01 78 39 - Project Record Documents.pdf

PDF 221 KB Posted

Attached to
Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153. 0436
Solicitation number
Not on record
Issued by
Monroe County, Pennsylvania

About this file

This is a Project Record Documents specification section prepared by Herbert, Rowland & Grubic, Inc. for the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) in Pennsylvania. The specification establishes requirements for the contractor to maintain comprehensive project record documents on-site throughout construction, including marked-up copies of all contract drawings, specifications, addenda, change orders, shop drawings, product data, and samples. The contractor must record actual revisions and installations concurrent with construction progress at a minimum weekly frequency, with particular attention to concealed elements, dimensional changes, underground utility locations, equipment locations, and internal utility routing. A pre-bid conference was scheduled for August 25, 2026 at 10:30 AM at the Skytop Lodge STP facility in Canadensis, Pennsylvania, with bid opening on Friday, September 18, 2026 at 10:00 AM. The project encompasses sewage treatment plant upgrades including an influent screening system, equalization tank, chemical feed system, two clarifier tanks, post aeration tank, UV disinfection system, and associated work.

The specification requires the contractor to submit one marked-up paper copy and PDF electronic files of all project record documents to the Engineer before substantial completion. Record drawings must be marked with erasable red-colored pencil, organized into manageable sets with durable paper covers, and clearly labeled as "PROJECT RECORD DRAWING" with contractor identification. The contractor must cross out the engineer's title block and seal from all sheets and prepare new drawings where existing contract or shop drawings are unsuitable for showing actual installation conditions. Miscellaneous record submittals must include material and equipment test and inspection reports, delivery slips, and other records required by individual specification sections, all properly bound and identified for future owner reference.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
33 14 16 - Site Water Utility Distribution Piping.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 78 39 – PROJECT RECORD DOCUMENTS

Herbert, Rowland & Grubic, Inc. 01 78 39 - 1 005153.0436

SECTION 01 78 39 - PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Project record documents.

2. Manual for Materials and Finishes.

3. Miscellaneous Record Submittals

B. Related Sections:

1. Section 01 77 00 - Closeout Procedures: general closeout procedures.

2. Individual Sections for specific requirements for Project Record Documents of the

Work in those Sections.

1.2 PROJECT RECORD DOCUMENTS

A. Maintain on Site one set of the following record documents; record actual revisions to the Work:

1. Drawings.

2. Specifications.

3. Addenda.

4. Change Orders and other modifications to the Contract.

5. Reviewed Shop Drawings, product data, and Samples.

6. Manufacturer's instruction for assembly, installation, and adjusting.

B. Ensure entries are complete and accurate, enabling future reference by Owner.

C. Store record documents separate from documents used for construction.

D. Record information concurrent with construction progress, not less than weekly.

E. Specifications: Legibly mark and record, at each product Section, description of actual products installed, including the following:

1. Manufacturer's name and product model and number.

2. Suppliers name and contact.

3. Product substitutions or alternates used.

4. Changes made by Addenda and modifications.

F. Record Drawings: Maintain one set of the Contract Drawings and Shop Drawings:

1. Preparation: Mark Drawings to show the actual installation. Require individual or entity who obtained record data to prepare the marked-up Record Prints:

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Accurately record information in an understandable drawing technique.

c. Record data as soon as possible after obtaining it. Record and check the markup before enclosing concealed installations.

Herbert, Rowland & Grubic, Inc. 01 78 39 - 2 005153.0436

2. Content: Types of items requiring marking include, but are not limited to, the following:

a. Dimensional changes to Drawings.

b. Revisions to details shown on Drawings.

c. Depths of foundations in relation to plant datum.

d. Measured horizontal and vertical locations of underground utilities and appurtenances, referenced to permanent surface improvements:

1) Depth of buried utility lines.

2) Dimension distances from permanent facility components that are parallel to utilities.

3) Dimension ends, corners, and junctions of buried utilities to permanent facility components using triangulation.

4) Identify and locate existing buried or concealed items encountered during Project.

e. Revisions to electrical circuitry.

f. Actual equipment locations.

g. Locations of concealed internal utilities.

h. Changes made by Addendum, Field Order, Change Order or Work Change

Directive.

i. Details not on the original Contract Drawings.

j. Field records for variable and concealed conditions.

k. Record information on the Work that is shown only schematically.

3. Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, show cross-reference on the Contract Drawings.

4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

5. Mark important additional information that was either shown schematically or omitted from original Drawings.

6. Note Addendum numbers, Field Order numbers, Work Change Directive numbers, Change Order numbers, and similar identification, where applicable.

7. Prepare new Drawings where neither the Contract Drawings nor Shop Drawings are not suitable to show actual installation:

a. New Drawings may be required when a Change Order is issued as a result of accepting an alternate, substitution, or other modification.

8. Format: Identify and date each Record Drawing; include the designation

"PROJECT RECORD DRAWING" in a prominent location:

a. Cross out Engineer's title block and seal from all sheets and stamp all sheets with name of Contractor.

b. Record Drawings: Organize Record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

G. Submit one (1) marked-up paper copy documents to Engineer before Substantial Completion.

H. Submit PDF electronic files of marked-up documents to Engineer before Substantial Completion.

Herbert, Rowland & Grubic, Inc. 01 78 39 - 3 005153.0436

1.3 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Sections. Bind or file miscellaneous records and identify each. Miscellaneous records include the following:

1. Material and equipment test and inspection reports.

2. Equipment and material delivery slips.

PART 2 - PRODUCTS - NOT USED.

PART 3 - EXECUTION - NOT USED.

END OF SECTION