6-On-Call Pipelining and Drainage Repair Services 9 BPM005628 Price Sheet.pdf

PDF 85 KB Posted

Attached to
On-Call Pipelining and Drainage Repair Services
Solicitation number
BPM005628
Issued by
Arizona

About this file

This is a price sheet for on-call pipelining and drainage repair services issued by the Arizona Department of Transportation (ADOT). The document establishes unit pricing for materials, labor, equipment, and services across six geographic districts: Central, Northcentral, Northeast, Northwest, Southwest, Southcentral, and Southeast. Services include HDPE pipe installation in various diameters (12" to 78" circular and oval configurations), drainage work such as bank protection using rip rap or soil-cement, rail bank protection, jetting, drilling, drainage excavation, and ditch regrading. The price sheet also covers ancillary services including hydrovac services, robotic inspection crawler CCTV camera work, emergency call-out labor, and traffic control items such as cones, barricades, warning lights, and flagging services. Estimated annual quantities are specified for each line item by district, with mobilization costs calculated on a per-mile basis for each region.

Pricing is structured as not-to-exceed unit rates, with costs varying significantly by district and service type. HDPE pipe pricing ranges from $200 to $1,300 per linear foot depending on diameter, material type (circular or oval), and district, while larger diameter pipes command premium pricing. Drainage work rates vary from $10 to $2,000 per unit, with bank protection services at the higher end of the pricing structure. Traffic control and labor services are priced at modest daily or hourly rates, ranging from $0.50 for barricades to $600 per hour for hydrovac services. Mobilization costs range from $70 to $300 per mile across districts. Offerors are not required to bid on every district, allowing contractors to submit proposals for specific geographic areas where they can provide services. This on-call contract structure enables ADOT to access pipelining and drainage repair services across the state on an as-needed basis without committing to a specific volume of work in advance.

View the file

Other files

File Type Posted
6-Method of Approach - Remote Areas.pdf PDF
BPM005628 Revised Price Sheet GCC 12.1.23.xlsx XLSX spreadsheet
6-9_BPM005628_Price_Sheet_Amendment_Three__3_Granite.xlsx XLSX spreadsheet
6-Method of Approach Pipe_1.pdf PDF
SWSW Mob Cost Breakdown 12.4.23.pdf PDF
6-Ordering and Maintaining Materials.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 6 BPM005628 Confidentiality and Trade Secrets.pdf PDF
BPM005628 Summary of Negotiations - SWSW.pdf PDF
6-8_BPM005628_Price_Increase_Percentages.pdf PDF
6-Method of Approach Remote Areas.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Two__2_.pdf PDF
BPM005628 Revised Price Sheet GCC 12.11.23.xlsx XLSX spreadsheet
6-SWSW History.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 8 BPM005628 Price Increase Percentages.pdf PDF
6-Proposal # 1-prop_items.xls XLS spreadsheet
6-3_BPM005628_SPO_Form_205_-_Forced_Labor_of_Ethnic_Uyghurs_Ban.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 1 BPM005628 Offer and Acceptance.pdf PDF
Response BPM005628 Request for BAFO - GCC 12.11.23.pdf PDF
BPM005628_Solicitation_Instructions.pdf PDF
6-Method of Approach Pipe.pdf PDF
BPM005628 Request for BAFO - SWSW.pdf PDF
6-Odering and Maintaing Materials.pdf PDF
Response to Invitation to Negotiation - BPM005628 On-Call Pipelining 11.20.23.pdf PDF
Method of Approach - Pipe 11.20.23.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 7 BPM005628 Equipment List.pdf PDF
Mobilization Narrative 12.4.23.pdf PDF
6-5_BPM005628_References.pdf PDF
Equipment Write up - Combined 11.20.23.pdf PDF
6-Project Team.pdf PDF
6-Method of Approach - Drainage Excavation.pdf PDF
BPM005628 Summary of Negotiations - Southwest Siteworks.pdf PDF
6-Financial Envelope-Proposal # 1-prop_answer.xls XLS spreadsheet
6-4_BPM005628_Subcontractors_and_Suppliers.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Four__4_.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 2 BPM005628 Boycott of Israel Disclosure.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Three__3_.pdf PDF
6-6_BPM005628_Confidentiality_and_Trade_Secrets.pdf PDF
BPM005628 Summary of Negotiations - SWSW 11.20.23.pdf PDF
BPM005628 Revised Price Sheet Southwest Siteworks 12.12.23.xlsx XLSX spreadsheet
6-[On-Call Pipelining and Drainage Repair Services] 4 BPM005628 Subcontractors and Suppliers.pdf PDF
BPM005628_Solicitation_Requirements_per_Amendment_Two__2_.pdf PDF
6-Experience in Remote Areas.pdf PDF
BPM005628 Revised Price Sheet_GCC 11.20.23.xlsx XLSX spreadsheet
Experience in Remote Areas 11.20.23.pdf PDF
BPM005628 Summary of Negotiations - GCC 12.1.23.pdf PDF
BPM005628 Request for BAFO - GCC 12.11.23.pdf PDF
6-Equipment - Combined.pdf PDF
BPM005628_Award_Documents.pdf PDF
BPM005628_Evaluation_Documents.pdf PDF
Method of Approach - Drainage Excavation 11.20.23.pdf PDF
Show 40 more

