01 31 13 - Project Coordination.pdf
PDF 214 KB Posted
- Attached to
- Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153.0436
- Solicitation number
- US.247986
- Issued by
- Monroe County, Pennsylvania
About this file
This is a Project Coordination specification document for the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) in Pennsylvania, prepared by Herbert, Rowland & Grubic, Inc. The project involves construction of sewage treatment plant upgrades including installation of an Influent Screening System, Equalization Tank, Chemical Feed System, two Clarifier Tanks, a Post Aeration Tank, and a UV Disinfection System. Bids are due and will be publicly opened on Friday, September 18, 2026, at 10:00 AM via PennBid. A pre-bid conference is scheduled for August 25, 2026, at 10:30 AM at the Skytop Lodge STP located at Falls Road, Canadensis, PA 18325. Attendance at the pre-bid conference is encouraged but not mandatory. Bidding documents are available for download through the designated PennBid website at https://pennbid.bonfirehub.com/, which will be periodically updated with addenda and other relevant information.
The specification establishes coordination and project management requirements for the contractor throughout construction. The contractor must coordinate scheduling, submittals, and work sequencing to ensure efficient and orderly installation of interdependent construction elements. The work involves modifications to and demolition of existing facilities while maintaining continuity of owner operations throughout construction, with the facility remaining occupied during the project. The contractor is responsible for all costs associated with damage to existing facilities and must furnish alternate equivalent facilities if contractor operations render existing facilities unavailable prior to their scheduled removal. Bid security in the form of a Certified Check or Bid Bond is required in an amount not less than 10% of the bid. All questions regarding the bidding documents must be submitted via PennBid in accordance with the Instructions to Bidders.
View the file
Other files
Show 40 more
Latest 50 of 157 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
01 31 13 - PROJECT COORDINATION
Herbert, Rowland & Grubic, Inc. 01 31 13 - 1 005153.0436
SECTION 01 31 13 - PROJECT COORDINATION
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Coordination and Project conditions.
B. Related Sections
1. Section 01 32 16 - Construction Progress Schedule: preparing and submitting
Contractor's construction schedule.
2. Section 01 73 00 - Execution: procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Section 01 77 00 - Closeout Procedures: coordinating closeout of the Contract.
1.2 COORDINATION AND PROJECT CONDITIONS
A. Coordinate scheduling, submittals, and Work of various Sections of Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.
B. Verify that utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate Work of various Sections having interdependent responsibilities for installing, connecting to, and placing operating equipment in service.
C. Coordinate space requirements, supports, and installation of mechanical and electrical Work indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit as closely as practical; place runs parallel with lines of building. Use spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs:
1. Coordination Drawings: Prepare as required to coordinate all portions of Work.
Show relationship and integration of different construction elements that require coordination during fabrication or installation to fit in space provided or to function as intended. Indicate locations where space is limited for installation and access and where sequencing and coordination of installations are important.
D. Coordination Meetings: In addition to other meetings specified in this Section, hold coordination meetings with personnel and Subcontractors to ensure coordination of Work.
E. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within construction. Coordinate locations of fixtures and outlets with finish elements.
F. Coordinate completion and clean-up of Work of separate Sections in preparation for Substantial Completion.
Herbert, Rowland & Grubic, Inc. 01 31 13 - 2 005153.0436
G. After Owner's occupancy of premises, coordinate access to Site for correction of defective Work and Work not complying with Contract Documents, to minimize disruption of Owner's activities.
1.3 COORDINATION AND MAINTENANCE OF SERVICE DURING CONSTRUCTION
A. The Contractor(s) will, at all times throughout the Work, cooperate fully with the Owner in maintaining all necessary utility services to the public.
B. The Work involves modifications to and the demolition of existing facilities and structures which must be completed in sequence with one another due to the physical requirements of the Work or the need to maintain operations of existing facility.
C. Should the Contractor's operations damage any existing facilities and render them unavailable for continued use prior to the scheduled time for their removal, the Contractor will take immediate action to furnish, install, and place into operation alternate equivalent facilities. Should only minor repairs be required to the existing facilities, the Contractor shall immediately make such necessary repairs and restore the existing facilities to full service. All costs for such repairs or additional costs for operation of alternate facilities for a period of time longer than planned will be paid for by the Contractor.
D. The nature, location, capacity, and type of facilities proposed for maintaining continuity of Owner operations will at all times are subject to the approval of the Engineer.
PART 2 - PRODUCTS - Not Used.
PART 3 - EXECUTION
3.1 ALTERATION PROCEDURES
A. Entire facility will be occupied for normal operations during progress of construction.
Cooperate with Owner in scheduling operations to minimize conflict and to permit continuous usage:
1. Perform Work not to interfere with operations of occupied areas.
2. Keep utility and service outages to a minimum and perform only after written approval of Owner.
3. Clean Owner-occupied areas daily. Clean spillage, overspray, and heavy collection of dust in Owner-occupied areas immediately.
B. Materials: As specified in product Sections; match existing products with new products for patching and extending Work.
C. Employ skilled and experienced installer to perform alteration and renovation Work.
D. Cut, move, or remove items as necessary for access to alterations and renovation Work.
Replace and restore at completion. Comply with Section 01 73 00 - Execution Requirements
Herbert, Rowland & Grubic, Inc. 01 31 13 - 3 005153.0436
E. Remove unsuitable material not marked for salvage, including rotted wood, corroded metals, and deteriorated masonry and concrete. Replace materials as specified for finished Work.
F. Remove debris and abandoned items from area and from concealed spaces.
G. Prepare surface and remove surface finishes to permit installation of new Work and finishes.
H. Close openings in exterior surfaces to protect existing Work from weather and extremes of temperature and humidity.
I. Remove, cut, and patch Work to minimize damage and to permit restoring products and finishes to original or specified condition.
J. Refinish existing visible surfaces to remain in renovated rooms and spaces, to specified condition for each material, with neat transition to adjacent finishes.
K. Where new Work abuts or aligns with existing Work, provide smooth and even transition.
Patch Work to match existing adjacent Work in texture and appearance.
L. When finished surfaces are cut so that smooth transition with new Work is not possible, terminate existing surface along straight line at natural line of division and submit recommendation to Engineer for review.
M. Where change of plane of 1/4 inch or more occurs, request instructions from Engineer.
N. Trim existing doors to clear new floor finish. Refinish trim to original or specified condition.
O. Patch or replace portions of existing surfaces that are damaged, lifted, discolored, or showing other imperfections.
P. Finish surfaces as specified in individual product Sections.
END OF SECTION
File details come from the government source that posted it. Updated .