Amendment A007.pdf
PDF 320 KB Posted
- Solicitation number
- 69056725B000001
About this file
This is Amendment A007 to solicitation 69056725B000001 issued by the Department of Transportation Federal Highway Administration for the Neck Lake Road Reconstruction project in Alaska. The amendment makes several revisions to the Special Contract Requirements sections, including changes to soil erosion and sediment control requirements, rock blasting qualifications, and geotechnical exploration specifications.
Key modifications include revising the timing of in-water work requirements, deleting subsection (d) of blasting qualifications, removing FP-14 requirements for pre-blast condition surveys, updating specifications for PAG rock disposal site preparation, and revising rental equipment descriptions. The amendment maintains the original response date and does not extend the solicitation period. The overall project involves reconstruction of Neck Lake Road from NPOWI Highway to Marine Access Facility Junction, with an estimated price range of $10-20 million and anticipated completion in Fall 2026.
View the file
Other files
Show 40 more
Latest 50 of 62 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE
N/A
PAGE
2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE NO. 5. PROJECT NO. (If applicable)
A007 1/3/2025 N/A AK PFH 58(1), Neck Lake Road Reconstruction: NPOWI HWY. TO
MARINE ACCESS FACILITY JCT.
6. ISSUED BY CODE N/A 7. ADMINISTERED BY (If other than Item 6) CODE N/A
Department of Transportation Federal Highway Administration 610 East Fifth Street Vancouver WA 98661-3801
8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and Zip Code) 9A. AMENDMENT OF SOLICITATION NO.
X
69056725B000001
9B. DATED (SEE ITEM 11)
11/18/2024
10A. MODIFICATION OF CONTRACT/ORDER NO.
N/A
10B. DATED (SEE ITEM 13)
CODE: N/A FACILITY CODE: N/A N/A
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
| X | The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers (_ ) is extended, ( X ) is not extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A THIS CHANGE ORDER IS ISSUED PURSUANT TO (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN
ITEM 10A.
N/A
B THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (Such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
N/A
C THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
N/A
D OTHER (Specify type of modification and authority) N/A
E. IMPORTANT: Contractor n/a is not, n/a is required to sign this document and return n/a copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
AK PFH 58(1), Neck Lake Road Reconstruction: Neck Lake Road Reconstruction: NPOWI Hwy. to Marine Access Facility Jct.
See page 2
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15a. NAME AND TITLE OF SIGNER (Type or print) 15a. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
N/A
15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED
BY_________________________________________ BY N/A___________________________ N/A (Signature of person authorized to sign) (Signature of Contracting Officer)
NSN 7540-01-152-8070
PREVIOUS EDITION NOT USABLE
30-105 STANDARD FORM 30 (REV. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
Amendment No. A007, dated 1/3/2025 AK PFH 58(1) Solicitation No. 69056725B000001 Neck Lake Road Reconstruction: NPOWI Hwy. to Page 2 Marine Access Facility Jct.
REVISIONS ARE AS FOLLOWS:
SPECIAL CONTRACT REQUIREMENTS
Page E-54, Subsection 157.04, General. Revises fifth paragraph.
Page F-10, Subsection 205.04, Qualifications. Deletes Subsection (d).
Page F-11, Subsection 205.06, Pre-blast Condition Survey and Blast Monitoring and Control. Deletes FP-14 requirements under this Subsection.
Page F-24, Subsection 271.03, General. Revises the first paragraph.
Page F-46, Subsection 622.01, DESCRIPTION. Revises Subsection (e).
ENCLOSURES
Pages:
E-54 / F-10 through F-11 / F-24 / F-46
E-54 DIVISION 150
Special Contract Requirements Project: AK PFH 58(1), Neck Lake Road Reconstruction: NPOWI Hwy. to Marine Access Facility Jct.
Section 157. — SOIL EROSION AND SEDIMENT CONTROL
01/06/23(2)– FP-14
Material
157.02 Add the following to the material list:
Filter Rock 705.08
Construction Requirements
157.03 Qualifications. Delete this Subsection and substitute the following:
Provide an Erosion Control Supervisor (ECS) meeting one of the following criteria:
(a) Alaska Certified Erosion and Sediment Control Lead (AK-CESCL)
(b) Certified Professional in Erosion and Sediment Control (CPESC);
(c) Certified Professional in Storm Water Quality (CPSWQ);
(d) Certified Erosion, Sediment and Storm Water Inspector (CESSWI); or
(e) Certified Inspector of Sediment and Erosion Control (CISEC).
157.04 General. Delete the text of this Subsection and substitute the following:
Provide and install permanent and temporary measures to control erosion, sedimentation, and discharge of pollutants, according to the Alaska Pollutant Discharge Elimination System (APDES) Construction General Permit (CGP), the project Storm Water Pollution Prevention Plan (SWPPP) of record, and this contract.
Immediately report to the CO any incident of non-compliance with the CGP that may endanger health or the environment. Provide copies of any correspondence or reports required by either the CGP or the SWPPP.
Provide an ECS to manage installation, maintenance, inspection, and reporting for erosion and sediment control measures, maintain and update the SWPPP of record, and prepare any documentation required by the CGP or the SWPPP. Furnish the ECS’s name, project office address, 24-hour telephone number(s), and qualifications at the preconstruction conference.
If wood chips are used, do not import without approval from the CO.
Limit the timing of in-water work according to Subsection 107.10(e)(9) 107.10(e)(7).
Revised by Amendment A007
F-10 DIVISION 200
Project: AK PFH 58(1), Neck Lake Road Reconstruction: NPOWI Hwy. to Marine Access Facility Jct.
Section 205. — ROCK BLASTING
Construction Requirements
205.04 Qualifications. Delete Subsection (d).
205.04A Blasting Consultant. (Added Subsection.)
Provide a blasting consultant with at least 10 years experience in the field of rock blasting as a designer of blasts with controlled blasting techniques. Use a blasting consultant that is not an employee of the Contractor, an explosives manufacturer, or explosives distributor.
(a) Use a blast consultant to:
(1) Assist in the blast design.
(2) Attend the preconstruction conference.
(3) Make on-site inspections of the blast site before the submittal of each blast plan.
(4) Make on-site inspections during drilling, loading, and blasting of test sections.
(5) Make on-site inspections during drilling, loading, and blasting of production sections.
(6) Approve all blasting plans and modifications. Include with each blast plan submitted to the CO written evidence that the blasting consultant has reviewed and approved the blasting plan.
(b) Provide the following to the CO before the preconstruction conference:
(1) A resume of the proposed blasting consultant. Include educational background related to blasting and a detailed resume of experience in the blasting field.
(2) A list of at least five highway rock projects that demonstrate successfully completed work on which the blasting consultant has worked in the capacity of a consultant in blast design.
List a description of the projects, details of the blast plan, and modifications made during the project. List names and telephone numbers of project owners with sufficient knowledge of the project to verify the submitted information.
(3) A cost breakdown of the individual items included in the lump sum blasting consultant item for use in making progress payments.
Based on the documentation provided, the CO will notify the Contractor of the acceptability of the proposed blasting consultant under the terms of the contract within 14 days.
Revised by Amendment A002
F-11 DIVISION 200
Project: AK PFH 58(1), Neck Lake Road Reconstruction: NPOWI Hwy. to Marine Access Facility Jct.
205.05 Blasting Plans. Amend as follows:
Add the following to the first paragraph:
All blasting plans and modifications to the plans must be signed by the CO. Do not begin drilling the blast pattern or deliver explosives to the project until the general blasting plan and site-specific blast plan are accepted.
Add the following to paragraph (a):
Allow 7 days for review and approval of the general blasting plan. Submit revisions and updates to the CO within 48 hours of any change in the general blasting plan.
Add the following to paragraph (b):
(11) Any rockfall containment designs and procedures; and
(12) Include an attenuation study for affected structures and indicate that the peak particle velocity versus peak frequency will not damage each structure when structures are within an area of ground vibration and/or air-blast overpressure concern.
205.06 Pre-blast Condition Survey and Blast Monitoring and Control. Delete the text of this Subsection.
205.06 Pre-blast Condition Survey and Blast Monitoring and Control. Amend as follows:
Delete the text of paragraph (c) and substitute the following:
(c) Control ground vibrations and air-blast over-pressures with properly designed delay sequences and maximum allowable charge weights per delay. Verify allowable charge weights per delay by conducting representative trial blasts and measuring ground vibrations and air-blast over-pressure levels. The attenuation study will enable successful prediction of the peak particle velocity in any component (longitudinal, transverse, or vertical) anywhere on the surface of the structure(s). Conduct test blasts with blast plan modifications that limit ground vibrations and air-blast over-pressures to levels that will not cause damage to nearby buildings, structures, utilities and/or natural features as determined by the Vibration Specialist. Submit a copy of the attenuation study results and predicted peak particle velocity versus peak frequency for each structure.