Latest 50 of 66 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ITEM NO. DESCRIPTION

Unit of

Measure

Estimated

Annual

Quantities

Not to Exceed Unit

Price

1 HDPE - Circular, 12" L. Ft. 40 $ 300.00

2 HDPE - Oval, 12" L. Ft. 0

3 HDPE - Circular, 15" L. Ft. 40 $ 325.00

4 HDPE - Oval, 15" L. Ft. 20 500.00$

5 HDPE - Circular, 18" L. Ft. 150 $ 250.00

6 HDPE - Oval, 18" L. Ft. 20 $ 500.00

7 HDPE - Circular, 21" L. Ft. 100 $ 300.00

8 HDPE - Oval, 21" L. Ft. 20 $ 500.00

9 HDPE - Circular, 24" L. Ft. 240 $ 300.00

10 HDPE – Oval, 24" L. Ft. 20 $ 450.00

11 HDPE - Circular, 27" L. Ft. 240 $ 325.00

12 HDPE - Oval, 27" L. Ft. 20 $ 450.00

13 HDPE - Circular, 30" L. Ft. 300 $ 350.00

14 HDPE - Oval, 30" L. Ft. 20 $ 475.00

15 HDPE - Circular, 33" L. Ft. 240 $ 375.00

16 HDPE - Oval, 33" L. Ft. 20 $ 500.00

17 HDPE - Circular, 36" L. Ft. 240 $ 400.00

18 HDPE - Oval, 36" L. Ft. 20 $ 550.00

19 HDPE - Circular, 39" L. Ft. 240 $ 500.00

20 HDPE - Oval, 39" L. Ft. 20 $ 600.00

21 HDPE - Circular, 42" L. Ft. 240 $ 525.00

22 HDPE - Oval, 42" L. Ft. 20 $ 800.00

23 HDPE - Circular, 48" L. Ft. 240 $ 550.00

24 HDPE - Oval, 48" L. Ft. 20 $ 1,000.00

25 HDPE - Circular, 54" L. Ft. 120 $ 700.00

26 HDPE - Oval, 54" L. Ft. 0

27 HDPE - Circular, 60" L. Ft. 0

28 HDPE - Oval, 60" L. Ft. 0

29 HDPE - Circular, 66" L. Ft. 80 $ 1,100.00

30 HDPE - Oval, 66" L. Ft. 0

31 HDPE - Circular, 72" L. Ft. 80 $ 1,150.00

32 HDPE - Oval, 72" L. Ft. 0

33 HDPE - Circular, 78" L. Ft. 80 $ 1,200.00

34 HDPE - Oval, 78" L. Ft. 0

35 Drainage Work - Bank Protection, Dumped

Rip Rap CY 100 $ 1,000.00

36 Drainage Work - Bank Protection, Wire Tied

Rip Rap CY 100 $ 1,500.00

37 Drainage Work - Bank Protection, Soil-

Cement CY 100 $ 2,000.00

38 Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 L. Ft. 20 $ 1,250.00

39 Drainage Work - Rail Bank Protection, Rail

Bank Protection at Abutments, Type 4, 5, and 6 L. Ft. 20 $ 1,500.00

40 Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 L. Ft. 20 $ 1,000.00

41 Drainage Work - Jetting Hr. 160 $ 130.00

42 Drainage Work - Drilling Ft. 0

43 Drainage Work - Drainage Excavation CY 250 $ 100.00

44 Drainage Work - Regrading cut ditch, resulting with no surplus material L. Ft. 250 $ 10.00

45 Drainage Work - Regrading cut ditch, resulting with surplus material to haul L. Ft. 250 $ 15.00

46 Hydrovac Services Hour 160 $ 600.00

47 Robotic Inspection Crawler CCTV Camera Hour 40 $ 150.00

48 Emergency Call Out Labor Hour 40 $ 135.00

49 Traffic Cones , 28”(height) Reflectorized EACH-DAY 300 $ 1.00

50 Flashing Arrow Panel EACH DAY 5 $ 50.00

51 Signs over 36” (High Intensity Reflective

Sheeting) EACH-DAY 12 $ 6.00

52 Sign Stand (Spring Type) EACH-DAY 12 $ 2.00

53 Pilot Vehicle with Driver HR 40 $ 60.00

54 Variable Message Board EACH DAY 5 $ 50.00

55 Type II Barricades EACH-DAY 40 $ 0.50

56 Warning Lights, Type A EACH-DAY 40 $ 0.50

57 Warning Lights, Type B EACH-DAY 40 $ 2.00

58 Warning Lights, Type C EACH-DAY 40 $ 0.50

59 Vertical Panels EACH-DAY 80 $ 0.50

60 Flag Type High Level Warning Device EACH-DAY 12 $ 8.56

61 Certified Civilian Flaggers HR 80 $ 36.00

62 DPS Law Enforcement Officers and Vehicles

HR 40 $ 100.00

63 Off-Duty uniformed Local Law Enforcement

Officer and vehicle HR 40 $ 100.00

64 Light Plant, day is 8 hours Day 2 $ 50.00

65 Mobilization - Central District Mile 150 $ 150.00

Attachment 9

Price Sheet

Offerors are not required to bid on every District. Enter the Not to Exceed Unit Price in column F for all line items in that District.

