BPM005628 Revised Price Sheet 11.20.23.xlsx
XLSX spreadsheet 20 KB Posted
- Attached to
- On-Call Pipelining and Drainage Repair Services
- Solicitation number
- BPM005628
- Issued by
- Arizona
About this file
Summary
This is a revised price sheet for on-call pipelining and drainage repair services required by the State of Arizona Department of Transportation. The price sheet establishes not-to-exceed unit pricing for 71 line items categorized into HDPE pipe products, drainage work services, inspection and labor services, traffic control equipment, and mobilization services across six geographic districts. HDPE offerings range from 12-inch to 78-inch diameter pipes in both circular and oval configurations, with annual estimated quantities varying from 20 to 2,240 linear feet. Drainage work encompasses bank protection services using dumped rip rap, wire-tied rip rap, and soil-cement applications; rail bank protection at drainage ways and abutments; jetting, drilling, and excavation services; and regrading of cut ditches. Additional services include hydrovac operations, robotic CCTV camera inspections, emergency call-out labor, and traffic management support including flaggers, pilot vehicles, law enforcement coordination, and signage.
Pricing is structured as not-to-exceed unit rates with annual estimated quantities serving as planning benchmarks rather than guaranteed minimums. Unit prices for HDPE pipe range from $300 to $1,400 per linear foot depending on diameter and configuration. Drainage work pricing varies from $10 per linear foot for regrading without surplus material to $2,000 per cubic yard for soil-cement bank protection. Traffic control and labor services are priced hourly or per-day, with rates ranging from $0.50 to $650 per unit. Mobilization services are priced by mile for seven geographic districts—Central, Northcentral, Northeast, Northwest, Southwest, Southcentral, and Southeast—with rates ranging from $70 to $300 per mile, reflecting varying distances and service areas across Arizona.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statewide
| Line Item | Description | UOM (unit of Measure) | Statewide ANNUAL Estimated Quantities | Not-to-Exceed Unit Price |
| 1 | HDPE - Circular, 12" | L. Ft. | 360 | $300.00 |
| 2 | HDPE - Oval, 12" | L. Ft. | 120 | $400.00 |
| 3 | HDPE - Circular, 15" | L. Ft. | 120 | $350.00 |
| 4 | HDPE - Oval, 15" | L. Ft. | 20 | $500.00 |
| 5 | HDPE - Circular, 18" | L. Ft. | 1,450 | $350.00 |
| 6 | HDPE - Oval, 18" | L. Ft. | 220 | $450.00 |
| 7 | HDPE - Circular, 21" | L. Ft. | 360 | $350.00 |
| 8 | HDPE - Oval, 21" | L. Ft. | 200 | $450.00 |
| 9 | HDPE - Circular, 24" | L. Ft. | 2,240 | $ 350.00 |
| 10 | HDPE – Oval, 24" | L. Ft. | 520 | $ 450.00 |
| 11 | HDPE - Circular, 27" | L. Ft. | 760 | $ 400.00 |
| 12 | HDPE - Oval, 27" | L. Ft. | 200 | $ 500.00 |
| 13 | HDPE - Circular, 30" | L. Ft. | 1,300 | $ 400.00 |
| 14 | HDPE - Oval, 30" | L. Ft. | 330 | $ 500.00 |
| 15 | HDPE - Circular, 33" | L. Ft. | 820 | $ 450.00 |
| 16 | HDPE - Oval, 33" | L. Ft. | 300 | $ 550.00 |
| 17 | HDPE - Circular, 36" | L. Ft. | 1,110 | $ 450.00 |
| 18 | HDPE - Oval, 36" | L. Ft. | 490 | $ 550.00 |
| 19 | HDPE - Circular, 39" | L. Ft. | 820 | $ 500.00 |
| 20 | HDPE - Oval, 39" | L. Ft. | 200 | $ 600.00 |
| 21 | HDPE - Circular, 42" | L. Ft. | 960 | $ 650.00 |
| 22 | HDPE - Oval, 42" | L. Ft. | 120 | $ 750.00 |
