01 73 00 - Execution Requirements.pdf

PDF 237 KB Posted

Attached to
Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153. 0436
Solicitation number
Not on record
Issued by
Monroe County, Pennsylvania

About this file

This is an Execution Requirements specification document for the Skytop Lodge Sewage Treatment Plant Improvements Project (Project Number 005153.0436) in Pennsylvania, prepared by Herbert, Rowland & Grubic, Inc. The document outlines comprehensive execution standards for construction contractors performing work on the sewage treatment plant upgrades, which include installation of an Influent Screening System, Equalization Tank, Chemical Feed System, two Clarifier Tanks, Post Aeration Tank, UV Disinfection System, and associated site work. Key execution requirements include engagement of a registered Pennsylvania land surveyor to establish and maintain field survey control, verification of site conditions and measurements prior to work commencement, coordination of equipment startup with seven days' notice to the Engineer, demonstration and instruction of all equipment operation and maintenance to Owner personnel in a classroom setting at the treatment plant two weeks prior to Substantial Completion, and preparation of a final property survey certifying locations and elevations of all constructed elements. A pre-bid conference is scheduled for August 25, 2026 at 10:30 AM at the Skytop Lodge STP facility in Canadensis, Pennsylvania, with bid opening scheduled for September 18, 2026 at 10:00 AM through PennBid.

The specification mandates that contractors employ skilled personnel for all cutting, patching, and installation work; maintain continuous field engineering services with detailed survey logs; comply with all manufacturer installation instructions and industry-recognized standards; and implement comprehensive progress cleaning and waste disposal protocols throughout the construction period. Contractors must verify substrate suitability, secure all work with positive anchorage devices, maintain minimum eight-foot headroom clearance in finished areas, and address any defective work through repair or replacement prior to Substantial Completion. All testing, adjusting, and balancing services will be performed by an independent firm, with reports submitted to the Engineer documenting compliance with contract requirements. Contractors must also protect installed work with temporary coverings, prohibit traffic on waterproofed or roofed surfaces, and maintain operations in compliance with NFPA 241 combustible waste removal requirements, disposing of waste materials legally without burying, burning, or washing materials into sewers or waterways.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
33 14 16 - Site Water Utility Distribution Piping.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 73 00 - EXECUTION REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 01 73 00 - 1 005153.0436

SECTION 01 73 00 - EXECUTION REQUIREMENTS

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Field engineering.

B. Starting of systems.

C. Demonstration and instructions.

D. Testing, adjusting, and balancing.

E. Examination.

F. Preparation.

G. Execution.

H. Cutting and patching.

I. Protecting installed construction.

J. Progress Cleaning

K. Correction of Defective Work

1.2 FIELD ENGINEERING

A. Employ land surveyor registered in State of Pennsylvania.

B. Locate and protect survey control and reference points. Promptly notify Engineer of discrepancies discovered.

C. Control datum for survey is indicated on Drawings.

D. Field Measurements:

1. Verify setbacks and easements; confirm Drawing dimensions and elevations.

2. Take field measurements to fit the Work properly. Recheck measurements before installing each product.

3. Verify space requirements and dimensions of items shown diagrammatically on

Drawings.

E. Provide field engineering services. Establish locations, elevations, lines, and levels using recognized engineering survey practices.

F. Submit copy of Site drawing signed by land surveyor certifying elevations and locations of the Work are in conformance with Contract Documents.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 2 005153.0436

G. Maintain complete and accurate log of control and survey Work as Work progresses.

H. Protect survey control points prior to starting Site Work; preserve permanent reference points during construction.

I. Promptly report to Engineer loss or destruction of reference point or relocation required because of changes in grades or other reasons.

J. Replace dislocated survey control points based on original survey control. Make no changes without prior written notice to Engineer.

K. Final Property Survey: Prior to Substantial Completion, prepare final property survey illustrating locations, dimensions, angles, and elevations of buildings and Site Work that have resulted from construction indicating their relationship to permanent bench marks and property lines:

1. Show significant features (real property) for Project.

2. Include certification on survey, signed by surveyor, that principal metes, bounds, lines, levels, and elevations of Project are accurately shown.

1.3 STARTING OF SYSTEMS

A. Coordinate schedule for startup of various equipment and systems.

B. Notify Engineer seven days prior to startup of each item.

C. Verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, and for conditions which may cause damage.

D. Verify that tests, meter readings, and electrical characteristics agree with those required by equipment or system manufacturer.

E. Verify that wiring and support components for equipment are complete and tested.

F. Execute startup under supervision of manufacturer's representative or Contractors' personnel according to manufacturer's instructions.

G. When specified in individual Specification Sections, require manufacturer to provide authorized representative who will be present at Site to inspect, check, and approve equipment or system installation prior to startup and will supervise placing equipment or system in operation.