Measure

Estimated

Annual

Quantities

Not to Exceed for

Unit Price

1 HDPE - Circular, 12" L. Ft. 80 $ 250.00

2 HDPE - Oval, 12" L. Ft. 0

3 HDPE - Circular, 15" L. Ft. 80 $ 260.00

4 HDPE - Oval, 15" L. Ft. 0

5 HDPE - Circular, 18" L. Ft. 160 $ 250.00

6 HDPE - Oval, 18" L. Ft. 0

7 HDPE - Circular, 21" L. Ft. 160 $ 300.00

8 HDPE - Oval, 21" L. Ft. 80 $ 500.00

9 HDPE - Circular, 24" L. Ft. 240 $ 300.00

10 HDPE – Oval, 24" L. Ft. 80 $ 475.00

11 HDPE - Circular, 27" L. Ft. 240 $ 325.00

12 HDPE - Oval, 27" L. Ft. 80 $ 500.00

13 HDPE - Circular, 30" L. Ft. 320 $ 350.00

14 HDPE - Oval, 30" L. Ft. 80 $ 525.00

15 HDPE - Circular, 33" L. Ft. 240 $ 375.00

16 HDPE - Oval, 33" L. Ft. 80 $ 575.00

17 HDPE - Circular, 36" L. Ft. 240 $ 400.00

18 HDPE - Oval, 36" L. Ft. 80 $ 600.00

19 HDPE - Circular, 39" L. Ft. 240 $ 500.00

20 HDPE - Oval, 39" L. Ft. 80 $ 775.00

21 HDPE - Circular, 42" L. Ft. 240 $ 525.00

22 HDPE - Oval, 42" L. Ft. 0

23 HDPE - Circular, 48" L. Ft. 240 $ 550.00

24 HDPE - Oval, 48" L. Ft. 0

25 HDPE - Circular, 54" L. Ft. 160 $ 700.00

26 HDPE - Oval, 54" L. Ft. 0

27 HDPE - Circular, 60" L. Ft. 80 $ 850.00

28 HDPE - Oval, 60" L. Ft. 0

29 HDPE - Circular, 66" L. Ft. 80 $ 950.00

30 HDPE - Oval, 66" L. Ft. 0

31 HDPE - Circular, 72" L. Ft. 80 $ 1,050.00

32 HDPE - Oval, 72" L. Ft. 0

33 HDPE - Circular, 78" L. Ft. 80 $ 1,150.00

34 HDPE - Oval, 78" L. Ft. 0

35 Drainage Work - Bank Protection, Dumped

Rip Rap CY 500 $ 1,000.00

36 Drainage Work - Bank Protection, Wire

Tied Rip Rap CY 125 $ 1,500.00

37 Drainage Work - Bank Protection, Soil-

Cement CY 125 $ 2,000.00

38 Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 L. Ft. 500 $ 1,000.00

39 Drainage Work - Rail Bank Protection, Rail

Bank Protection at Abutments, Type 4, 5, and 6 L. Ft. 500 $ 1,500.00

40 Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 L. Ft. 500 $ 650.00

41 Drainage Work - Jetting Hr. 30 $ 130.00

42 Drainage Work - Drilling Ft. 300 $ 100.00

43 Drainage Work - Drainage Excavation CY 300 $ 100.00

Drainage Work - Regrading cut ditch, resulting with no surplus material L. Ft. 6,000 $ 10.00

Drainage Work - Regrading cut ditch, resulting with surplus material to haul L. Ft. 6,000 $ 15.00

46 Hydrovac Services Hour 120 $ 600.00

47 Robotic Inspection Crawler CCTV Camera Hour 40 $ 150.00

48 Emergency Call Out Labor Hour 40 $ 135.00

49 Traffic Cones , 28”(height) Reflectorized EACH-DAY 200 $ 1.00

50 Flashing Arrow Panel EACH DAY 2 $ 50.00

51 Signs over 36” (High Intensity Reflective

Sheeting) EACH-DAY 12 $ 6.00

52 Sign Stand (Spring Type) EACH-DAY 12 $ 2.00

53 Pilot Vehicle with Driver HR 40 $ 60.00

54 Variable Message Board EACH DAY 2 $ 50.00

55 Type II Barricades EACH-DAY 20 $ 0.50

56 Warning Lights, Type A EACH-DAY 20 $ 0.50

57 Warning Lights, Type B EACH-DAY 20 $ 2.00

58 Warning Lights, Type C EACH-DAY 20 $ 0.50

59 Vertical Panels EACH-DAY 40 $ 0.50

60 Flag Type High Level Warning Device EACH-DAY 12 $ 9.00

61 Certified Civilian Flaggers HR 80 $ 36.00

62 DPS Law Enforcement Officers and Vehicles

HR 40 $ 100.00

63 Off-Duty uniformed Local Law Enforcement

Officer and vehicle HR 40 $ 100.00

64 Light Plant, day is 8 hours Day 2 $ 50.00

65 Mobilization - Northcentral District Mile 1,800 $ 70.00

Attachment 9

Price Sheet

Offerors are not required to bid on every District. Enter the Not to Exceed Unit Price in column F for all line items in that District.

