This is a Permit Requirements specification document prepared by Herbert, Rowland & Grubic, Inc. for the Skytop Lodge Sewage Treatment Plant Improvements Project in Pennsylvania. The project involves construction of sewage treatment plant upgrades including installation of an Influent Screening System, Equalization Tank, Chemical Feed System, two Clarifier Tanks, a Post Aeration Tank, a UV Disinfection System, and associated work. Bids for Contract 2026-01 (Project Number 005153.0436) are due on September 18, 2026 at 10:00 AM and will be publicly opened at PennBid. A pre-bid conference is scheduled for August 25, 2026 at 10:30 AM at the project site located at Skytop Lodge STP, Falls Road, Canadensis, PA 18325. Attendance at the pre-bid conference is encouraged but not required. Bidding documents are available for download at https://pennbid.bonfirehub.com/, which will be updated periodically with addenda and other relevant information.

The specification section establishes that the Contractor must implement the PADEP Water Quality Management Permit in full conformance with all applicable Pennsylvania Department of Environmental Protection requirements and the Contract Documents. Contractors are required to submit copies of inspection reports, certifications, correspondence, and other compliance documentation for the Owner's records. Bid security in the form of a Certified Check or Bid Bond must be provided in an amount not less than ten percent. All official notifications and addenda will be distributed exclusively through the designated PennBid website, with neither the Owner nor Engineer responsible for documents obtained from alternative sources.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
33 14 16 - Site Water Utility Distribution Piping.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 41 26 - PERMIT REQUIREMENTS

Herbert, Rowland & Grubic, Inc. 01 41 26 - 1 005153.0436

SECTION 01 41 26 - PERMIT REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. PADEP Water Quality Management Permit.

B. Related Sections:

1. Section 00 31 46 - Permits: Copies of the permits obtained for the Project.

1.2 SUBMITTALS

A. Permits and Certificates: For Owner's records, submit copies of inspection reports, certifications, correspondence, records, and similar documents, established for compliance with standards and regulations required by permits for the project.

PART 2 - PRODUCTS - NOT USED.

PART 3 - EXECUTION

3.1 PADEP WATER QUALITY MANAGEMENT PERMIT

A. The Contractor shall implement the WQM Permit in conformance with all applicable PADEP requirements, as well as in accordance with the Contract Documents.

END OF SECTION