01 61 00 - Product Requirements.pdf

PDF 221 KB Posted

Attached to
Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153. 0436
Solicitation number
Not on record
Issued by
Monroe County, Pennsylvania

About this file

This is a Product Requirements specification document for the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) located in Canadensis, Pennsylvania. The project involves construction and installation of sewage treatment plant upgrades, including an Influent Screening System, Equalization Tank, Chemical Feed System, two Clarifier Tanks, a Post Aeration Tank, a UV Disinfection System, and associated work. Bids will be received and publicly opened on Friday, September 18, 2026 at 10:00 AM local time through PennBid. A pre-bid conference is scheduled for August 25, 2026 at 10:30 AM at Skytop Lodge STP, Falls Road, Canadensis, PA 18325. Attendance at the pre-bid conference is encouraged but not required. Bidding documents are available for download at https://pennbid.bonfirehub.com/, which will be updated periodically with addenda and other relevant information.

The specification establishes comprehensive requirements for product selection, delivery, storage, and handling. All products must be new at the time of installation, undamaged, and complete with necessary accessories and fasteners. Domestic products are required unless otherwise specified. Products must be delivered in manufacturer's original sealed containers with complete labels and instructions, and delivery must be coordinated to minimize on-site storage. Sensitive products require weathertight, climate-controlled storage, and all products must be stored with seals and labels intact and arranged to permit inspection access. Bid security is required in the form of a Certified Check or Bid Bond in an amount not less than 10%. All questions regarding the bidding documents must be submitted through PennBid in accordance with the Instructions to Bidders.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
33 14 16 - Site Water Utility Distribution Piping.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 61 00 - PRODUCT REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 01 61 00 - 1 005153.0436

SECTION 01 61 00 - PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Products.

B. Product delivery requirements.

C. Product storage and handling requirements.

D. Product options.

E. Equipment electrical characteristics and components.

1.2 DEFINITIONS

A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent:

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature that is current as of date of the Contract Documents.

2. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.

3. “Or Equal” Product: Product that is demonstrated and approved through submittal process to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

B. Basis of Design Product: The Project was designed generally around the first or singularly named manufacturers. Where a specific manufacturer's product is named, including make or model number or other designation, it is to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics. If the Contractor chooses to furnish an alternately named manufacturer or product, a substitution request must be made in accordance with paragraph 7.05 of the General Conditions.

1.3 PRODUCTS

A. At minimum, comply with specified requirements and reference standards.

B. Specified products define standard of quality, type, function, dimension, appearance, and performance required.

Herbert, Rowland & Grubic, Inc. 01 61 00 - 2 005153.0436

C. Furnish products of qualified manufacturers that are suitable for intended use. Furnish products of each type by single manufacturer unless specified otherwise. Confirm that manufacturer's production capacity can provide sufficient product, on time, to meet Project requirements.

D. Domestic Products: Except where specified otherwise, domestic products are required and interpreted to mean products mined, manufactured, fabricated, or produced in United States or its territories.

1.4 PRODUCT DELIVERY REQUIREMENTS

A. Comply with delivery requirements in Section 01 74 19 - Construction Waste Management and Disposal.

B. Transport and handle products according to manufacturer's instructions.

C. Deliver products in manufacturer's original sealed container or packaging, complete with labels/instructions for storing, handling, unpacking, protecting, and installing.

D. Promptly inspect shipments to ensure products comply with requirements, quantities are correct, and products are undamaged.

E. Provide equipment and personnel to handle products; use methods to prevent soiling, disfigurement, or damage.

F. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces:

1. Coordinate delivery with installation to ensure minimum storage for items that are hazardous, easily damaged, or sensitive to deterioration, theft, and other losses.

1.5 PRODUCT STORAGE AND HANDLING REQUIREMENTS

A. Store and protect products according to manufacturer's instructions.

B. Store products with seals and labels intact and legible.

C. Store sensitive products in weathertight, climate-controlled enclosures in an environment suitable to product.

D. For exterior storage of fabricated products, place products on sloped supports aboveground.

E. Provide bonded off-Site storage and protection when Site does not permit on-Site storage or protection.

F. Cover products subject to deterioration with impervious sheet covering. Provide ventilation to prevent condensation and degradation of products.

Herbert, Rowland & Grubic, Inc. 01 61 00 - 3 005153.0436

G. Store loose granular materials on solid flat surfaces in well-drained area. Prevent mixing with foreign matter.

H. Provide equipment and personnel to store products; use methods to prevent soiling, disfigurement, or damage.

I. Arrange storage of products to permit access for inspection. Periodically inspect to verify products are undamaged and are maintained in acceptable condition.

1.6 PRODUCT OPTIONS

A. Products Specified by Reference Standards or by Description Only: Products complying with specified reference standards or description.

B. Products Specified by Naming One or More Manufacturers: Products of one of manufacturers named and complying with Specifications; no options or substitutions allowed.

C. Products Specified by Naming One or More Manufacturers with Provision for Substitutions: Submit Request for Substitution for any manufacturer not named, according to Section 01 25 00 - Substitution Procedures.

PART 2 - PRODUCTS

2.1 PRODUCT SELECTION PROCEDURES

A. General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged and that are new at time of installation:

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been produced and used successfully in similar situations on other projects.

3. Engineer reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents.

B. Product Selection Procedures:

1. Product: Where Specifications name a single product and manufacturer, provide the named product. Where Specifications include a list of names of both products and manufacturers, provide one of the products listed that complies with requirements.

2. Manufacturer/Source: Where Specifications name a single manufacturer or source, provide a product by the named manufacturer or equal source that complies with requirements. Where Specifications include a list of manufacturers' names, provide a product by one of the manufacturers listed that complies with requirements.

3. Basis-of-Design Product: Where Specifications name a product and manufacturer, provide the specified product. Where Contract Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that

Herbert, Rowland & Grubic, Inc. 01 61 00 - 4 005153.0436 are based on the product named provide named product. Comply with provisions in Part 2 "Product Substitutions" Article for consideration of an unnamed product or system.

4. Visual Selection Specification: Where Specifications include the phrase "as selected from manufacturer's colors, patterns, textures" or a similar phrase, select a product that complies with other specified requirements:

a. Standard Range: Where Specifications include the phrase "standard range of colors, patterns, textures" or similar phrase, Owner and Engineer will select color, pattern, density, or texture from manufacturer's product line that does not include premium items.

b. Full Range: Where Specifications include the phrase "full range of colors, patterns, textures" or similar phrase, Owner and Engineer will select color, pattern, density, or texture from manufacturer's product line that includes both standard and premium items.

2.2 EQUIPMENT ELECTRICAL CHARACTERISTICS AND COMPONENTS

A. Wiring Terminations: Furnish terminal lugs to match branch circuit conductor quantities, sizes, and materials indicated. Include lugs for terminal box.

B. Cord and Plug: Furnish minimum 6-foot long cord and plug including grounding connector for connection to electric wiring system. Cord of longer length may be specified in individual Specification Sections.

PART 3 - EXECUTION - NOT USED.