Measure

Northeast

District

Not to Exceed for

Unit Price

1 HDPE - Circular, 12" L. Ft. 120 $ 250.00

2 HDPE - Oval, 12" L. Ft. 0

3 HDPE - Circular, 15" L. Ft. 0

4 HDPE - Oval, 15" L. Ft. 0

5 HDPE - Circular, 18" L. Ft. 160 $ 250.00

6 HDPE - Oval, 18" L. Ft. 0

7 HDPE - Circular, 21" L. Ft. 0

8 HDPE - Oval, 21" L. Ft. 0

9 HDPE - Circular, 24" L. Ft. 800 $ 300.00

10 HDPE – Oval, 24" L. Ft. 120 $ 400.00

11 HDPE - Circular, 27" L. Ft. 40 $ 400.00

12 HDPE - Oval, 27" L. Ft. 0

13 HDPE - Circular, 30" L. Ft. 120 $ 350.00

14 HDPE - Oval, 30" L. Ft. 40 $ 500.00

15 HDPE - Circular, 33" L. Ft. 0

16 HDPE - Oval, 33" L. Ft. 0

17 HDPE - Circular, 36" L. Ft. 40 $ 450.00

18 HDPE - Oval, 36" L. Ft. 40 $ 600.00

19 HDPE - Circular, 39" L. Ft. 0

20 HDPE - Oval, 39" L. Ft. 0

21 HDPE - Circular, 42" L. Ft. 0

22 HDPE - Oval, 42" L. Ft. 0

23 HDPE - Circular, 48" L. Ft. 80 $ 550.00

24 HDPE - Oval, 48" L. Ft. 80

25 HDPE - Circular, 54" L. Ft. 0 $ 700.00

26 HDPE - Oval, 54" L. Ft. 0

27 HDPE - Circular, 60" L. Ft. 120 $ 800.00

28 HDPE - Oval, 60" L. Ft. 0

29 HDPE - Circular, 66" L. Ft. 80 $ 825.00

30 HDPE - Oval, 66" L. Ft. 0

31 HDPE - Circular, 72" L. Ft. 80 $ 900.00

32 HDPE - Oval, 72" L. Ft. 0

33 HDPE - Circular, 78" L. Ft. 80 $ 1,000.00

34 HDPE - Oval, 78" L. Ft. 0

35 Drainage Work - Bank Protection, Dumped

Rip Rap CY 250 $ 1,000.00

36 Drainage Work - Bank Protection, Wire

Tied Rip Rap CY 125 $ 1,500.00

37 Drainage Work - Bank Protection, Soil-

Cement CY 125 $ 2,000.00

38 Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 L. Ft. 1 $ 1,000.00

39 Drainage Work - Rail Bank Protection, Rail

Bank Protection at Abutments, Type 4, 5, and 6 L. Ft. 1 $ 1,500.00

40 Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 L. Ft. 1 $ 650.00

41 Drainage Work - Jetting Hr. 80 $ 130.00

42 Drainage Work - Drilling Ft. 400 $ 100.00

43 Drainage Work - Drainage Excavation CY 450 $ 100.00

Drainage Work - Regrading cut ditch, resulting with no surplus material L. Ft. 1 $ 10.00

Drainage Work - Regrading cut ditch, resulting with surplus material to haul L. Ft. 1 $ 15.00

46 Hydrovac Services Hour 120 $ 600.00

47 Robotic Inspection Crawler CCTV Camera Hour 4 $ 150.00

48 Emergency Call Out Labor Hour 40 $ 135.00

49 Traffic Cones , 28”(height) Reflectorized EACH-DAY 20 $ 1.00

50 Flashing Arrow Panel EACH DAY 2 $ 50.00

51 Signs over 36” (High Intensity Reflective

Sheeting) EACH-DAY 12 $ 6.00

52 Sign Stand (Spring Type) EACH-DAY 12 $ 2.00

53 Pilot Vehicle with Driver HR 40 $ 60.00

54 Variable Message Board EACH DAY 2 $ 50.00

55 Type II Barricades EACH-DAY 20 $ 0.50

56 Warning Lights, Type A EACH-DAY 20 $ 0.50

57 Warning Lights, Type B EACH-DAY 20 $ 2.00

58 Warning Lights, Type C EACH-DAY 20 $ 0.50

59 Vertical Panels EACH-DAY 40 $ 0.50

60 Flag Type High Level Warning Device EACH-DAY 12 $ 9.00

61 Certified Civilian Flaggers HR 80 $ 36.00

62 DPS Law Enforcement Officers and

Vehicles HR 40 $ 100.00

63 Off-Duty uniformed Local Law

Enforcement Officer and vehicle HR 40 $ 100.00

64 Light Plant, day is 8 hours Day 2 $ 50.00

65 Mobilization - Northeast District Mile 3,000 70

Attachment 9

Price Sheet

Offerors are not required to bid on every District. Enter the Not to Exceed Unit Price in column F for all line items in that District.

