43 05 53 - Identification for Process Gas and Liquid Handling Equipment.pdf
PDF 219 KB Posted
- Attached to
- Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153. 0436
- Solicitation number
- Not on record
- Issued by
- Monroe County, Pennsylvania
About this file
This is a technical specification document for identification systems for process gas and liquid handling equipment related to the Skytop Lodge Sewage Treatment Plant Improvements Project in Pennsylvania (Project Number 005153.0436). The specification establishes requirements for nameplates, tags, stencils, labels, and lockout devices to be installed on sewage treatment equipment including an Influent Screening System, Equalization Tank, Chemical Feed System, Clarifier Tanks, Post Aeration Tank, and UV Disinfection System. Bids for the overall sewage treatment plant upgrades project are due on Friday, September 18, 2026 at 10:00 AM via PennBid, with a pre-bid conference scheduled for August 25, 2026 at 10:30 AM at the Skytop Lodge STP facility in Canadensis, Pennsylvania. The identification work must be completed by a manufacturer with a minimum of three years of documented experience, and all identification devices must be installed after completion of coverings and painting using corrosion-resistant materials and fasteners.
The specification requires submission of product data, shop drawings detailing wording, symbols, letter sizes, and color coding, samples of nameplates and labels, manufacturer installation instructions, and manufacturer certificates confirming compliance with specifications. Products specified include laminated three-layer plastic nameplates with engraved black letters, plastic and stainless-steel tags measuring a minimum of 1-1/2 inches square, clear plastic warning tags measuring 3-1/4 by 5-5/8 inches, Mylar labels with adhesive backing, stencils with 1-3/4 inch letter height, and reinforced nylon lockout hasps. Bid security in the form of a certified check or bid bond must accompany all bids in an amount not less than 10 percent. Bidding documents are available through the PennBid website at https://pennbid.bonfirehub.com/, and all official notifications and addenda will be posted exclusively through this designated website.
View the file
Other files
Show 40 more
Latest 50 of 157 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
43 05 53 - IDENTIFICATION FOR PROCESS GAS AND LIQUID HANDLING EQUIPMENT
Herbert, Rowland & Grubic, Inc. 43 05 53 - 1 005153.0436
SECTION 43 05 53 - IDENTIFICATION FOR PROCESS GAS AND LIQUID HANDLING EQUIPMENT
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Nameplates.
2. Tags.
3. Stencils.
4. Labels.
5. Lockout devices.
B. Related Requirements:
1. Section 43 05 20 - Common Work Results for Liquid Handling Equipment: Basic materials and methods for pumps.
1.2 PREINSTALLATION MEETINGS
A. Convene minimum one week prior to commencing Work of this Section.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data: Submit manufacturer's catalog literature for each product required.
C. Shop Drawings: Submit list of wording, symbols, letter size, and color coding for equipment identification and schedule, including equipment number, location, function, and manufacturer's name and model number.
D. Samples: Submit two nameplates, labels and tags, for each size used on Project.
E. Manufacturer's Installation Instructions: Indicate installation instructions, special procedures, and installation.
F. Manufacturer's Certificate: Certify that products meet or exceed specified requirements.
G. Qualifications Statement:
1. Submit qualifications for manufacturer.
1.4 MAINTENANCE MATERIAL SUBMITTALS
A. Section 01 73 00 - Execution Requirements: Requirements for maintenance materials.
B. Tools: Furnish special crimpers and other devices required for Owner to reinstall tags.
Herbert, Rowland & Grubic, Inc. 43 05 53 - 2 005153.0436
1.5 QUALITY ASSURANCE
A. Perform Work according to industry standards.
1.6 QUALIFICATIONS
A. Manufacturer: Company specializing in manufacturing products specified in this Section with minimum three years' documented experience.
PART 2 - PRODUCTS
2.1 NAMEPLATES
A. Description: Laminated three-layer plastic with engraved, black letters on light, contrasting background color.
2.2 TAGS
A. Plastic Tags:
1. Description:
a. Laminated three-layer plastic with engraved, black letters on light, contrasting background color.
b. Minimum Tag Size and Configuration: 1-1/2 inch; square.
B. Metal Tags:
1. Description:
a. Stainless-steel construction; stamped letters.
b. Minimum Tag Size and Configuration: 1-1/2 inch; square with finished edges.
C. Information Tags:
1. Description:
a. Clear plastic with printed WARNING and message.
b. Minimum Tag Size: 3-1/4 by 5-5/8 inches.
c. Furnish grommet and self-locking nylon ties.
2.3 STENCILS
A. Description:
1. Clean-cut symbols.
2. Letter Height: 1-3/4 inch.
B. Stencil Paint: As specified in Section 09 90 00 - Painting and Coating; semi-gloss enamel.
2.4 LABELS
A. Description:
1. Laminated Mylar construction.
2. Minimum Size: 1.9 by 0.75 inches.
Herbert, Rowland & Grubic, Inc. 43 05 53 - 3 005153.0436
3. Adhesive backed, with printed identification.
2.5 LOCKOUT DEVICES
A. Lockout Hasps:
1. Description:
a. Reinforced nylon construction.
b. Furnish hasp with erasable label surface.
c. Minimum Size: 7-1/4 by 3 inches.
PART 3 - EXECUTION
3.1 PREPARATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation preparation.
B. Degrease and clean surfaces to receive adhesive for identification materials.
3.2 INSTALLATION
A. Identify equipment with [plastic nameplates] [stencil painting].
B. Identify in-line pumps and other small devices with tags.
C. Identify control panels and major control components outside panels with plastic nameplates.
D. Install identifying devices after completion of coverings and painting.
E. Install plastic nameplates with corrosion-resistant mechanical fasteners or adhesive.
F. Labels:
1. Install labels with sufficient adhesive for permanent adhesion and seal with clear lacquer.
2. For unfinished covering, apply paint primer before applying labels.
G. Install tags using corrosion-resistant chain.
END OF SECTION