31 10 00 - Site Clearing.pdf
PDF 208 KB Posted
- Attached to
- Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153.0436
- Solicitation number
- US.247986
- Issued by
- Monroe County, Pennsylvania
About this file
This is a Scope of Work document prepared by Herbert, Rowland & Grubic, Inc. for the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) in Canadensis, Pennsylvania. The document details site clearing requirements as the initial phase of construction. Work includes removal of surface debris, designated paving and curbs, trees, shrubs, and plant life, abandoned utilities, and topsoil excavation. The scope specifies clearing and grubbing to a minimum depth of 12 inches for site access, application of herbicide to remaining stumps, removal of all debris from the site with continuous cleanup, and stockpiling of excavated topsoil to a maximum depth of 35 feet in a designated area. A pre-bid conference is scheduled for August 25, 2026 at 10:30 AM at the Skytop Lodge STP facility located at Falls Road, Canadensis, PA 18325. Bids are due by September 18, 2026 at 10:00 AM and will be publicly opened on that date through PennBid.
The document requires contractors to comply with Pennsylvania Department of Environmental Protection Regulations and mandates that all debris be disposed of at locations outside the Owner's property, permanent easement, or right of way in accordance with applicable laws. Contractors must contact the Local Utility Line Information service at least three working days before performing work to locate and mark underground utilities. All submittals, including herbicide product data and disposal agreements with property owners releasing the Owner from liability, must be provided per submittal procedures. Bid security in the form of a Certified Check or Bid Bond is required in an amount not less than 10 percent. Topsoil excavation is restricted to dry conditions and must be kept separate from foreign materials for use in finish grading.
View the file
Other files
Show 40 more
Latest 50 of 157 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
31 10 00 - SITE CLEARING
Herbert, Rowland & Grubic, Inc. 31 10 00 - 1 005153.0436
SECTION 31 10 00 - SITE CLEARING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Removing surface debris.
2. Removing designated paving and curbs.
3. Removing designated trees, shrubs, and other plant life.
4. Removing abandoned utilities.
5. Excavating topsoil.
B. Related Sections:
1. Section 31 22 13 - Rough Grading.
2. Section 31 23 16.26 – Rock Removal.
1.2 DEFINITIONS
A. Clearing is defined as the removal of trees, brush, down timber, rotten wood, rubbish, any other vegetation, and other material at or above original ground elevation not designated to be saved. Clearing also includes removal and replacement of fences, walls, guideposts, guide rail, signs, and other obstructions interfering with the proposed work.
B Grubbing is defined as the removal from below the surface of the natural ground of stumps, roots and stubs, brush, topsoil, organic materials and debris.
1.3 SUBMITTALS
A. Section 01 33 00 - Submittal Procedures: Requirements for submittals.
B. Product Data: Submit data for herbicide. Indicate compliance with applicable codes for environmental protection.
C. Permits for Disposal of Debris:
1. Arrange for disposal of debris to locations outside the Owner's property, permanent easement, or right of way. Comply with all applicable laws.
2. Submit two copies of any agreement with each property owner releasing the
Owner from responsibility in connection with the disposal of the debris.
1.4 QUALITY ASSURANCE
A. Conform to applicable Pennsylvania Department of Environmental Protection Regulations.
Herbert, Rowland & Grubic, Inc. 31 10 00 - 2 005153.0436
PART 2 - PRODUCTS - NOT USED.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Section 01 73 00 - Execution Requirements: Verification of existing conditions before starting work.
B. Verify existing plant life designated to remain is tagged or identified.
3.2 PREPARATION
A. Call Local Utility Line Information service not less than three (3) working days before performing Work:
1. Request underground utilities to be located and marked within and surrounding construction areas.
3.3 PROTECTION
A. Locate, identify, and protect utilities indicated to remain, from damage.
B. Protect bench marks, survey control points, and existing structures from damage or displacement.
3.4 CLEARING
A. Clear and grub areas required for access to site and execution of Work to minimum depth of 12 inches.
B. Remove trees and shrubs.
C. Clear undergrowth and deadwood, without disturbing subsoil.
D. Apply herbicide to remaining stumps to inhibit growth.
3.5 REMOVAL
A. Remove debris, rock, and extracted plant life from site.
B. Remove paving and curbs.
C. Continuously clean-up and remove waste materials from site. Do not allow materials to accumulate on site.
E. Do not burn or bury materials on site. Leave site in clean condition.
3.6 TOPSOIL EXCAVATION
A. Excavate topsoil from areas to be further excavated, relandscaped, or regraded without
Herbert, Rowland & Grubic, Inc. 31 10 00 - 3 005153.0436 mixing with foreign materials for use in finish grading.
B. Do not excavate wet topsoil.
C. Stockpile in area designated on site to depth not exceeding 35 feet and protect from erosion.
END OF SECTION