20.23.pdf PDF
Experience in Remote Areas 11.20.23.pdf PDF
6-Method of Approach Remote Areas.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Three__3_.pdf PDF
6-Project Team.pdf PDF
Equipment Write up - Combined 11.20.23.pdf PDF
6-Method of Approach - Remote Areas.pdf PDF
BPM005628 Summary of Negotiations - GCC 12.1.23.pdf PDF
BPM005628 Revised Price Sheet GCC 12.1.23.xlsx XLSX spreadsheet
6-5_BPM005628_References.pdf PDF
BPM005628 Request for BAFO - GCC 12.11.23.pdf PDF
6-3_BPM005628_SPO_Form_205_-_Forced_Labor_of_Ethnic_Uyghurs_Ban.pdf PDF
6-6_BPM005628_Confidentiality_and_Trade_Secrets.pdf PDF
BPM005628 Revised Price Sheet Southwest Siteworks 12.12.23.xlsx XLSX spreadsheet
Mobilization Narrative 12.4.23.pdf PDF
BPM005628 Summary of Negotiations - SWSW.pdf PDF
BPM005628 Summary of Negotiations - SWSW 11.20.23.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 2 BPM005628 Boycott of Israel Disclosure.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 4 BPM005628 Subcontractors and Suppliers.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 6 BPM005628 Confidentiality and Trade Secrets.pdf PDF
BPM005628_Pre-Solicitation_Documents.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Five__5_.pdf PDF
BPM005628_Solicitation_Amendment_Summary_One__1_.pdf PDF
6-Operations Capacity.pdf PDF
6-Company History.pdf PDF
6-Method of Approach - Pipe.pdf PDF
6-2_BPM005628_Boycott_of_Israel_Disclosure.pdf PDF
6-9_BPM005628_Price_Sheet_Amendment_Three__3_Granite.xlsx XLSX spreadsheet
6-1_BPM005628_Offer_and_Acceptance.pdf PDF
6-Project Team .pdf PDF
SWSW Mob Cost Breakdown 12.4.23.pdf PDF
BPM005628 Revised Price Sheet Southwest Siteworks 12.4.23.xlsx XLSX spreadsheet
6-[On-Call Pipelining and Drainage Repair Services] 5 BPM005628 References.pdf PDF
Equipment List 11.20.23.pdf PDF
Method of Approach Pipe 11.20.23.pdf PDF
BPM005628 Revised Price Sheet 11.20.23.xlsx XLSX spreadsheet
6-[On-Call Pipelining and Drainage Repair Services] 3 BPM005628 SPO Form 205 - Forced Labor of Ethnic Uyghurs Ban.pdf PDF
6-Method of Approach Pipe_1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Procurement

ATTACHMENT 8

PRICE INCREASE PERCENTAGES

Solicitation No: BPM005553 Available online at https://appstate.az.gov/

Rev. 09/2022

The offeror should use the space below to identify the maximum price increase percentage that they may want to request at the time of renewal if ADOT exercises its option per the applicable provisions under any resultant contract(s).

1st Renewal Period ______5_____________% Maximum Increase

2nd Renewal Period ______10_____________% Maximum Increase

3rd Renewal Period _______15___________% Maximum Increase

4th Renewal Period _______20___________% Maximum Increase

The offeror is cautioned that each renewal period’s increase percentage shall be computed against the ORIGINAL contract price. If information is not provided in the space above, prices shall remain the same as the original contract term. Please see the following example for further clarification.

Example: If the offeror anticipates requesting a 2% increase at each renewal period per Special Terms and Conditions, they should enter 2%, 4%, 6%, and 8% in the attachment.

Each percentage increase is calculated using the original contract price. See example in table below.

Renewal Period

% Maximum Increase from Attachment

Original Contract

Price

Maximum Increase Allowed

Maximum Contract

Price 1 2% $100.00 $2.00 $102.00 2 4% $100.00 $4.00 $104.00 3 6% $100.00 $6.00 $106.00 4 8% $100.00 $8.00 $108.00

Furthermore, the offeror is advised that the State of Arizona does not automatically grant any increase when renewing the contract. If an increase is requested, documentation of need must be provided at the time of renewal.

https://appstate.az.gov/