31 23 16 - Excavation.pdf

PDF 216 KB Posted

Attached to
Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153. 0436
Solicitation number
Not on record
Issued by
Monroe County, Pennsylvania

About this file

This is a technical specification document for excavation work related to the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) in Canadensis, Pennsylvania. The excavation section specifies unclassified excavation requirements for paving, roads, parking areas, slabs-on-grade, and site structures associated with the sewage treatment plant upgrades. The work includes removal of all subsurface materials encountered, including soil, fill, shale, rock, hardpan, boulders, and miscellaneous materials, with the contract price covering excavation, handling, reuse, stockpiling, and lawful disposal of excavated materials. The specification requires submission of an excavation protection plan describing sheeting, shoring, and bracing materials with structural calculations, prepared under the direct supervision of a Pennsylvania-licensed Professional Engineer. A pre-bid conference is scheduled for August 25, 2026 at 10:30 AM at the Skytop Lodge STP site, with bid opening set for September 18, 2026 at 10:00 AM via PennBid, and bid security of not less than 10% is required.

The specification prohibits blasting and explosive use, requiring mechanical excavation methods including ripping, hydraulic hammering, drilling, sawing, or splitting for rock removal. All contractors must call the Pennsylvania One Call System at least three working days before beginning work to locate and mark underground utilities. The specification mandates protection of existing structures, utilities, landscaping, and survey control points, with notification required to the Engineer for any unexpected subsurface conditions. Field quality control includes inspection of excavation and controlled fill operations in accordance with applicable codes, with visual inspection of bearing surfaces required before subsequent work installation. The contract documents are available through the PennBid website at https://pennbid.bonfirehub.com/, where all official notifications and addenda will be posted.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

31 23 16 - EXCAVATION

Herbert, Rowland & Grubic, Inc. 31 23 16 - 1 005153.0436

SECTION 31 23 16 - EXCAVATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Excavating for paving, roads, and parking areas.

2. Excavating for slabs-on-grade.

3. Excavating for site structures.

B. Related Sections:

1. Section 31 05 13 - Soils for Earthwork: Stockpiling excavated materials.

2. Section 31 05 16 - Aggregates for Earthwork: Stockpiling excavated materials.

3. Section 31 22 13 - Rough Grading: Topsoil and subsoil removal from site surface.

4. Section 31 23 16.13 – Trenching: Excavating for utility trenches.

5. Section 31 23 16.26 - Rock Removal: Removal of rock during excavating.

6. Section 33 14 16 - Site Water Utility Distribution Piping.

7. Document 00 31 32: Geotechnical report; bore hole locations and findings of subsurface materials.

C. Blasting and the use of explosives are prohibited.

1.2 REFERENCES

A. Local utility standards when working within 24 inches of utility lines.

1.3 EXCAVATION CLASSIFICATION

A. Excavation required under this Section is unclassified. Excavation includes removal of all materials encountered, regardless of character, including soil, fill, shale, rock, hardpan, boulders, and miscellaneous subsurface materials.

B. The Contract Price includes excavation, handling, reuse, stockpiling, and lawful disposal of excavated materials. No separate measurement or payment will be made based on the character of the material encountered.

C. This excavation classification does not modify the rights and responsibilities of Owner and Contractor concerning differing subsurface conditions, Underground Facilities, or Hazardous Environmental Conditions under the General Conditions.

1.4 SUBMITTALS

A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.

B. Excavation Protection Plan: Describe sheeting, shoring, and bracing materials and installation required to protect excavations and adjacent structures and property; include structural calculations to support plan.

Herbert, Rowland & Grubic, Inc. 31 23 16 - 2 005153.0436

C. Shop Drawings: Indicate soil densification grid for each size and configuration footing requiring soils densification.

1.5 QUALIFICATIONS

A. Prepare excavation protection plan under direct supervision of Professional Engineer experienced in design of this Work and licensed in the State of Pennsylvania

PART 2 - PRODUCTS - NOT USED.

PART 3 - EXECUTION

3.1 PREPARATION

A. Call Pennsylvania One Call System, Inc. at 1-800-242-1776 not less than three working days before performing Work.

1. Request underground utilities to be located and marked within and surrounding construction areas.

B. Identify required lines, levels, contours, and datum.

C. Protect utilities indicated to remain from damage.

D. Protect plant life, lawns, and other features remaining as portion of final landscaping.

E. Protect bench marks, survey control points, existing structures, fences, sidewalks, paving, and curbs from excavating equipment and vehicular traffic.

3.2 EXCAVATION

A. Underpin adjacent structures which may be damaged by excavation work.

B. Excavate subsoil to accommodate building foundations, slabs-on-grade paving and site structures, and construction operations.

C. Slope banks with machine to angle of repose or less until shored.

D. Do not interfere with 45 degree bearing splay of foundations.

E. Grade top perimeter of excavation to prevent surface water from draining into excavation.

F. Trim excavation. Remove loose matter.

G. Remove lumped subsoil, boulders, and rock up to 1/3 cu yd measured by volume. Remove larger material as specified in Section 31 23 16.26.

H. Notify Engineer of unexpected subsurface conditions.

I. Correct areas over excavated as directed by Engineer.

Herbert, Rowland & Grubic, Inc. 31 23 16 - 3 005153.0436

J. Remove excess and unsuitable material from site.

K. Repair or replace items indicated to remain damaged by excavation.

3.3 ROCK EXCAVATION

A. Remove rock using mechanical methods, including ripping, hydraulic hammering, drilling, sawing, or splitting.

B. Blasting and the use of explosives are not permitted.

3.4 FIELD QUALITY CONTROL

A. Section 01 40 00 - Quality Requirements: Field inspecting, testing, adjusting, and balancing.

B. Request inspection of excavation and controlled fill operations in accordance with applicable code.

C. Request visual inspection of bearing surfaces by inspection agency before installing subsequent work.

3.5 PROTECTION

A. Prevent displacement or loose soil from falling into excavation; maintain soil stability.

B. Protect bottom of excavations and soil adjacent to and beneath foundation from freezing.

C. Protect structures, utilities and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth operations.

END OF SECTION

File details come from the government source that posted it. Updated .