This is a Method of Approach document for the Arizona Department of Transportation's On-Call Pipelining and Drainage Repair Services contract (BPM005628). The document outlines the bidder's proposed operational strategy for executing work in remote areas. Prior to pricing each task order, the Project Manager will conduct an onsite meeting with the district representative to identify specific schedule requirements for each location. The bidder indicates flexibility in work schedules, with a standard approach of four days per week at ten hours per day for remote locations, scalable to six days per week at ten hours per day if expedited schedules are required. The company also indicates capability to staff projects with multiple crews and management personnel to support around-the-clock operations when necessary to meet project deadlines.

Upon arrival at project sites, the bidder's crews will conduct safety meetings to review job hazard analysis and work plans before commencing operations. Standard mobilization time allows crews to begin work within fifteen minutes of arriving onsite, with the exception of major operations on the first day at a new location, which may require up to one hour for site walks and hazard identification. This approach demonstrates the bidder's commitment to safety protocols and operational readiness while maintaining flexibility to accommodate varying project demands across the state's remote work areas.

View the file

Other files

File Type Posted
BPM005628_Solicitation_Amendment_Summary_Three__3_.pdf PDF
6-Project Team.pdf PDF
Equipment Write up - Combined 11.20.23.pdf PDF
BPM005628 Summary of Negotiations - GCC 12.1.23.pdf PDF
BPM005628 Revised Price Sheet GCC 12.1.23.xlsx XLSX spreadsheet
6-5_BPM005628_References.pdf PDF
BPM005628 Request for BAFO - GCC 12.11.23.pdf PDF
6-3_BPM005628_SPO_Form_205_-_Forced_Labor_of_Ethnic_Uyghurs_Ban.pdf PDF
6-6_BPM005628_Confidentiality_and_Trade_Secrets.pdf PDF
6-8_BPM005628_Price_Increase_Percentages.pdf PDF
BPM005628 Revised Price Sheet Southwest Siteworks 12.12.23.xlsx XLSX spreadsheet
Mobilization Narrative 12.4.23.pdf PDF
BPM005628 Summary of Negotiations - SWSW.pdf PDF
BPM005628 Summary of Negotiations - SWSW 11.20.23.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 2 BPM005628 Boycott of Israel Disclosure.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 4 BPM005628 Subcontractors and Suppliers.pdf PDF
6-[On-Call Pipelining and Drainage Repair Services] 6 BPM005628 Confidentiality and Trade Secrets.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Two__2_.pdf PDF
BPM005628_Solicitation_Requirements_per_Amendment_Two__2_.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Four__4_.pdf PDF
BPM005628_Award_Documents.pdf PDF
BPM005628_Solicitation_Instructions.pdf PDF
Method of Approach - Drainage Excavation 11.20.23.pdf PDF
BPM005628 Revised Price Sheet_GCC 11.20.23.xlsx XLSX spreadsheet
BPM005628 Revised Price Sheet GCC 12.11.23.xlsx XLSX spreadsheet
6-Experience in Remote Areas.pdf PDF
6-4_BPM005628_Subcontractors_and_Suppliers.pdf PDF
6-Ordering and Maintaining Materials.pdf PDF
6-Method of Approach Pipe.pdf PDF
Method of Approach Drainage Excavation 11.20.23.pdf PDF
Experience in Remote Areas 11.20.23.pdf PDF
6-Method of Approach Remote Areas.pdf PDF
BPM005628_Pre-Solicitation_Documents.pdf PDF
BPM005628_Solicitation_Amendment_Summary_Five__5_.pdf PDF
BPM005628_Solicitation_Amendment_Summary_One__1_.pdf PDF
6-Operations Capacity.pdf PDF
6-Company History.pdf PDF
6-Method of Approach - Pipe.pdf PDF
6-2_BPM005628_Boycott_of_Israel_Disclosure.pdf PDF
6-9_BPM005628_Price_Sheet_Amendment_Three__3_Granite.xlsx XLSX spreadsheet
6-1_BPM005628_Offer_and_Acceptance.pdf PDF
6-Project Team .pdf PDF
SWSW Mob Cost Breakdown 12.4.23.pdf PDF
BPM005628 Revised Price Sheet Southwest Siteworks 12.4.23.xlsx XLSX spreadsheet
6-[On-Call Pipelining and Drainage Repair Services] 5 BPM005628 References.pdf PDF
Equipment List 11.20.23.pdf PDF
Method of Approach Pipe 11.20.23.pdf PDF
BPM005628 Revised Price Sheet 11.20.23.xlsx XLSX spreadsheet
6-[On-Call Pipelining and Drainage Repair Services] 3 BPM005628 SPO Form 205 - Forced Labor of Ethnic Uyghurs Ban.pdf PDF
6-Method of Approach Pipe_1.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

METHOD OF APPROACH

ADOT Procurement - On-Call Pipelining and Drainage Repair Services (BPM005628)

Provide your company’s method of approach for working in remote areas. At a minimum include the number of hours per day your company would be working and how soon your company would arrive on site before work is to commence.

Remote Work Areas:

Prior to providing a price for a task order Danny Hoback, Project Manager, will meet onsite with the district representative. During this site visit he will identify the schedule requirements for each location. Generally, in remote locations for this type of work we will work 4 days per week, 10 hours per day. However, if the situation warrants an expedited work schedule, our crews are accustomed to working up to 6 days per week 10 hours per day. We are also able to staff projects around the clock with multiple crews and management personnel to meet the desired schedule. Once onsite our crews will conduct a safety meeting to review the job hazard analysis and work plan for the operation. In most cases the crews will commence work within 15 minutes of arriving onsite. On the first day at a new location for a major operation the crew will walk the site and review all potential hazards which may result in up to one hour from the time of arrival until work commences.