H. Submit a written report according to Section 01 33 00 - Submittal Procedures that equipment or system has been properly installed and is functioning correctly.

1.4 DEMONSTRATION AND INSTRUCTIONS

A. Demonstrate operation and maintenance of products to Owner's personnel two weeks prior to date of Substantial Completion.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 3 005153.0436

B. Demonstrate Project equipment and instruct in classroom environment located at Sewage Treatment Plant and instructed by authorized manufacturer's representative who is knowledgeable about the Project.

C. Use operation and maintenance manuals as basis for instruction. Review contents of manual with Owner's personnel in detail to explain all aspects of operation and maintenance.

D. Demonstrate startup, operation, control, adjustment, troubleshooting, servicing, maintenance, and shutdown of each item of equipment at agreed designated location.

E. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instruction.

F. Required instruction time for each item of equipment and system is specified in individual Specification Sections.

1.5 TESTING, ADJUSTING, AND BALANCING

A. Independent firm will perform services specified in the Contract Documents.

B. Reports will be submitted by independent firm to Engineer indicating observations and results of tests and indicating compliance or noncompliance with requirements of Contract Documents.

PART 2 - PRODUCTS - NOT USED.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that existing Site conditions (including improvements and utilities) and substrate surfaces are acceptable for subsequent Work. Beginning new Work means acceptance of existing conditions.

B. Verify that existing substrate is capable of structural support or attachment of new Work being applied or attached.

C. Examine and verify specific space and conditions described in individual Specification Sections.

D. Verify that utility services are available with correct characteristics and in correct locations.

E. Failure to so inspect, verify and report shall constitute an acceptance of the field condition, or other work, as fit and proper for the reception of his work.

F. Promptly report to the Engineer any defects in such work that render it unsuitable for such proper execution and results; written report shall include:

1. Description of the Work.

2. List of detrimental conditions, including substrates.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 4 005153.0436

3. List of unacceptable installation tolerances.

4. Recommended corrections.

5. Verify compatibility with and suitability of substrates.

6. Examine roughing-in systems to verify actual locations of connections before equipment and fixture installation.

7. Examine walls, floors, and roofs for suitable conditions where products and systems are to be installed.

8. Proceed with installation only after unsatisfactory conditions have been corrected. Proceeding with the Work indicates acceptance of surfaces and conditions.

3.2 PREPARATION

A. Clean substrate surfaces prior to applying next material or substance according to manufacturer's instructions.

B. Seal cracks or openings of substrate prior to applying next material or substance.

C. Apply manufacturer-required or -recommended substrate primer, sealer, or conditioner prior to applying new material or substance in contact or bond.

3.3 EXECUTION

A. Locate the Work and components of the Work accurately, in correct alignment and elevation, as indicated:

1. Make vertical work plumb and make horizontal work level.

2. Where space is limited, install components to maximize space available for maintenance and ease of removal for replacement.

3. Conceal pipes, ducts, and wiring in finished areas, unless otherwise indicated.

4. Maintain minimum headroom clearance of 8 feet in spaces without a suspended ceiling.

B. Comply with manufacturer's installation instructions, performing each step in sequence.

Maintain one set of manufacturer's installation instructions at Project Site during installation and until completion of construction.

C. When manufacturer's installation instructions conflict with Contract Documents, request clarification from Engineer before proceeding.

D. Verify that field measurements are as indicated on approved Shop Drawings or as instructed by manufacturer.

E. Secure products in place with positive anchorage devices designed and sized to withstand stresses, vibration, physical distortion, or disfigurement:

1. Secure Work true to line and level and within specified tolerances, or if not specified, industry-recognized tolerances.

2. Physically separate products in place, provide electrical insulation, or provide protective coatings to prevent galvanic action or corrosion between dissimilar metals.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 5 005153.0436

3. Exposed Joints: Provide uniform joint width and arrange to obtain best visual effect. Refer questionable visual-effect choices to Architect/Engineer for final decision.

F. Allow for expansion of materials and building movement.

G. Joints: Make joints of uniform width. Where joint locations in exposed work are not indicated, arrange joints for the best visual effect. Fit exposed connections together to form hairline joints.

H. Climatic Conditions and Project Status: Install each unit of Work under conditions to ensure best possible results in coordination with entire Project:

1. Isolate each unit of Work from incompatible Work as necessary to prevent deterioration.

2. Coordinate enclosure of Work with required inspections and tests to minimize necessity of uncovering Work for those purposes.

I. Mounting Heights: Where not indicated, mount individual units of Work at industry recognized standard mounting heights for particular application indicated:

1. Refer questionable mounting heights choices to Engineer for final decision.

2. Elements Identified as Accessible to Handicapped: Comply with applicable codes and regulations.

J. Adjust operating products and equipment to ensure smooth and unhindered operation.

K. Clean and perform maintenance on installed Work as frequently as necessary through remainder of construction period. Lubricate operable components as recommended by manufacturer.

