01 29 00 - Payment Procedures.pdf

PDF 219 KB Posted

Attached to
Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153. 0436
Solicitation number
Not on record
Issued by
Monroe County, Pennsylvania

About this file

This is a Payment Procedures specification document for the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) in Pennsylvania, involving Skytop Lodge, Inc. as the Owner and Herbert, Rowland & Grubic, Inc. as the Engineer. The project encompasses construction of sewage treatment plant upgrades, including installation of an Influent Screening System, Equalization Tank, Chemical Feed System, two Clarifier Tanks, a Post Aeration Tank, a UV Disinfection System, and associated work. Bids were to be received and publicly opened on September 18, 2026 at 10:00 AM via PennBid. A pre-bid conference was scheduled for August 25, 2026 at 10:30 AM at the Skytop Lodge STP facility in Canadensis, Pennsylvania. Bid security in the form of a Certified Check or Bid Bond was required in an amount not less than 10%.

The Payment Procedures section establishes that the contractor receives compensation as full payment for furnishing all materials, labor, tools, and equipment necessary to complete the work in an acceptable manner, including miscellaneous labor and materials not specifically mentioned in the contract documents. The contractor must submit a Schedule of Values within 15 days of the Owner-Contractor Agreement, with breakdown details sufficient to facilitate evaluation of payment applications and progress reports. Applications for Payment must be submitted at intervals stipulated in the Agreement on forms provided in Section 00 62 76, with supporting documentation including current construction photographs, partial releases of liens from subcontractors and vendors, and revised construction schedules. Payment will not be made for rejected products, including those wasted, deemed unacceptable, improperly unloaded, placed beyond required lines and levels, or remaining on hand after project completion.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
33 14 16 - Site Water Utility Distribution Piping.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 29 00 - PAYMENT PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 29 00 - 1 005153.0436

SECTION 01 29 00 - PAYMENT PROCEDURES

PART 1 - GENERAL

1.1 SECTION INCLUDES

A. Scope of Payment.

B. Schedule of Values.

C. Application for Payment.

D. Defect Assessment.

1.2 SCOPE OF PAYMENT

A. Contractor will receive and accept compensation provided for in the Contract as full payment for furnishing all materials, labor, tools, and equipment and for performing all Work in a complete and acceptable manner and for all risk, loss, damage, or expense of whatever character arising out of the nature of the Work or the prosecution thereof.

B. Contractor shall furnish all labor, materials, equipment, machinery, apparatus and tools and perform all operations necessary to install, equip, adjust and put into satisfactory operation the Work, and shall connect the various items or sections of the Work as to form a complete and properly operating whole. Any miscellaneous labor, materials, equipment or apparatus not specifically mentioned herein, or shown on the drawings, which may be found necessary to complete or perfect any portion of the Work in a substantial manner and in compliance with the requirements stated or implied by the Contract Documents, shall be furnished by the Contractor without additional compensation. This includes the cost of material disposal, water for testing and all testing costs including laboratory fees.

1.3 SCHEDULE OF VALUES

A. Coordination: Coordinate preparation of the Schedule of Values with preparation of Contractor's Construction Schedule.

B. Submit electronic file via email of schedule on Application for Payment Continuation Sheets.

C. Submit Schedule of Values as electronic file via email within 15 days after date of Owner- Contractor Agreement.

D. Format:

1. Provide a breakdown of the Contract Price in enough detail to facilitate continued evaluation of Applications for Payment and progress reports.

Herbert, Rowland & Grubic, Inc. 01 29 00 - 2 005153.0436

2. Use Table of Contents of this Project Manual. Identify each line item with number and title of major Specification Section. Provide several line items for principal subcontract amounts, where appropriate.

3. Identify Site mobilization and bonds and insurances.

4. Round amounts to nearest whole dollar; total shall equal the Contract Sum.

E. Include within each line item, direct proportional amount of Contractor's overhead and profit:

1. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the Schedule of Values or distributed as general overhead expense, at Contractor's option.

F. Revise schedule to list approved Change Orders with each Application for Payment.

1.4 APPLICATION FOR PAYMENT

A. Submit an electronic copy of each Application for Payment on form(s) provided in Section 00 62 76 in accordance with requirements of the General Conditions:

1. Initial Application for Payment, Application for Payment at time of Substantial

Completion, and final Application for Payment involve additional requirements.

B. Content and Format: Use Schedule of Values for listing items in Application for Payment:

1. Execute by a person authorized to sign legal documents on behalf of Contractor.

Engineer will return incomplete applications without action.

2. Include amounts of Change Orders issued before last day of construction period covered by application.

C. Submit updated construction schedule with each Application for Payment.

D. Payment Period: Submit at intervals stipulated in the Agreement.

E. Submit executed originals with transmittal letter to Engineer by method ensuring receipt within 24 hours.

F. Substantiating Data: When Engineer requires substantiating information, submit data justifying dollar amounts in question. Include the following with Application for Payment:

1. Current construction photographs specified in Section 01 32 33 - Photographic

Documentation.

2. Partial release of liens from major Subcontractors and vendors.

3. Record Documents as specified in Section 01 77 00 - Closeout Requirements, for review by Owner, which will be returned to Contractor.

4. Affidavits attesting to off-Site stored products.

5. Construction Progress Schedule, revised and current as specified in Section 01 33

00 - Submittal Procedures.

G. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:

1. List of subcontractors.

2. Contractor's Construction Schedule (preliminary if not final).

Herbert, Rowland & Grubic, Inc. 01 29 00 - 3 005153.0436

3. Products list.

4. Submittals Schedule (preliminary if not final).

5. Certificates of insurance and insurance policies.

H. Application for Payment at Substantial Completion: After issuance of the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete less the amounts certified by the Engineer as remaining:

1. Administrative actions and submittals that must precede or coincide with submittal of the Substantial Completion Application for Payment include the following:

a. Final Operation and Maintenance Manuals, as applicable.

b. Final test and field reports.

c. Draft Project Record Documents.

I. Final Payment Application: Submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following. Final Application will be prepared by the Engineer following completion of the final inspection per Section 01 77 00.

1. Evidence of completion of Project closeout requirements.

2. Final Project Record Documents.

3. Insurance certificates for products and completed operations and proof that taxes, fees, and similar obligations were paid.

4. Contractor's Affidavit: Submit on form provided by Engineer.

5. Consent of Surety to Final Payment: Submit on form provided by Engineer.

1.5 DEFECT ASSESSMENT

A. Nonpayment for Rejected Products: Payment will not be made for rejected products for any of the following reasons:

1. Products wasted or disposed of in a manner that is not acceptable.

2. Products determined as unacceptable before or after placement.

3. Products not completely unloaded from transporting vehicle.

4. Products placed beyond lines and levels of the required Work.

5. Products remaining on hand after completion of the Work.

6. Loading, hauling, and disposing of rejected products.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION