01 26 13 - Requests for Interpretation.pdf

PDF 216 KB Posted

Attached to
Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153. 0436
Solicitation number
Not on record
Issued by
Monroe County, Pennsylvania

About this file

This is a Requests for Interpretation specification section prepared by Herbert, Rowland & Grubic, Inc. for the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) in Pennsylvania. The specification establishes the procedural requirements and standards for contractors to submit Requests for Information/Interpretation (RFIs) regarding clarifications needed on contract drawings and specifications. RFIs must be submitted using the designated RFI Form (Document 00 63 13) with complete information identifying the specific drawing numbers, locations, specification sections, pages, and paragraphs requiring clarification. All RFIs must be submitted in consecutive numerical order through the Project Documentation Website or official correspondence, with subcontractor and supplier RFIs routed through the prime contractor for approval before submission to the Engineer. The Engineer will endeavor to respond to properly prepared RFIs in a timely manner, though requested response dates are not guaranteed if deemed too expeditious.

RFIs that are improperly prepared or request information already available in the contract documents will be classified as improper or frivolous and will be processed at the Engineer's standard hourly rate, with costs deducted from monies due the contractor. RFIs cannot be used to request approval of submittals or substitutions, request changes involving additional costs, or request different work methods. RFIs addressing coordination issues must include a contractor-prepared scaled drawing or sketch with a suggested solution. Contractors must not proceed with work based on RFI responses if they believe the clarification results in additional cost or time; instead, a Change Proposal must be submitted. Unanswered RFIs will be returned with a "Not Reviewed" notation, and RFI responses do not constitute approval to perform extra work or justify cost increases or schedule changes.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
33 14 16 - Site Water Utility Distribution Piping.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 26 13 – REQUESTS FOR INTERPRETATION

Herbert, Rowland & Grubic, Inc. 01 26 13 - 1 005153.0436

SECTION 01 26 13 – REQUESTS FOR INTERPRETATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Requests For Interpretation.

B. Related Sections:

1. Document 00 60 00 – Project Forms.

2. Document 00 63 13 – RFI Form.

3. Section 01 26 00 – Contract Modification.

1.2 DEFINITIONS

A. Request For Information / Interpretation (RFI):

1. A properly prepared request for information / interpretation shall include a detailed written statement that indicates the specific Drawings or Specification in need of clarification and the nature of the clarification requested:

a. Drawings shall be identified by drawing number and location on the drawing sheet.

b. Specifications shall be identified by Section number, page and paragraph.

2. Requests for Information: Request made by Contractor concerning items not indicated on drawings or contained in Contract Documents that is required to properly perform the work.

B. Improper and Frivolous RFIs:

1. RFIs that are not properly prepared, or

2. RFIs that request information that is clearly shown on the Contract Documents.

1.3 CONTRACTOR'S REQUESTS FOR INFORMATION

A. Format: use form Document 00 63 13 – RFI Form:

1. Forms shall be completely filled in, and if prepared by hand, shall be fully legible after photocopying or scanning.

2. RFIs shall be submitted in numerical order with no breaks in the consecutive numbering.

3. Each page of attachments to RFIs shall bear the RFI number and shall be consecutively numbered in chronological order.

4. Submit RFI through Project Documentation Website or correspondence.

B. Contractor shall carefully study the Contract Documents to assure that the requested information is not available therein. RFIs which request information available in the Contract Documents will be deemed either "improper" or "frivolous":

1. Improper or Frivolous RFIs will be processed by the Engineer at the Engineer's standard hourly rate and Engineer will charge the Owner, and such costs will be

Herbert, Rowland & Grubic, Inc. 01 26 13 - 2 005153.0436 deducted from monies still due the Contractor. The Contractor will be notified by the Engineer prior to the processing of improper RFIs.

C. When the Contractor is unable to determine from the Contract Documents, the material, process or system to be installed, the Engineer shall be requested to make a clarification of the indeterminate item.

D. RFIs shall be originated by the Contractor:

1. RFIs from subcontractors or suppliers shall be submitted through, reviewed by, and approved by the Contractor prior to submittal to the Engineer.

2. RFIs from subcontractors or material suppliers sent directly to the Engineer shall not be accepted and will be returned unanswered.

E. In cases where RFIs are issued to request clarification of coordination issues, the Contractor shall fully lay out a suggested solution using drawings or sketches drawn to scale, and submit same with the RFI. RFIs which fail to include a suggested solution will be returned unanswered with a requirement that the Contractor submit a complete request.

F. RFIs shall not be used for the following purposes:

1. To request approval of submittals.

2. To request approval of substitutions.

3. To request changes which are known to entail additional cost or credit.

4. To request different methods of performing work.

G. Contractor shall allow a reasonable time for review and response time for RFIs.

1. The Engineer will endeavor to respond in a timely fashion to RFIs.

2. RFI shall state requested date/time for response, however, this requested date/time for response is not a guarantee that the RFI will be answered by that date/time if that date/time is too expeditious.

1.4 ENGINEER'S RESPONSE TO RFIs

A. Engineer will respond to RFIs on one of the following forms:

1. Properly prepared RFIs:

a. Response directly upon Request for Information / Interpretation form.

b. Request for Proposal.

2. Improper or Frivolous RFIs:

a. Notification of Processing Fee(s).

b. Unanswered RFIs will be returned with a notation: Not Reviewed.

3. Answers to properly prepared RFIs will be directly upon the RFI form as deemed appropriate by the Engineer.

B. Engineer may opt to retain RFIs for discussion during regularly scheduled project meetings for inclusion of responses in meeting minutes.

C. In the event the Contractor believes that a clarification by the Engineer results in additional cost or time, Contractor shall submit a Change Proposal and not proceed with the Work indicated by the RFI until a Change Order (or Work Change Directive) is prepared

Herbert, Rowland & Grubic, Inc. 01 26 13 - 3 005153.0436 and approved. RFIs shall not justify a cost increase in the work or a change in the project schedule.

1. Answered RFIs shall not be construed as approval to perform extra work.

2. Unanswered RFIs will be returned with a stamp or notation: Not Reviewed.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION