About this opportunity

The Federal Highway Administration is seeking a contractor to reconstruct approximately 6 miles of Neck Lake Road located 45 miles northwest of Coffman Cove on Prince of Wales Island, Alaska. The project involves comprehensive roadway reconstruction including excavation, sub-excavation, soft ground embankment construction, grading, rock blasting, drainage installation, aggregate surface course placement, guardrail installation, erosion control, temporary traffic control, and turf establishment. The solicitation will be offered through a sealed bid, firm-fixed-price contract with full and open competition on an unrestricted basis. Potential bidders must submit their proposals by January 14, 2025, with questions to be submitted via email to wfl.contracts@dot.gov. The contract requires detailed technical capabilities, including experience with rock blasting, drainage construction, and potentially acid generating (PAG) rock management.

The project is not set aside for any specific contractor type and will be open to all qualified bidders. The estimated contract value ranges between $10,000,000 and $20,000,000, with the work divided into three separate bid schedules of 1.6, 2.0, and 2.4 miles, though only one schedule will be awarded. The tentative project completion date is Fall 2026, with a notice to proceed date of March 6, 2025, and all work required to be completed by October 31, 2026. The place of performance is in the Hyder Census Area of Prince of Wales Island, Alaska, specifically along the route connecting the North Prince of Wales Island Highway to the Marine Access Facility Junction. Bid evaluation will focus on technical capabilities, compliance with specifications, and competitive pricing across the proposed schedules.

Notice text

2 versions

Update #2 · Latest ·

UPDATE 11/19/2024: Physical data files updated af05801_SEGMENT1_proposed-alignment.pdf and af05801_SEGMENT1_proposed-profile.pdf. Physical data file added- af05801_XS_Labeled_SchA.pdf.

PROJECT: AK PFH 58(1), Neck Lake Rd. Reconstruction: NPOWI Hwy.to Marine Access Facility Jct.
LOCATION:  45 miles NW of Coffman Cove, Hyder Census Area, Prince of Wales Island, Alaska
WORK: Work consists of roadway excavation, sub-excavation, soft ground embankment construction (surcharge), grading, rock blasting, riprap placement, rockery, drainage (including large Aquatic Organism Pipes), embankment (including settlement monitoring), placement of aggregate surface course, guardrail installation, erosion control, temporary traffic control, permanent signage, and turf establishment.  See “Project Description” for additional details

LENGTH: 
Schedule A – 1.6 miles of road reconstruction
Schedule B – 2.0 miles of road reconstruction
Schedule C – 2.4 miles of road reconstruction

TENTATIVE COMPLETION DATE:  Fall 2026

CONTRACT TYPE: Sealed Bid, Firm-Fixed-Price

ESTIMATED PRICE RANGE: Between $10,000,000 and $20,000,000

INTERESTED VENDORS LIST: To view the Interested Vendors List, you must register as a SAM user, be logged in, and linked to an entity. If you are signed into SAM.gov with your registered entity and you cannot see the Interested Vendors List, you will need to be assigned the Contract Opportunities Administrator role for your entity in SAM.gov. If you need assistance, call the Federal Service Desk at 866-606-8220.

THIS SOLICITATION IS OFFERED FOR FULL AND OPEN COMPETITION ON AN UNRESTRICTED BASIS

This project is anticipated to be solicited Winter 2024/2025                      

This project will include 3 bid schedules. Only one schedule will be awarded.
 

Update #1 ·

PROJECT: AK PFH 58(1), Neck Lake Rd. Reconstruction: NPOWI Hwy.to Marine Access Facility Jct.
LOCATION:  45 miles NW of Coffman Cove, Hyder Census Area, Prince of Wales Island, Alaska
WORK: Work consists of roadway excavation, sub-excavation, soft ground embankment construction (surcharge), grading, rock blasting, riprap placement, rockery, drainage (including large Aquatic Organism Pipes), embankment (including settlement monitoring), placement of aggregate surface course, guardrail installation, erosion control, temporary traffic control, permanent signage, and turf establishment.  See “Project Description” for additional details

LENGTH: 
Schedule A – 1.6 miles of road reconstruction
Schedule B – 2.0 miles of road reconstruction
Schedule C – 2.4 miles of road reconstruction

TENTATIVE COMPLETION DATE:  Fall 2026

CONTRACT TYPE: Sealed Bid, Firm-Fixed-Price

ESTIMATED PRICE RANGE: Between $10,000,000 and $20,000,000

INTERESTED VENDORS LIST: To view the Interested Vendors List, you must register as a SAM user, be logged in, and linked to an entity. If you are signed into SAM.gov with your registered entity and you cannot see the Interested Vendors List, you will need to be assigned the Contract Opportunities Administrator role for your entity in SAM.gov. If you need assistance, call the Federal Service Desk at 866-606-8220.

THIS SOLICITATION IS OFFERED FOR FULL AND OPEN COMPETITION ON AN UNRESTRICTED BASIS

This project is anticipated to be solicited Winter 2024/2025                      

This project will include 3 bid schedules. Only one schedule will be awarded.
 

Files

File Type Posted
BidTab Neck Lake Road Reconstruction.pdf PDF
BidSum-AK PFH 58(1).pdf PDF
QA_01-08-2025.pdf PDF
Amendment A008.pdf PDF
QA_01-07-2025.pdf PDF
Amendment A007.pdf PDF
Amendment A006.pdf PDF
QA_12-30-2024.pdf PDF
Amendment A005.pdf PDF
Amendment A004.pdf PDF
QA_12-16-2024.pdf PDF
Amendment A003.pdf PDF
Amendment A002.pdf PDF
QA_12-13-2024.pdf PDF
QA_12-18-2024.pdf PDF
QA_12-06-2024.pdf PDF
Amendment A001.pdf PDF
QA_12-05-2024.pdf PDF
QA_11-26-2024.pdf PDF
af05801_SEGMENT1_proposed-profile.pdf PDF
af05801_SEGMENT1_proposed-alignment.pdf PDF
af05801_XS_Labeled_SchA.pdf PDF
ak pfh 58(1)_FinalHydraulicReport.pdf PDF
ak pfh 58(1)_GR0818.pdf PDF
Neck Lake Physical Data.zip ZIP file
af05801_TIE4_proposed-profile.pdf PDF
af05801_XS_SchB.pdf PDF
af05801_XS_Labeled_SchB.pdf PDF
af05801_TIE1_proposed-profile.pdf PDF
ak pfh 58(1)_Neck Lake ARD Technical Memorandum.pdf PDF
af05801_XS_SchC.pdf PDF
af05801_TIE2_superelevation.pdf PDF
ak pfh 58(1)_NeckLakeRoad_Rockery_TM 1.21.2019.pdf PDF
af05801_TIE4_proposed-alignment.pdf PDF
af05801_TIE3_proposed-profile.pdf PDF
af05801_TIE4_superelevation.pdf PDF
af05801_TIE3_superelevation.pdf PDF
af05801_TIE3_Earthwork.pdf PDF
af05801_BULK_superelevation.pdf PDF
af05801_TIE2_proposed-profile.pdf PDF
ak pfh 58(1)_GR1516_pp1-384.pdf PDF
af05801_BULK_proposed-profile.pdf PDF
af05801_SEGMENT1_proposed-profile.pdf PDF
af05801_XS_Labeled_SchC.pdf PDF
af05801_BULK_proposed-alignment.pdf PDF
af05801_TIE1_proposed-alignment.pdf PDF
aka-pfh58-1_SWPPP for compilation_Final.pdf PDF
af05801_SchedC_Earthwork.pdf PDF
Neck Lake Plans ak pfh 58(1)_plans Updated 2024.10.31.pdf PDF
af05801_XS_SchA.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

Notice history

Notice Type Posted
AK PFH 58(1), Neck Lake Road Reconstruction: NPOWI Hwy. to Marine Access Facility Jct. Award Award Notice
This notice Latest solicitation Solicitation
AK PFH 58(1), Neck Lake Road Reconstruction: NPOWI Hwy. to Marine Access Facility Jct. Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
AK FLAP ANCHORAGE 2021(1), Far North Bicentennial Park Enhancements Anchorage, Alaska, United States · NAICS 237310 Federal Highway Administration No set-aside
Acadia National Park Maine, United States · NAICS 237310 Federal Highway Administration Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors