02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf
PDF 226 KB Posted
- Attached to
- Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153. 0436
- Solicitation number
- Not on record
- Issued by
- Monroe County, Pennsylvania
About this file
This is a Selective Building Demolition specification document for the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) in Canadensis, Pennsylvania, prepared by Herbert, Rowland & Grubic, Inc. The scope of work includes demolishing designated building equipment and fixtures, cutting and alterations necessary for project completion, removing items designated for owner retention, and protecting items designated to remain. Specific equipment and materials required to be removed, stored, and protected include a SCADA Panel, Auto Dialer, Chemical Feed Shed, Vacuum Pumps, Sonic Starts, Pump Check Valves, and Generator. The contractor must submit a demolition schedule indicating overall timeline and required utility and building service interruptions, along with shop drawings detailing demolition sequence and temporary work locations. A pre-installation meeting must be convened minimum one week prior to commencing work. The pre-bid conference for the project is scheduled for August 25, 2026 at 10:30 AM at Skytop Lodge STP, Falls Road, Canadensis, PA, with bid opening on Friday, September 18, 2026 at 10:00 AM on PennBid. Bid security of not less than 10% in the form of a Certified Check or Bid Bond is required.
The contractor must conduct all demolition work in compliance with applicable codes and Cranberry Township standards, coordinate all sequencing and scheduling activities with Cranberry Township and the owner, and minimize interference with daily operations. Work must be performed carefully to protect existing improvements and supporting structural members, with all demolished materials removed from site except where specifically noted otherwise. The contractor is responsible for disconnecting and removing designated utilities, capping and identifying abandoned utilities at termination points, and providing accurate record drawings indicating locations of capped utilities and any concealed utilities or subsurface obstructions discovered during demolition. All salvage items must be carefully removed, disassembled as required, packaged with assembly instructions, and delivered to the owner with signed receipt documentation. Temporary barriers, security devices, warning signs, weatherproof closures, and appropriate exit signage must be maintained throughout the project without closing or obstructing building egress paths or fire and life safety systems.
View the file
Other files
Show 40 more
Latest 50 of 157 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Herbert, Rowland & Grubic, Inc. 02 41 19.13 - 1 005153.0436
02 41 19.13 - SELECTIVE BUILDING DEMOLITION
SECTION 02 41 19.13 - SELECTIVE BUILDING DEMOLITION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Demolishing designated building equipment and fixtures.
2. Cutting and alterations for completion of the Work.
3. Removing designated items for Owner’s retention.
4. Protecting items designated to remain.
1.2 SUBMITTALS
A. Refer to Owner Front End Documents: Requirements for submittals.
B. Demolition Schedule: Indicate overall schedule and interruptions required for utility and building services.
C. Shop Drawings:
1. Indicate demolition sequence.
2. Indicate location and construction of temporary work.
1.3 CLOSEOUT SUBMITTALS
A. Refer to Owner Front End Documents: Requirements for submittals.
B. Project Record Documents: Accurately record actual locations of newly installed equipment, capped utilities, concealed utilities discovered during demolition, and subsurface obstructions.
C. Operation and Maintenance Data: Submit description of system, inspection data, and parts lists.
1.4 QUALITY ASSURANCE
A. Conform to applicable code for demolition work, dust control, products requiring electrical disconnection and re-connection.
B. Conform to applicable code for procedures when hazardous or contaminated materials are discovered.
C. Obtain required permits from authorities having jurisdiction.
D. Perform Work in accordance with Cranberry Township standard.
1.5 PRE-INSTALLATION MEETINGS
A. Refer to Owner Front End Documents: Pre-installation meeting.
Herbert, Rowland & Grubic, Inc. 02 41 19.13 - 2 005153.0436
B. Convene minimum one week prior to commencing work of this section.
1.6 SEQUENCING
A. Refer to Owner Front End Documents: Requirements for sequencing.
B. All Sequencing activities to be coordinated with Cranberry Township.
C. Owner will conduct salvage operations before demolition begins to remove materials Owner chooses to retain.
1.7 SCHEDULING
A. Refer to Owner Front End Documents: Requirements for scheduling.
B. Schedule Work to coincide with new construction.
C. Cooperate with Owner in scheduling noisy operations and waste removal that may impact Owner’s operations.
D. Coordinate utility and building service interruptions with Owner.
1.8 PROJECT CONDITIONS
A. Conduct demolition to minimize interference with daily operations.
B. Cease operations immediately if structure appears to be in danger and notify Engineer.
Do not resume operations until directed.
PART 2 – PRODUCTS - NOT USED.
PART 3 - EXECUTION
3.1 PREPARATION
A. Notify affected utility companies before starting work and comply with their requirements.
B. Mark location and termination of utilities.
C. Erect, and maintain temporary barriers and security devices including warning signs and lights, and similar measures, for protection of the Owner.
D. Erect and maintain weatherproof closures for exterior openings.
E. Provide appropriate temporary signage including signage for exit or building egress.
F. Do not close or obstruct building egress path.
Herbert, Rowland & Grubic, Inc. 02 41 19.13 - 3 005153.0436
G. Do not disable or disrupt building fire or life safety systems.
3.2 SALVAGE REQUIREMENTS
A. Coordinate with Owner to identify building components and equipment required to be removed and delivered to Owner.
B. Tag components and equipment Owner designates for salvage.
C. Protect designated salvage items from demolition operations until items can be removed.
D. Carefully remove building components and equipment indicated to be salvaged.
E. Disassemble as required to permit removal from building.
F. Package small and loose parts to avoid loss.
G. Mark equipment and packaged parts to permit identification and consolidation of components of each salvaged item.
H. Prepare assembly instructions consistent with disassembled parts. Package assembly instructions in protective envelope and securely attach to each disassembled salvaged item.
I. Deliver salvaged items to Owner. Obtain signed receipt from Owner.
3.3 DEMOLITION
A. Conduct demolition to minimize interference with operations.
B. Do not close or obstruct roadways without permits.
C. Cease operations immediately when structure appears to be in danger and notify Engineer.
D. Disconnect and remove designated utilities within demolition areas.
E. Cap and identify abandoned utilities at termination points when utility is not completely removed. Annotate Record Drawings indicating location and type of service for capped utilities remaining after demolition.
F. Demolish in orderly and careful manner. Protect existing improvements, supporting structural members.
G. Remove demolished materials from site except where specifically noted otherwise. Do not burn or bury materials on site.
H. Remove materials as Work progresses. Upon completion of Work, leave areas in clean condition.
Herbert, Rowland & Grubic, Inc. 02 41 19.13 - 4 005153.0436
I. Remove temporary Work.
3.4 SCHEDULES
A. Remove, store, and protect the following materials and equipment:
1. SCADA Panel.
2. Auto Dialer.
3. Chemical Feed Shed.
4. Vacuum Pumps.
5. Sonic Starts.
6. Pump Check Valves.
7. Generator.
END OF SECTION
File details come from the government source that posted it. Updated .