Measure

Northwest

District

Not to Exceed for

Unit Price

1 HDPE - Circular, 12" L. Ft. 120 $ 200.00

2 HDPE - Oval, 12" L. Ft. 120 $ 250.00

3 HDPE - Circular, 15" L. Ft. 0

4 HDPE - Oval, 15" L. Ft. 0

5 HDPE - Circular, 18" L. Ft. 160 $ 250.00

6 HDPE - Oval, 18" L. Ft. 0

7 HDPE - Circular, 21" L. Ft. 100 $ 300.00

8 HDPE - Oval, 21" L. Ft. 100 $ 400.00

9 HDPE - Circular, 24" L. Ft. 160 $ 300.00

10 HDPE – Oval, 24" L. Ft. 100 $ 450.00

11 HDPE - Circular, 27" L. Ft. 0

12 HDPE - Oval, 27" L. Ft. 0

13 HDPE - Circular, 30" L. Ft. 100 $ 325.00

14 HDPE - Oval, 30" L. Ft. 50 $ 500.00

15 HDPE - Circular, 33" L. Ft. 100 $ 350.00

16 HDPE - Oval, 33" L. Ft. 100 $ 525.00

17 HDPE - Circular, 36" L. Ft. 100 $ 375.00

18 HDPE - Oval, 36" L. Ft. 100 $ 600.00

19 HDPE - Circular, 39" L. Ft. 100 $ 400.00

20 HDPE - Oval, 39" L. Ft. 0

21 HDPE - Circular, 42" L. Ft. 100 $ 500.00

22 HDPE - Oval, 42" L. Ft. 0

23 HDPE - Circular, 48" L. Ft. 100 $ 550.00

24 HDPE - Oval, 48" L. Ft. 0

25 HDPE - Circular, 54" L. Ft. 100 $ 700.00

26 HDPE - Oval, 54" L. Ft. 0

27 HDPE - Circular, 60" L. Ft. 80 $ 750.00

28 HDPE - Oval, 60" L. Ft. 0

29 HDPE - Circular, 66" L. Ft. 80 $ 800.00

30 HDPE - Oval, 66" L. Ft. 0

31 HDPE - Circular, 72" L. Ft. 80 $ 900.00

32 HDPE - Oval, 72" L. Ft. 0

33 HDPE - Circular, 78" L. Ft. 80 $ 1,000.00

34 HDPE - Oval, 78" L. Ft. 0

35 Drainage Work - Bank Protection, Dumped

Rip Rap CY 200 $ 1,000.00

36 Drainage Work - Bank Protection, Wire

Tied Rip Rap CY 100 $ 1,500.00

37 Drainage Work - Bank Protection, Soil-

Cement CY 100 $ 2,000.00

38 Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 L. Ft. 1,000 $ 1,000.00

39 Drainage Work - Rail Bank Protection, Rail

Bank Protection at Abutments, Type 4, 5, and 6 L. Ft. 1,000 $ 1,500.00

40 Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 L. Ft. 1,000 $ 650.00

41 Drainage Work - Jetting Hr. 80 $ 130.00

42 Drainage Work - Drilling Ft. 250 $ 100.00

43 Drainage Work - Drainage Excavation CY 200 $ 100.00

Drainage Work - Regrading cut ditch, resulting with no surplus material L. Ft. 10,560 $ 10.00

Drainage Work - Regrading cut ditch, resulting with surplus material to haul L. Ft. 5,280 $ 15.00

46 Hydrovac Services Hour 80 $ 600.00

47 Robotic Inspection Crawler CCTV Camera Hour 4 $ 150.00

48 Emergency Call Out Labor Hour 40 $ 135.00

49 Traffic Cones , 28”(height) Reflectorized EACH-DAY 52 $ 1.00

50 Flashing Arrow Panel EACH DAY 2 $ 50.00

51 Signs over 36” (High Intensity Reflective

Sheeting) EACH-DAY 12 $ 6.00

52 Sign Stand (Spring Type) EACH-DAY 12 $ 2.00

53 Pilot Vehicle with Driver HR 40 $ 60.00

54 Variable Message Board EACH DAY 2 $ 50.00

55 Type II Barricades EACH-DAY 20 $ 0.50

56 Warning Lights, Type A EACH-DAY 20 $ 0.50

57 Warning Lights, Type B EACH-DAY 20 $ 2.00

58 Warning Lights, Type C EACH-DAY 20 $ 0.50

59 Vertical Panels EACH-DAY 40 $ 0.50

60 Flag Type High Level Warning Device EACH-DAY 12 $ 9.00

61 Certified Civilian Flaggers HR 40 $ 36.00

62 DPS Law Enforcement Officers and

Vehicles HR 40 $ 100.00

63 Off-Duty uniformed Local Law

Enforcement Officer and vehicle HR 40 $ 100.00

64 Light Plant, day is 8 hours Day 2 $ 50.00

65 Mobilization - Northwest District Mile 260 70

Attachment 9

Price Sheet

Offerors are not required to bid on every District. Enter the Not to Exceed Unit Price in column F for

