This is a technical specification document for hydrostatic testing services related to the Skytop Lodge Sewage Treatment Plant Improvements Project in Pennsylvania, a state and local contract opportunity managed by Skytop Lodge, Inc. The specification details the requirements for hydrostatic testing of pressure sanitary sewer and water piping systems that will be installed as part of the sewage treatment plant upgrades. The project (005153.0436) includes an Influent Screening System, Equalization Tank, Chemical Feed System, two Clarifier Tanks, a Post Aeration Tank, UV Disinfection System, and associated piping infrastructure. Bids for Contract 2026-01 are due on September 18, 2026 at 10:00 AM local time through PennBid. A pre-bid conference is scheduled for August 25, 2026 at 10:30 AM at the facility located in Canadensis, Pennsylvania, with attendance encouraged but not required. Bid security of 10% must be submitted in the form of a Certified Check or Bid Bond.

The hydrostatic testing specification requires contractors to comply with American Water Works Association (AWWA) standards C600, C605, C900, and C901, as well as ASTM F 2164 standards for polyethylene piping. Testing must be performed by qualified applicators with a minimum of three years' documented experience. The contractor must submit testing procedures, equipment lists, testing sequence schedules, water disposal provisions, and pressure gage calibration certifications prior to commencing work. Tests must be conducted at 1.5 times the working pressure for ductile iron and PVC piping, held for at least two hours, with pressure maintained within plus or minus 5 psi. For polyethylene piping, an initial 4-hour expansion phase is required followed by a 1-hour monitoring phase with pressure reduction of 10 psi. All visible leaks must be corrected regardless of leakage quantity, and sections must be retested after deficiencies are remedied to ensure compliance with allowable leakage rates calculated using specified formulas.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

33 05 05.31 - HYDROSTATIC TESTING

Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 1 005153.0436

SECTION 33 05 05.31 - HYDROSTATIC TESTING

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes: Hydrostatic testing of pressure sanitary sewer and water piping.

B. Related Requirements:

1. Section 33 31 23 - Sanitary Sewerage Force Main Piping: Pipe materials and accessories normally encountered with municipal sanitary sewage force mains.

2. Section 33 14 16 - Site Water Utility Distribution Piping: Pipe materials and accessories normally encountered with pressurized water distribution systems.

1.2 REFERENCE STANDARDS

A. American Water Works Association:

1. AWWA C600 - Installation of Ductile-Iron Water Mains and their Appurtenances.

2. AWWA C605 - Underground Installation of Polyvinyl Chloride (PVC) and

Molecularly Oriented Polyvinyl Chloride (PVCO) Pressure Pipe and Fittings.

3. AWWA C900 - Polyvinyl Chloride (PVC) Pressure Pipe and Fabricated Fittings, for

Water Service.

4. AWWA C901 - Polyethylene (PE) Pressure Pipe and Tubing, for Water Service.

B. American Standard Testing Methods:

1. ASTM F 2164 - Standard Practice for Field Leak Testing of Polyethylene (PE) and

Crosslinked Polyethylene (PEX) Pressure Piping Systems Using Hydrostatic Pressure.

1.3 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Submit following items prior to start of testing:

1. Testing procedures.

2. List of test equipment.

3. Testing sequence schedule.

4. Provisions for disposal of flushing and test water.

5. Certification of test gage calibration.

C. Test and Evaluation Reports: Indicate results of piping tests.

D. Qualifications Statement:

1. Submit qualifications for applicator.

1.4 QUALIFICATIONS

A. Applicator: Company specializing in performing Work of this Section with minimum three years' documented experience.

Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 2 005153.0436

PART 2 - PRODUCTS

2.1 HYDROSTATIC TESTING

A. Equipment:

1. Pressure pump.

2. Pressure hose.

3. Water meter.

4. Test connections.

5. Pressure relief valve.

6. Pressure Gage: Calibrated to 0.1 psi.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Section 01 73 00 - Execution Requirements: Requirements for installation examination.

B. Verify that piping is ready for testing.

C. Verify that trenches are backfilled.

D. Verify that pressure piping thrust restraints have been installed.

3.2 FIELD QUALITY CONTROL

A. Section 01 40 00 - Quality Requirements: Requirements for inspecting and testing.

B. Testing of Pressure Ductile Iron or PVC Piping:

1. Test system according to AWWA C600 and following:

a. Hydrostatically test each portion of pressure piping, including valved section, at 1.5 times working pressure of piping, based on elevation of lowest point in piping corrected to elevation of test gage.

b. Conduct hydrostatic testing for at least two hours.

c. Slowly fill with water portion of piping to be tested, expelling air from piping at high points.

d. Install corporation cocks at high points.

e. Close air vents and corporation cocks after air is expelled.

f. Raise pressure to specified test pressure.

g. Observe joints, fittings, and valves undergoing testing.

h. Remove and renew cracked pipes, joints, fittings, and valves that show visible leakage.

i. Retest.

j. Correct visible deficiencies and continue testing at same test pressure for additional two hours to determine leakage rate.

k. Maintain pressure within plus or minus 5.0 psi of test pressure.

l. Leakage is defined as quantity of water supplied to piping necessary to maintain test pressure during period of testing.

m. Compute maximum allowable leakage using following formula:

1) L = [SD x sqrt(P)]/C.

Herbert, Rowland & Grubic, Inc. 33 05 05.31 - 3 005153.0436

2) L = testing allowance, gph.

3) S = length of pipe tested, feet.

4) D = nominal diameter of pipe, inches.

5) P = average test pressure during hydrostatic testing, psig.

6) C = 148,000.

7) If pipe undergoing testing contains sections of various diameters, calculate allowable leakage from sum of computed leakage for each pipe size.

2. If testing of piping indicates leakage greater than that allowed, locate source of leakage, make corrections, and retest until leakage is within acceptable limits.

3. Correct visible leaks regardless of quantity of leakage.

C. Testing of Pressure PE Piping:

1. Test system according to ASTM F 2164 and following:

a. Hydrostatically test each portion of pressure piping, including valved section, at 1.5 times working pressure of piping, based on elevation of lowest point in piping corrected to elevation of test gage.

b. Initial expansion phase:

1) Slowly fill with water portion of piping to be tested, expelling air from piping at high points.

2) Install corporation cocks at high points.

3) Close air vents and corporation cocks after air is expelled.

4) Raise pressure to specified test pressure.

5) Observe joints, fittings, and valves undergoing testing.

6) Add make-up water as necessary to maintain maximum test pressure for 4 hours.

c. Test Phase.

d. Immediately after expansion phase, reduce test pressure by 10 psi and stop adding makeup water.

e. Monitor pressure for 1 hour.

f. Remove and renew cracked pipes, joints, fittings, and valves that show visible leakage.

g. Retest after section is depressurized for 8 hours, minimum.

h. If no visual leakage is observed and test pressure remains within 5% of the target pressure, no leakage is indicated.

2. If testing of piping indicates leakage, locate source of leakage, make corrections, and retest until leakage is within acceptable limits.

3. Correct visible leaks regardless of quantity of leakage.

END OF SECTION