About this file
This is a technical specification document for hydrostatic testing services related to the Skytop Lodge Sewage Treatment Plant Improvements Project in Pennsylvania, a state and local contract opportunity managed by Skytop Lodge, Inc. The specification details the requirements for hydrostatic testing of pressure sanitary sewer and water piping systems that will be installed as part of the sewage treatment plant upgrades. The project (005153.0436) includes an Influent Screening System, Equalization Tank, Chemical Feed System, two Clarifier Tanks, a Post Aeration Tank, UV Disinfection System, and associated piping infrastructure. Bids for Contract 2026-01 are due on September 18, 2026 at 10:00 AM local time through PennBid. A pre-bid conference is scheduled for August 25, 2026 at 10:30 AM at the facility located in Canadensis, Pennsylvania, with attendance encouraged but not required. Bid security of 10% must be submitted in the form of a Certified Check or Bid Bond.
The hydrostatic testing specification requires contractors to comply with American Water Works Association (AWWA) standards C600, C605, C900, and C901, as well as ASTM F 2164 standards for polyethylene piping. Testing must be performed by qualified applicators with a minimum of three years' documented experience. The contractor must submit testing procedures, equipment lists, testing sequence schedules, water disposal provisions, and pressure gage calibration certifications prior to commencing work. Tests must be conducted at 1.5 times the working pressure for ductile iron and PVC piping, held for at least two hours, with pressure maintained within plus or minus 5 psi. For polyethylene piping, an initial 4-hour expansion phase is required followed by a 1-hour monitoring phase with pressure reduction of 10 psi. All visible leaks must be corrected regardless of leakage quantity, and sections must be retested after deficiencies are remedied to ensure compliance with allowable leakage rates calculated using specified formulas.
View the file
Other files
Show 40 more
Latest 50 of 157 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
33 05 05.31 - HYDROSTATIC TESTING
Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 1 005153.0436
SECTION 33 05 05.31 - HYDROSTATIC TESTING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes: Hydrostatic testing of pressure sanitary sewer and water piping.
B. Related Requirements:
1. Section 33 31 23 - Sanitary Sewerage Force Main Piping: Pipe materials and accessories normally encountered with municipal sanitary sewage force mains.
2. Section 33 14 16 - Site Water Utility Distribution Piping: Pipe materials and accessories normally encountered with pressurized water distribution systems.
1.2 REFERENCE STANDARDS
A. American Water Works Association:
1. AWWA C600 - Installation of Ductile-Iron Water Mains and their Appurtenances.
2. AWWA C605 - Underground Installation of Polyvinyl Chloride (PVC) and
Molecularly Oriented Polyvinyl Chloride (PVCO) Pressure Pipe and Fittings.
3. AWWA C900 - Polyvinyl Chloride (PVC) Pressure Pipe and Fabricated Fittings, for
Water Service.
4. AWWA C901 - Polyethylene (PE) Pressure Pipe and Tubing, for Water Service.
B. American Standard Testing Methods:
1. ASTM F 2164 - Standard Practice for Field Leak Testing of Polyethylene (PE) and
Crosslinked Polyethylene (PEX) Pressure Piping Systems Using Hydrostatic Pressure.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Submit following items prior to start of testing:
1. Testing procedures.
2. List of test equipment.
3. Testing sequence schedule.
4. Provisions for disposal of flushing and test water.
5. Certification of test gage calibration.
C. Test and Evaluation Reports: Indicate results of piping tests.
D. Qualifications Statement:
1. Submit qualifications for applicator.
1.4 QUALIFICATIONS
A. Applicator: Company specializing in performing Work of this Section with minimum three years' documented experience.
Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 2 005153.0436
PART 2 - PRODUCTS
2.1 HYDROSTATIC TESTING
A. Equipment:
1. Pressure pump.
2. Pressure hose.
3. Water meter.
4. Test connections.
5. Pressure relief valve.
6. Pressure Gage: Calibrated to 0.1 psi.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.
B. Verify that piping is ready for testing.
C. Verify that trenches are backfilled.
D. Verify that pressure piping thrust restraints have been installed.
3.2 FIELD QUALITY CONTROL
A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.
B. Testing of Pressure Ductile Iron or PVC Piping:
1. Test system according to AWWA C600 and following:
a. Hydrostatically test each portion of pressure piping, including valved section, at 1.5 times working pressure of piping, based on elevation of lowest point in piping corrected to elevation of test gage.
b. Conduct hydrostatic testing for at least two hours.
c. Slowly fill with water portion of piping to be tested, expelling air from piping at high points.
d. Install corporation cocks at high points.
e. Close air vents and corporation cocks after air is expelled.
f. Raise pressure to specified test pressure.
g. Observe joints, fittings, and valves undergoing testing.
h. Remove and renew cracked pipes, joints, fittings, and valves that show visible leakage.
i. Retest.
j. Correct visible deficiencies and continue testing at same test pressure for additional two hours to determine leakage rate.
k. Maintain pressure within plus or minus 5.0 psi of test pressure.
l. Leakage is defined as quantity of water supplied to piping necessary to maintain test pressure during period of testing.
m. Compute maximum allowable leakage using following formula:
1) L = [SD x sqrt(P)]/C.
Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 3 005153.0436
2) L = testing allowance, gph.
3) S = length of pipe tested, feet.
4) D = nominal diameter of pipe, inches.
5) P = average test pressure during hydrostatic testing, psig.
6) C = 148,000.
7) If pipe undergoing testing contains sections of various diameters, calculate allowable leakage from sum of computed leakage for each pipe size.
2. If testing of piping indicates leakage greater than that allowed, locate source of leakage, make corrections, and retest until leakage is within acceptable limits.
3. Correct visible leaks regardless of quantity of leakage.
C. Testing of Pressure PE Piping:
1. Test system according to ASTM F 2164 and following:
a. Hydrostatically test each portion of pressure piping, including valved section, at 1.5 times working pressure of piping, based on elevation of lowest point in piping corrected to elevation of test gage.
b. Initial expansion phase:
1) Slowly fill with water portion of piping to be tested, expelling air from piping at high points.
2) Install corporation cocks at high points.
3) Close air vents and corporation cocks after air is expelled.
4) Raise pressure to specified test pressure.
5) Observe joints, fittings, and valves undergoing testing.
6) Add make-up water as necessary to maintain maximum test pressure for 4 hours.
c. Test Phase.
d. Immediately after expansion phase, reduce test pressure by 10 psi and stop adding makeup water.
e. Monitor pressure for 1 hour.
f. Remove and renew cracked pipes, joints, fittings, and valves that show visible leakage.
g. Retest after section is depressurized for 8 hours, minimum.
h. If no visual leakage is observed and test pressure remains within 5% of the target pressure, no leakage is indicated.
2. If testing of piping indicates leakage, locate source of leakage, make corrections, and retest until leakage is within acceptable limits.
3. Correct visible leaks regardless of quantity of leakage.
END OF SECTION