Measure

Southwest

District

Not to Exceed for

Unit Price

1 HDPE - Circular, 12" L. Ft. 0

2 HDPE - Oval, 12" L. Ft. 0

3 HDPE - Circular, 15" L. Ft. 0

4 HDPE - Oval, 15" L. Ft. 0

5 HDPE - Circular, 18" L. Ft. 200 $ 250.00

6 HDPE - Oval, 18" L. Ft. 100 $ 500.00

7 HDPE - Circular, 21" L. Ft. 0

8 HDPE - Oval, 21" L. Ft. 0

9 HDPE - Circular, 24" L. Ft. 240 $ 300.00

10 HDPE – Oval, 24" L. Ft. 100 $ 450.00

11 HDPE - Circular, 27" L. Ft. 240 $ 325.00

12 HDPE - Oval, 27" L. Ft. 100 $ 450.00

13 HDPE - Circular, 30" L. Ft. 240 $ 350.00

14 HDPE - Oval, 30" L. Ft. 100 $ 475.00

15 HDPE - Circular, 33" L. Ft. 240 $ 375.00

16 HDPE - Oval, 33" L. Ft. 100 $ 500.00

17 HDPE - Circular, 36" L. Ft. 240 $ 400.00

18 HDPE - Oval, 36" L. Ft. 100 $ 550.00

19 HDPE - Circular, 39" L. Ft. 240 $ 410.00

20 HDPE - Oval, 39" L. Ft. 100 $ 500.00

21 HDPE - Circular, 42" L. Ft. 240 $ 500.00

22 HDPE - Oval, 42" L. Ft. 100 $ 550.00

23 HDPE - Circular, 48" L. Ft. 240 $ 600.00

24 HDPE - Oval, 48" L. Ft. 100 $ 650.00

25 HDPE - Circular, 54" L. Ft. 240 $ 700.00

26 HDPE - Oval, 54" L. Ft. 100 $ 750.00

27 HDPE - Circular, 60" L. Ft. 240 $ 800.00

28 HDPE - Oval, 60" L. Ft. 100 $ 850.00

29 HDPE - Circular, 66" L. Ft. 240 $ 1,050.00

30 HDPE - Oval, 66" L. Ft. 100 $ 1,100.00

31 HDPE - Circular, 72" L. Ft. 240 $ 1,100.00

32 HDPE - Oval, 72" L. Ft. 100 $ 1,200.00

33 HDPE - Circular, 78" L. Ft. 240 $ 1,200.00

34 HDPE - Oval, 78" L. Ft. 100 $ 1,300.00

35 Drainage Work - Bank Protection, Dumped

Rip Rap CY 475 $ 1,000.00

36 Drainage Work - Bank Protection, Wire

Tied Rip Rap CY 100 $ 1,500.00

37 Drainage Work - Bank Protection, Soil-

Cement CY 100 $ 2,000.00

38 Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 L. Ft. 100 $ 1,000.00

39 Drainage Work - Rail Bank Protection, Rail

Bank Protection at Abutments, Type 4, 5, and 6 L. Ft. 100 $ 1,500.00

40 Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 L. Ft. 100 $ 750.00

41 Drainage Work - Jetting Hr. 40 $ 130.00

42 Drainage Work - Drilling Ft. 300 $ 100.00

43 Drainage Work - Drainage Excavation CY 250 $ 100.00

Drainage Work - Regrading cut ditch, resulting with no surplus material L. Ft. 250 $ 30.00

Drainage Work - Regrading cut ditch, resulting with surplus material to haul L. Ft. 500 $ 50.00

46 Hydrovac Services Hour 120 $ 600.00

47 Robotic Inspection Crawler CCTV Camera Hour 6 $ 150.00

48 Emergency Call Out Labor Hour 40 $ 135.00

49 Traffic Cones , 28”(height) Reflectorized EACH-DAY 200 $ 1.00

50 Flashing Arrow Panel EACH DAY 4 $ 50.00

51 Signs over 36” (High Intensity Reflective

Sheeting) EACH-DAY 24 $ 6.00

52 Sign Stand (Spring Type) EACH-DAY 24 $ 2.00

53 Pilot Vehicle with Driver HR 40 $ 60.00

54 Variable Message Board EACH DAY 20 $ 50.00

55 Type II Barricades EACH-DAY 2 $ 0.50

56 Warning Lights, Type A EACH-DAY 20 $ 0.50

57 Warning Lights, Type B EACH-DAY 20 $ 2.00

58 Warning Lights, Type C EACH-DAY 20 $ 0.50

59 Vertical Panels EACH-DAY 40 $ 0.50

60 Flag Type High Level Warning Device EACH-DAY 10 $ 9.00

61 Certified Civilian Flaggers HR 80 $ 36.00

62 DPS Law Enforcement Officers and

Vehicles HR 40 $ 100.00

63 Off-Duty uniformed Local Law

Enforcement Officer and vehicle HR 40 $ 100.00

64 Light Plant, day is 8 hours Day 4 $ 50.00

65 Mobilization - Southwest District Mile 280 175

Attachment 9

Price Sheet

Offerors are not required to bid on every District. Enter the Not to Exceed Unit Price in column F for all line items in that District.

