01 32 36 - Video Monitoring and Documentation.pdf

PDF 215 KB Posted

Attached to
Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153. 0436
Solicitation number
Not on record
Issued by
Monroe County, Pennsylvania

About this file

This is a technical specification document for the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) in Canadensis, Pennsylvania. The specification outlines requirements for video monitoring and documentation services during construction of sewage treatment plant upgrades, including installation of an influent screening system, equalization tank, chemical feed system, two clarifier tanks, post aeration tank, and UV disinfection system. The contractor is required to submit a key plan identifying video recording vantage points, conduct preconstruction video recordings before work begins to document existing site and building conditions, and perform monthly periodic construction video recordings coordinated with each Application for Payment. A pre-bid conference is scheduled for August 25, 2026 at 10:30 AM at Skytop Lodge STP in Canadensis, Pennsylvania, with bid opening on Friday, September 18, 2026 at 10:00 AM via PennBid. Bid security must be furnished in the form of a Certified Check or Bid Bond in an amount not less than 10%.

Video recordings must be submitted within seven days of recording via large file exchange website and must include detailed identification information, weather conditions, and transcripts prepared on 8.5-by-11-inch paper in heavy-duty three-ring binders. All recordings must be conducted during periods of good visibility without precipitation or snow cover, with a minimum recording time of 15 minutes for periodic construction videos. The contractor must transfer copyright usage rights to the Owner for unlimited use and reproduction of video documentation. Outdoor coverage must include driveways, sidewalks, curbs, ditches, streets, landscaping, utilities, and building exteriors within zones of influence, with all media storage properly identified by number, date, location, and project name. Bidding documents are available at https://pennbid.bonfirehub.com/, and all official notifications and addenda will be provided only through this designated website.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 32 36 - VIDEO MONITORING AND DOCUMENTATION

Herbert, Rowland & Grubic, Inc. 01 32 36 - 1 005153.0436

SECTION 01 32 36 - VIDEO MONITORING AND DOCUMENTATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Preconstruction video recordings.

2. Periodic construction video recordings.

B. Related Sections:

1. Section 01 33 00 – Submittals: Procedures for submitting photographic documentation.

2. Section 01 77 00 – Closeout Procedures: Procedures for submitting photographic documentation as project record documents at Project closeout.

1.2 SUBMITTALS

A. Key Plan: Submit key plan of Project site and building with notation of vantage points marked for location and direction of each video recording. Indicate elevation or story of construction. Include same information as corresponding video documentation.

B. Video Recordings: Submit video recordings within [seven] <Insert number> days of recording:

1. Submit video recordings by posting to a large file exchange website.

2. Identification: With each submittal, provide the following information:

a. Name of Project.

b. Name and address of photographer.

c. Name of Engineer.

d. Name of Contractor.

e. Date video recording was recorded.

f. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

g. Weather conditions at time of recording.

3. Transcript: Prepared on 8-1/2-by-11-inch paper, punched and bound in heavy-duty, three-ring, vinyl-covered binders. Mark appropriate identification on front and spine of each binder. Include a cover sheet with same label information as corresponding video recording. Include name of Project and date of video recording on each page.

1.3 USAGE RIGHTS

A. Transfer copyright usage rights to Owner for unlimited use and reproduction of video documentation.

Herbert, Rowland & Grubic, Inc. 01 32 36 - 2 005153.0436

PART 2 - PRODUCTS - NOT USED.

PART 3 - EXECUTION

3.1 GENERAL

A. Take videos using the maximum range of depth of field, and that are in focus, to clearly show the Work. Videos with blurry or out-of-focus areas will not be accepted:

1. Maintain key plan with each set of construction photographs that identifies each location.

3.2 VIDEO TAPING PROCEDURE

A. All video to be done during periods of good visibility and not during periods of visible precipitation or while ground is covered by snow.

B. Control direction of travel, panning rates, and zoom in-out rates in a manner that produces clarity of subject during playback.

C. Include in outdoor video coverage driveways, sidewalks, curbs, ditches (to show drainage patterns), street (as full width as possible), landscaping, trees, shrubs, culverts, catch basins, retaining walls, headwalls, fences, visible utilities, and building exteriors within the zones of influence. Buildings should be identified both audibly and visibly when possible.

D. Properly identify all media storage by number, date, locations and project name. Begin each storage media with current date, project name and municipality.

E. Supply an index run sheet with a record of each media storage device contents and identify locations, station numbers, line numbers, etc., referenced to time and date encoded in video.

3.3 CONSTRUCTION VIDEO RECORDINGS

A. Preconstruction Video Recording: Before starting construction, record video recording of Project site and surrounding properties from sufficiently different vantage points to completely record the state of the site and existing building in and around the construction area. Coordinate with Owner Representative to ensure no sensitive areas outside of the limits of construction are videotaped:

1. Flag construction limits before recording construction video recordings.

2. Show existing conditions adjacent to Project site before starting the Work.

3. Show existing building on site to accurately record physical conditions at the start of construction.

4. Show protection efforts by Contractor.

B. Periodic Construction Video Recordings: Record video recording monthly with the cutoff date associated with each Application for Payment. Select vantage points to show status of construction and progress since last video recordings were recorded:

Herbert, Rowland & Grubic, Inc. 01 32 36 - 3 005153.0436

1. Video shall sufficiently show how construction is affecting the existing structure and site, and the efforts of the Contractor to protect existing site and structures.

2. Minimum recording time shall be 15 minutes.

END OF SECTION