3.4 CUTTING AND PATCHING

A. Employ skilled and experienced installers to perform cutting and patching.

B. Submit written request in advance of cutting or altering elements affecting:

1. Structural integrity of element.

2. Integrity of weather-exposed or moisture-resistant elements.

3. Efficiency, maintenance, or safety of element.

4. Visual qualities of sight-exposed elements.

5. Work of Owner or separate contractor.

C. Execute cutting, fitting, and patching including excavation and fill to complete Work and to:

1. Fit the several parts together, to integrate with other Work.

2. Uncover Work to install or correct ill-timed Work.

3. Remove and replace defective and nonconforming Work.

4. Remove samples of installed Work for testing.

5. Provide openings in elements of Work for penetrations of mechanical and electrical Work.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 6 005153.0436

D. Execute Work by methods to avoid damage to other Work and to provide proper surfaces to receive patching and finishing.

E. Cut masonry and concrete materials using masonry saw or core drill.

F. Restore Work with new products according to requirements of Contract Documents.

G. Fit Work tight to pipes, sleeves, ducts, conduits, and other penetrations through surfaces.

H. Maintain integrity of wall, ceiling, or floor construction; completely seal voids.

I. Refinish surfaces to match adjacent finishes. For continuous surfaces, refinish to nearest intersection; for assembly, refinish entire unit.

J. Identify hazardous substances or conditions exposed during the Work to Architect/Engineer for decision or remedy.

3.5 PROTECTING INSTALLED CONSTRUCTION

A. Protect installed Work and provide special protection where specified in individual Specification Sections.

B. Provide temporary and removable protection for installed products. Control activity in immediate Work area to prevent damage.

C. Provide protective coverings at walls, projections, jambs, sills, and soffits of openings.

D. Use durable sheet materials to protect finished floors, stairs, and other surfaces from traffic, dirt, wear, damage, or movement of heavy objects.

E. Prohibit traffic or storage upon waterproofed or roofed surfaces. When traffic or activity is necessary, obtain recommendations for protection from waterproofing or roofing material manufacturer.

F. Prohibit traffic from landscaped areas.

3.6 PROGRESS CLEANING

A. General: Clean Project site and work areas daily, including common areas. Coordinate progress cleaning for joint-use areas where more than one installer has worked. Enforce requirements strictly. Dispose of materials lawfully:

1. Comply with requirements in NFPA 241 for removal of combustible waste materials and debris.

2. Do not hold materials more than 7 days during normal weather or 3 days if the temperature is expected to rise above 80 deg F (27 deg C).

3. Containerize hazardous and unsanitary waste materials separately from other waste. Mark containers appropriately and dispose of legally, according to regulations.

B. Site: Maintain Project site free of waste materials and debris.

Herbert, Rowland & Grubic, Inc. 01 73 00 - 7 005153.0436

C. Work Areas: Clean areas where work is in progress to the level of cleanliness necessary for proper execution of the Work:

1. Remove liquid spills promptly.

2. Where dust would impair proper execution of the Work, broom-clean or vacuum the entire work area, as appropriate.

D. Installed Work: Keep installed work clean. Clean installed surfaces according to written instructions of manufacturer or fabricator of product installed, using only cleaning materials specifically recommended. If specific cleaning materials are not recommended, use cleaning materials that are not hazardous to health or property and that will not damage exposed surfaces.

E. Concealed Spaces: Remove debris from concealed spaces before enclosing the space.

F. Exposed Surfaces in Finished Areas: Clean exposed surfaces and protect as necessary to ensure freedom from damage and deterioration at time of Substantial Completion.

G. Waste Disposal: Burying or burning waste materials on-site will not be permitted.

Washing waste materials down sewers or into waterways will not be permitted.

H. During handling and installation, clean and protect construction in progress and adjoining materials already in place. Apply protective covering where required to ensure protection from damage or deterioration at Substantial Completion.

I. Clean and provide maintenance on completed construction as frequently as necessary through the remainder of the construction period. Adjust and lubricate operable components to ensure operability without damaging effects.

J. Limiting Exposures: Supervise construction operations to assure that no part of the construction, completed or in progress, is subject to harmful, dangerous, damaging, or otherwise deleterious exposure during the construction period.

3.7 CORRECTION OF DEFECTIVE WORK

A. Repair or remove and replace defective construction. Restore damaged substrates and finishes:

1. Repairing includes replacing defective parts, refinishing damaged surfaces, touching up with matching materials, and properly adjusting operating equipment.

B. Restore permanent facilities used during construction to their specified condition.

C. Remove and replace damaged surfaces that are exposed to view if surfaces cannot be repaired without visible evidence of repair.

D. Repair components that do not operate properly. Remove and replace operating components that cannot be repaired.

E. Remove and replace chipped, scratched, and broken glass or reflective surfaces.

END OF SECTION