This is a revised price sheet for the On-Call Pipelining and Drainage Repair Services contract issued by the Arizona Department of Transportation. The price sheet establishes unit rates for materials and services across multiple categories, including High-Density Polyethylene (HDPE) pipe in circular and oval configurations ranging from 12 inches to 78 inches in diameter, drainage work services, inspection and maintenance equipment, traffic control devices, labor resources, and mobilization costs. HDPE pipe line items comprise the majority of the pricing schedule, with circular 24-inch pipe representing the highest annual estimated quantity at 2,240 linear feet and oval 78-inch pipe commanding the highest unit price at $1,965 per linear foot. Drainage work services include bank protection options using rip rap and soil-cement, rail bank protection at drainage ways and abutments, jetting, drilling, and excavation services. The schedule also covers specialized services such as hydrovac services, robotic inspection crawler camera inspection, emergency call-out labor, and traffic control resources including cones, signs, barricades, warning lights, and flaggers.
The price sheet establishes not-to-exceed unit prices for statewide annual estimated quantities across all line items, with rates varying significantly based on pipe diameter and material configuration. Traffic control and labor rates include certified civilian flaggers at $85 per hour, DPS law enforcement officers at $105 per hour, and off-duty local law enforcement at $125 per hour. Mobilization costs are standardized at $65 per mile across seven geographic districts within Arizona, with estimated annual quantities ranging from 150 miles for the Central District to 3,000 miles for the Northeast District. The pricing structure reflects an on-call service model with pre-negotiated rates applicable to emergency repairs and scheduled maintenance activities throughout the state's transportation infrastructure.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statewide
| Line Item | Description | UOM (unit of Measure) | Statewide ANNUAL Estimated Quantities | Not-to-Exceed Unit Price |
| 1 | HDPE - Circular, 12" | L. Ft. | 360 | $122.00 |
| 2 | HDPE - Oval, 12" | L. Ft. | 120 | $375.00 |
| 3 | HDPE - Circular, 15" | L. Ft. | 120 | $150.00 |
| 4 | HDPE - Oval, 15" | L. Ft. | 20 | $600.00 |
| 5 | HDPE - Circular, 18" | L. Ft. | 1,450 | $200.00 |
| 6 | HDPE - Oval, 18" | L. Ft. | 220 | $425.00 |
| 7 | HDPE - Circular, 21" | L. Ft. | 360 | $250.00 |
| 8 | HDPE - Oval, 21" | L. Ft. | 200 | $565.00 |
| 9 | HDPE - Circular, 24" | L. Ft. | 2,240 | $300.00 |
| 10 | HDPE – Oval, 24" | L. Ft. | 520 | $500.00 |
| 11 | HDPE - Circular, 27" | L. Ft. | 760 | $325.00 |
| 12 | HDPE - Oval, 27" | L. Ft. | 200 | $570.00 |
| 13 | HDPE - Circular, 30" | L. Ft. | 1,300 | $375.00 |
| 14 | HDPE - Oval, 30" | L. Ft. | 330 | $670.00 |
| 15 | HDPE - Circular, 33" | L. Ft. | 820 | $395.00 |
| 16 | HDPE - Oval, 33" | L. Ft. | 300 | $675.00 |
| 17 | HDPE - Circular, 36" | L. Ft. | 1,110 | $475.00 |
| 18 | HDPE - Oval, 36" | L. Ft. | 490 | $790.00 |
| 19 | HDPE - Circular, 39" | L. Ft. | 820 | $480.00 |
| 20 | HDPE - Oval, 39" | L. Ft. | 200 | $1,060.00 |
| 21 | HDPE - Circular, 42" | L. Ft. | 960 | $595.00 |