Measure

Southcentral

District

Not to Exceed for Unit Price

1 HDPE - Circular, 12" L. Ft. 0

2 HDPE - Oval, 12" L. Ft. 0

3 HDPE - Circular, 15" L. Ft. 0

4 HDPE - Oval, 15" L. Ft. 0

5 HDPE - Circular, 18" L. Ft. 100 $ 250.00

6 HDPE - Oval, 18" L. Ft. 0

7 HDPE - Circular, 21" L. Ft. 0

8 HDPE - Oval, 21" L. Ft. 0

9 HDPE - Circular, 24" L. Ft. 120 $ 300.00

10 HDPE – Oval, 24" L. Ft. 0

11 HDPE - Circular, 27" L. Ft. 0

12 HDPE - Oval, 27" L. Ft. 0

13 HDPE - Circular, 30" L. Ft. 100 $ 400.00

14 HDPE - Oval, 30" L. Ft. 0

15 HDPE - Circular, 33" L. Ft. 0

16 HDPE - Oval, 33" L. Ft. 0

17 HDPE - Circular, 36" L. Ft. 100 $ 450.00

18 HDPE - Oval, 36" L. Ft. 0

19 HDPE - Circular, 39" L. Ft. 0

20 HDPE - Oval, 39" L. Ft. 0

21 HDPE - Circular, 42" L. Ft. 0

22 HDPE - Oval, 42" L. Ft. 0

23 HDPE - Circular, 48" L. Ft. 120 $ 700.00

24 HDPE - Oval, 48" L. Ft. 0

25 HDPE - Circular, 54" L. Ft. 0

26 HDPE - Oval, 54" L. Ft. 0

27 HDPE - Circular, 60" L. Ft. 100 $ 800.00

28 HDPE - Oval, 60" L. Ft. 0

29 HDPE - Circular, 66" L. Ft. 0

30 HDPE - Oval, 66" L. Ft. 0

31 HDPE - Circular, 72" L. Ft. 0

32 HDPE - Oval, 72" L. Ft. 0

33 HDPE - Circular, 78" L. Ft. 0

34 HDPE - Oval, 78" L. Ft. 0

35 Drainage Work - Bank Protection, Dumped

Rip Rap CY 200 $ 1,000.00

36 Drainage Work - Bank Protection, Wire

Tied Rip Rap CY 100 $ 1,500.00

37 Drainage Work - Bank Protection, Soil-

Cement CY 100 $ 2,000.00

38 Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 L. Ft. 60 $ 1,200.00

39 Drainage Work - Rail Bank Protection, Rail

Bank Protection at Abutments, Type 4, 5, and 6 L. Ft. 60 $ 1,600.00

40 Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 L. Ft. 60 $ 800.00

41 Drainage Work - Jetting Hr. 40 $ 130.00

42 Drainage Work - Drilling Ft. 300 $ 100.00

43 Drainage Work - Drainage Excavation CY 300 $ 100.00

Drainage Work - Regrading cut ditch, resulting with no surplus material L. Ft. 250 $ 30.00

Drainage Work - Regrading cut ditch, resulting with surplus material to haul L. Ft. 250 $ 50.00

46 Hydrovac Services Hour 120 $ 600.00

47 Robotic Inspection Crawler CCTV Camera Hour 3 $ 150.00

48 Emergency Call Out Labor Hour 40 $ 135.00

49 Traffic Cones , 28”(height) Reflectorized EACH-DAY 40 $ 1.00

50 Flashing Arrow Panel EACH DAY 2 $ 50.00

51 Signs over 36” (High Intensity Reflective

Sheeting) EACH-DAY 12 $ 6.00

52 Sign Stand (Spring Type) EACH-DAY 12 $ 2.00

53 Pilot Vehicle with Driver HR 40 $ 60.00

54 Variable Message Board EACH DAY 2 $ 50.00

55 Type II Barricades EACH-DAY 20 $ 0.50

56 Warning Lights, Type A EACH-DAY 20 $ 0.50

57 Warning Lights, Type B EACH-DAY 20 $ 2.00

58 Warning Lights, Type C EACH-DAY 20 $ 0.50

59 Vertical Panels EACH-DAY 40 $ 0.50

60 Flag Type High Level Warning Device EACH-DAY 12 $ 9.00

61 Certified Civilian Flaggers HR 80 $ 36.00

62 DPS Law Enforcement Officers and

Vehicles HR 40 $ 100.00

63 Off-Duty uniformed Local Law

Enforcement Officer and vehicle HR 40 $ 100.00

64 Light Plant, day is 8 hours Day 8 $ 50.00

65 Mobilization - Southcentral District Mile 280 300

Attachment 9

Price Sheet

Offerors are not required to bid on every District. Enter the Not to Exceed Unit Price in column F for