| 23 | HDPE - Circular, 48" | L. Ft. | 1,160 | $ 700.00 |
| 24 | HDPE - Oval, 48" | L. Ft. | 200 | $ 800.00 |
| 25 | HDPE - Circular, 54" | L. Ft. | 780 | $ 750.00 |
| 26 | HDPE - Oval, 54" | L. Ft. | 100 | $ 850.00 |
| 27 | HDPE - Circular, 60" | L. Ft. | 760 | $ 800.00 |
| 28 | HDPE - Oval, 60" | L. Ft. | 100 | $ 900.00 |
| 29 | HDPE - Circular, 66" | L. Ft. | 560 | $ 1,050.00 |
| 30 | HDPE - Oval, 66" | L. Ft. | 100 | $ 1,200.00 |
| 31 | HDPE - Circular, 72" | L. Ft. | 600 | $ 1,100.00 |
| 32 | HDPE - Oval, 72" | L. Ft. | 100 | $ 1,300.00 |
| 33 | HDPE - Circular, 78" | L. Ft. | 560 | $ 1,200.00 |
| 34 | HDPE - Oval, 78" | L. Ft. | 100 | $ 1,400.00 |
| 35 | Drainage Work - Bank Protection, Dumped Rip Rap | CY | 2,125 | $ 1,000.00 |
| 36 | Drainage Work - Bank Protection, Wire Tied Rip Rap | CY | 850 | $ 1,500.00 |
| 37 | Drainage Work - Bank Protection, Soil-Cement | CY | 950 | $ 2,000.00 |
| 38 | Drainage Work - Rail Bank Protection, Drainage Ways, Type 1, 2, and 3 | L. Ft. | 1,682 | $ 1,000.00 |
| 39 | Drainage Work - Rail Bank Protection, Rail Bank Protection at Abutments, Type 4, 5, and 6 | L. Ft. | 1,682 | $ 1,500.00 |
| 40 | Drainage Work - Rail Bank Protection, Drainage Ways, Type 7, 8, and 9 | L. Ft. | 1,682 | $ 650.00 |
| 41 | Drainage Work - Jetting | Hr. | 460 | $ 130.00 |
| 42 | Drainage Work - Drilling | Ft. | 1,850 | $ 150.00 |
| 43 | Drainage Work - Drainage Excavation | CY | 2,050 | $ 100.00 |
| 44 | Drainage Work - Regrading cut ditch, resulting with no surplus material | L. Ft. | 17,561 | $ 10.00 |
| 45 | Drainage Work - Regrading cut ditch, resulting with surplus material to haul | L. Ft. | 12,531 | $ 26.00 |
| 46 | Hydrovac Services | Hour | 840 | $ 650.00 |
| 47 | Robotic Inspection Crawler CCTV Camera | Hour | 100 | $ 150.00 |
| 48 | Emergency Call Out Labor | Hour | 240 | $ 150.00 |
| 49 | Traffic Cones , 28”(height) Reflectorized | EACH-DAY | 1,062 | $ 1.00 |
| 50 | Flashing Arrow Panel | EACH DAY | 19 | $ 50.00 |
| 51 | Signs over 36” (High Intensity Reflective Sheeting) | EACH-DAY | 96 | $ 6.00 |
| 52 | Sign Stand (Spring Type) | EACH-DAY | 96 | $ 2.00 |
| 53 | Pilot Vehicle with Driver | HR | 280 | $ 60.00 |
| 54 | Variable Message Board | EACH DAY | 35 | $ 50.00 |
| 55 | Type II Barricades | EACH-DAY | 142 | $ 0.50 |
| 56 | Warning Lights, Type A | EACH-DAY | 160 | $ 0.50 |
| 57 | Warning Lights, Type B | EACH-DAY | 160 | $ 2.00 |
| 58 | Warning Lights, Type C | EACH-DAY | 160 | $ 0.50 |
| 59 | Vertical Panels | EACH-DAY | 320 | $ 0.50 |
| 60 | Flag Type High Level Warning Device | EACH-DAY | 80 | $ 9.00 |
| 61 | Certified Civilian Flaggers | HR | 520 | $ 36.00 |
| 62 | DPS Law Enforcement Officers and Vehicles | HR | 280 | $ 100.00 |
| 63 | Off-Duty uniformed Local Law Enforcement Officer and vehicle | HR | 280 | $ 100.00 |
| 64 | Light Plant, day is 8 hours | Day | 22 | $ 50.00 |
| 65 | Mobilization - Central District | Mile | 150 | $ 150.00 |
| 66 | Mobilization - Northcentral District | Mile | 1,800 | 70 |
| 67 | Mobilization - Northeast District | Mile | 3,000 | 70 |
| 68 | Mobilization - Northwest District | Mile | 260 | 70 |
| 69 | Mobilization - Southwest District | Mile | 280 | 175 |
| 70 | Mobilization - Southcentral District | Mile | 280 | 300 |
| 71 | Mobilization - Southeast District | Mile | 250 | 175 |
File details come from the government source that posted it. Updated .