Add the following:
Submit a copy of the interpreted seismograph and air-blast records to the CO with a certifying signature by the Vibration Specialist. If actual peak particle velocity versus peak frequency measurements exceed those predicted for a structure, the site-specific blast plan will need to be
Revised by Amendment A002
F-24 DIVISION 250
Project: AK PFH 58(1), Neck Lake Road Reconstruction: NPOWI Hwy. to Marine Access Facility Jct.
Section 271. — GEOTECHNICAL EXPLORATION
(ADDED SECTION)
08/01/14–FP14
Description
271.01 This work consists of installing piezometers for pore water pressure monitoring during soft ground embankment construction and surcharging.
This work also consists of installing piezometers for water quality monitoring at the rock disposal site.
Material
271.02 Conform to the following Subsections:
Piezometers 708.05(e)
Construction Requirements
271.03 General. Install 2 inch to 3 inch slotted PVC pipe piezometers in conjunction with settlement plate assemblies according to Subsection 204.10A and as shown on the plans. The piezometer depth for the soft ground embankment areas that do not require subexcavation is to be approximately 5 feet below the original ground elevation. Whereas the piezometer depth for the Type 3 soft ground embankment area that requires subexcavation is to be approximately 5 feet below the reduced surface elevation after the subexcavation is completed. Install 2 inch to 3 inch slotted PVC pipe piezometers in conjunction with potentially acid-generating (PAG) material disposal and containment according to Section 646 and as shown on the plans. The depth for the two piezometers placed along the limestone filter trench at the PAG rock disposal site is to be approximately 5 feet. Whereas the depth for the two piezometers (with data logger) at the PAG rock disposal site should be assumed to be up to 30 feet for bidding purposes. See Section 646 for rock disposal site location. Adjust piezometer location (and depths) to match field conditions as approved. Provide a cap at the bottom of the piezometer.
Provide removable cap assembly at the top of the piezometer. Provide construction details to the CO, including depth, size, slotting, and top of piezometer pipe elevation seven days before installation for approval.
Protect piezometer installations. Repair or replace PVC deviating from a vertical position by one foot or horizontally by one foot or that become uncoupled or broken due to Contractor operations.
271.04 Pore Water Monitoring for Settlement. Record the elevation of the top of the water level according to Section 152 in the presence of the CO. Determine the location of the settlement plate assembly installation in plan to an accuracy of 0.01 feet and in elevation to an accuracy of
0.01 feet. Cap the casing immediately after the elevation is determined. Stamp or label the casing cap with the installation date and location.
Install additional casing sections on the piezometer as required as embankment construction proceeds to keep the top of the casing above the embankment and surcharge.
Clearly mark and flag each assembly as approved by the CO.
F-46 DIVISION 600
Project: AK PFH 58(1), Neck Lake Road Reconstruction: NPOWI Hwy. to Marine Access Facility Jct.
Section 622. — RENTAL EQUIPMENT
08/01/14–FP14
Description
622.01 Delete the text of this Subsection and substitute the following:
This work consists of furnishing and operating equipment for the construction work as ordered by the CO and listed below. Work under this Section does not include equipment time used to perform work provided for under any other pay item shown in the bid schedule. The work anticipated under this Section includes:
(a) Minor landscaping;
(b) Minor drainage corrections;
(c) Removal of miscellaneous items;
(d) Maintenance of detour route;
(e) PAG rock disposal site preparation and access route (NF 3060) maintenance; and
(f) Removal of hazard trees outside clearing limits and within existing roadway easements.
Construction Requirements
622.02 Rental Equipment. Delete the text of the first paragraph and substitute the following:
Furnish and operate the following equipment:
Number of Units Type of Equipment 1 Dump truck, 10 cubic yard minimum capacity
1 Backhoe loader, 10 cubic yard minimum capacity, 36-inch width
1 Wheel loader, 4 cubic yard minimum rated capacity
1 Bulldozer, 120 hp minimum flywheel power
1 Roller
1 Motor grader, 12 foot minimum blade
1 Hydraulic excavator, 1 cubic yard minimum capacity with thumb attachment
1 Chain saw, with operator
Submit the model number and serial number for each piece of equipment before use. Make equipment available for inspection and approval before use.