ITEM NO. DESCRIPTION Measure District Unit Price

1 HDPE - Circular, 12" L. Ft. 0

2 HDPE - Oval, 12" L. Ft. 0

3 HDPE - Circular, 15" L. Ft. 0

4 HDPE - Oval, 15" L. Ft. 0

5 HDPE - Circular, 18" L. Ft. 520 $ 250.00

6 HDPE - Oval, 18" L. Ft. 100 $ 450.00

7 HDPE - Circular, 21" L. Ft. 0

8 HDPE - Oval, 21" L. Ft. 0

9 HDPE - Circular, 24" L. Ft. 440 $ 260.00

10 HDPE – Oval, 24" L. Ft. 100 $ 500.00

11 HDPE - Circular, 27" L. Ft. 0

12 HDPE - Oval, 27" L. Ft. 0

13 HDPE - Circular, 30" L. Ft. 120 $ 350.00

14 HDPE - Oval, 30" L. Ft. 40 $ 525.00

15 HDPE - Circular, 33" L. Ft. 0

16 HDPE - Oval, 33" L. Ft. 0

17 HDPE - Circular, 36" L. Ft. 150 $ 400.00

18 HDPE - Oval, 36" L. Ft. 150 $ 550.00

19 HDPE - Circular, 39" L. Ft. 0

20 HDPE - Oval, 39" L. Ft. 0

21 HDPE - Circular, 42" L. Ft. 140 $ 525.00

22 HDPE - Oval, 42" L. Ft. 0

23 HDPE - Circular, 48" L. Ft. 140 $ 600.00

24 HDPE - Oval, 48" L. Ft. 0

25 HDPE - Circular, 54" L. Ft. 160 $ 725.00

26 HDPE - Oval, 54" L. Ft. 0

27 HDPE - Circular, 60" L. Ft. 140 $ 800.00

28 HDPE - Oval, 60" L. Ft. 0

29 HDPE - Circular, 66" L. Ft. 0

30 HDPE - Oval, 66" L. Ft. 0

31 HDPE - Circular, 72" L. Ft. 40 $ 1,200.00

32 HDPE - Oval, 72" L. Ft. 0

33 HDPE - Circular, 78" L. Ft. 0

34 HDPE - Oval, 78" L. Ft. 0

35 Drainage Work - Bank Protection, Dumped

Rip Rap CY 400 $ 1,000.00

36 Drainage Work - Bank Protection, Wire Tied

Rip Rap CY 200 $ 1,500.00

37 Drainage Work - Bank Protection, Soil-

Cement CY 300 $ 2,000.00

38 Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 L. Ft. 1 $ 1,000.00

39 Drainage Work - Rail Bank Protection, Rail

Bank Protection at Abutments, Type 4, 5, and 6 L. Ft. 1 $ 1,500.00

40 Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 L. Ft. 1 $ 750.00

41 Drainage Work - Jetting Hr. 30 $ 130.00

42 Drainage Work - Drilling Ft. 300 $ 100.00

43 Drainage Work - Drainage Excavation CY 300 $ 100.00

Drainage Work - Regrading cut ditch, resulting with no surplus material L. Ft. 250 $ 30.00

Drainage Work - Regrading cut ditch, resulting with surplus material to haul L. Ft. 250 $ 50.00

46 Hydrovac Services Hour 120 $ 600.00

47 Robotic Inspection Crawler CCTV Camera Hour 3 $ 150.00

48 Emergency Call Out Labor Hour 0 $ 135.00

49 Traffic Cones , 28”(height) Reflectorized EACH-DAY 250 $ 1.00

50 Flashing Arrow Panel EACH DAY 2 $ 50.00

51 Signs over 36” (High Intensity Reflective

Sheeting) EACH-DAY 12 $ 6.00

52 Sign Stand (Spring Type) EACH-DAY 12 $ 2.00

53 Pilot Vehicle with Driver HR 40 $ 60.00

54 Variable Message Board EACH DAY 2 $ 50.00

55 Type II Barricades EACH-DAY 20 $ 0.50

56 Warning Lights, Type A EACH-DAY 20 $ 0.50

57 Warning Lights, Type B EACH-DAY 20 $ 2.00

58 Warning Lights, Type C EACH-DAY 20 $ 0.50

59 Vertical Panels EACH-DAY 40 $ 0.50

60 Flag Type High Level Warning Device EACH-DAY 10 $ 9.00

61 Certified Civilian Flaggers HR 80 $ 36.00

62 DPS Law Enforcement Officers and Vehicles

HR 40 $ 100.00

63 Off-Duty uniformed Local Law Enforcement

Officer and vehicle HR 40 $ 100.00

64 Light Plant, day is 8 hours Day 2 $ 50.00

65 Mobilization - Southeast District Mile 250 175

Attachment 9

Price Sheet

Offerors are not required to bid on every District. Enter the Not to Exceed Unit Price in column F for

File details come from the government source that posted it. Updated .