| 22 | HDPE - Oval, 42" | L. Ft. | 120 | $1,250.00 |
| 23 | HDPE - Circular, 48" | L. Ft. | 1,160 | $755.00 |
| 24 | HDPE - Oval, 48" | L. Ft. | 200 | $1,265.00 |
| 25 | HDPE - Circular, 54" | L. Ft. | 780 | $890.00 |
| 26 | HDPE - Oval, 54" | L. Ft. | 100 | $1,800.00 |
| 27 | HDPE - Circular, 60" | L. Ft. | 760 | $895.00 |
| 28 | HDPE - Oval, 60" | L. Ft. | 100 | $1,810.00 |
| 29 | HDPE - Circular, 66" | L. Ft. | 560 | $1,210.00 |
| 30 | HDPE - Oval, 66" | L. Ft. | 100 | $1,780.00 |
| 31 | HDPE - Circular, 72" | L. Ft. | 600 | $1,195.00 |
| 32 | HDPE - Oval, 72" | L. Ft. | 100 | $1,870.00 |
| 33 | HDPE - Circular, 78" | L. Ft. | 560 | $1,280.00 |
| 34 | HDPE - Oval, 78" | L. Ft. | 100 | $1,965.00 |
| 35 | Drainage Work - Bank Protection, Dumped Rip Rap | CY | 2,125 | $380.00 |
| 36 | Drainage Work - Bank Protection, Wire Tied Rip Rap | CY | 850 | $515.00 |
| 37 | Drainage Work - Bank Protection, Soil-Cement | CY | 950 | $1,330.00 |
| 38 | Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 | L. Ft. | 1,682 | $870.00 |
| 39 | Drainage Work - Rail Bank Protection, Rail Bank Protection at Abutments, Type 4, 5, and 6 | L. Ft. | 1,682 | $690.00 |
| 40 | Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 | L. Ft. | 1,682 | $520.00 |
| 41 | Drainage Work - Jetting | Hr. | 460 | $400.00 |
| 42 | Drainage Work - Drilling | Ft. | 1,850 | $65.00 |
| 43 | Drainage Work - Drainage Excavation | CY | 2,050 | $26.00 |
| 44 | Drainage Work - Regrading cut ditch, resulting with no surplus material | L. Ft. | 17,561 | $4.00 |
| 45 | Drainage Work - Regrading cut ditch, resulting with surplus material to haul | L. Ft. | 12,531 | $25.00 |
| 46 | Hydrovac Services | Hour | 840 | $540.00 |
| 47 | Robotic Inspection Crawler CCTV Camera | Hour | 100 | $295.00 |
| 48 | Emergency Call Out Labor | Hour | 240 | $240.00 |
| 49 | Traffic Cones , 28”(height) Reflectorized | EACH-DAY | 1,062 | $9.00 |
| 50 | Flashing Arrow Panel | EACH DAY | 19 | $48.00 |
| 51 | Signs over 36” (High Intensity Reflective Sheeting) | EACH-DAY | 96 | $10.00 |
| 52 | Sign Stand (Spring Type) | EACH-DAY | 96 | $10.00 |
| 53 | Pilot Vehicle with Driver | HR | 280 | $80.00 |
| 54 | Variable Message Board | EACH DAY | 35 | $85.00 |
| 55 | Type II Barricades | EACH-DAY | 142 | $10.00 |
| 56 | Warning Lights, Type A | EACH-DAY | 160 | $9.00 |
| 57 | Warning Lights, Type B | EACH-DAY | 160 | $11.00 |
| 58 | Warning Lights, Type C | EACH-DAY | 160 | $8.00 |
| 59 | Vertical Panels | EACH-DAY | 320 | $9.00 |
| 60 | Flag Type High Level Warning Device | EACH-DAY | 80 | $9.00 |
| 61 | Certified Civilian Flaggers | HR | 520 | $85.00 |
| 62 | DPS Law Enforcement Officers and Vehicles | HR | 280 | $105.00 |
| 63 | Off-Duty uniformed Local Law Enforcement Officer and vehicle | HR | 280 | $125.00 |
| 64 | Light Plant, day is 8 hours | Day | 22 | $220.00 |
| 65 | Mobilization - Central District | Mile | 150 | $65.00 |
| 66 | Mobilization - Northcentral District | Mile | 1,800 | $65.00 |
| 67 | Mobilization - Northeast District | Mile | 3,000 | $65.00 |
| 68 | Mobilization - Northwest District | Mile | 260 | $65.00 |
| 69 | Mobilization - Southwest District | Mile | 280 | $65.00 |
| 70 | Mobilization - Southcentral District | Mile | 280 | $65.00 |
| 71 | Mobilization - Southeast District | Mile | 250 | $65.00 |