01 31 13 - Project Coordination.pdf

PDF 214 KB Posted

Attached to
Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153.0436
Solicitation number
US.247986
Issued by
Monroe County, Pennsylvania

About this file

This is a Project Coordination specification document for the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) in Pennsylvania, prepared by Herbert, Rowland & Grubic, Inc. The project involves construction of sewage treatment plant upgrades including installation of an Influent Screening System, Equalization Tank, Chemical Feed System, two Clarifier Tanks, a Post Aeration Tank, and a UV Disinfection System. Bids are due and will be publicly opened on Friday, September 18, 2026, at 10:00 AM via PennBid. A pre-bid conference is scheduled for August 25, 2026, at 10:30 AM at the Skytop Lodge STP located at Falls Road, Canadensis, PA 18325. Attendance at the pre-bid conference is encouraged but not mandatory. Bidding documents are available for download through the designated PennBid website at https://pennbid.bonfirehub.com/, which will be periodically updated with addenda and other relevant information.

The specification establishes coordination and project management requirements for the contractor throughout construction. The contractor must coordinate scheduling, submittals, and work sequencing to ensure efficient and orderly installation of interdependent construction elements. The work involves modifications to and demolition of existing facilities while maintaining continuity of owner operations throughout construction, with the facility remaining occupied during the project. The contractor is responsible for all costs associated with damage to existing facilities and must furnish alternate equivalent facilities if contractor operations render existing facilities unavailable prior to their scheduled removal. Bid security in the form of a Certified Check or Bid Bond is required in an amount not less than 10% of the bid. All questions regarding the bidding documents must be submitted via PennBid in accordance with the Instructions to Bidders.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 31 13 - PROJECT COORDINATION

Herbert, Rowland & Grubic, Inc. 01 31 13 - 1 005153.0436

SECTION 01 31 13 - PROJECT COORDINATION

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Coordination and Project conditions.

B. Related Sections

1. Section 01 32 16 - Construction Progress Schedule: preparing and submitting

Contractor's construction schedule.

2. Section 01 73 00 - Execution: procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.

3. Section 01 77 00 - Closeout Procedures: coordinating closeout of the Contract.

1.2 COORDINATION AND PROJECT CONDITIONS

A. Coordinate scheduling, submittals, and Work of various Sections of Project Manual to ensure efficient and orderly sequence of installation of interdependent construction elements.

B. Verify that utility requirements and characteristics of operating equipment are compatible with building utilities. Coordinate Work of various Sections having interdependent responsibilities for installing, connecting to, and placing operating equipment in service.

C. Coordinate space requirements, supports, and installation of mechanical and electrical Work indicated diagrammatically on Drawings. Follow routing shown for pipes, ducts, and conduit as closely as practical; place runs parallel with lines of building. Use spaces efficiently to maximize accessibility for other installations, for maintenance, and for repairs:

1. Coordination Drawings: Prepare as required to coordinate all portions of Work.

Show relationship and integration of different construction elements that require coordination during fabrication or installation to fit in space provided or to function as intended. Indicate locations where space is limited for installation and access and where sequencing and coordination of installations are important.

D. Coordination Meetings: In addition to other meetings specified in this Section, hold coordination meetings with personnel and Subcontractors to ensure coordination of Work.

E. In finished areas except as otherwise indicated, conceal pipes, ducts, and wiring within construction. Coordinate locations of fixtures and outlets with finish elements.

F. Coordinate completion and clean-up of Work of separate Sections in preparation for Substantial Completion.

Herbert, Rowland & Grubic, Inc. 01 31 13 - 2 005153.0436

G. After Owner's occupancy of premises, coordinate access to Site for correction of defective Work and Work not complying with Contract Documents, to minimize disruption of Owner's activities.

1.3 COORDINATION AND MAINTENANCE OF SERVICE DURING CONSTRUCTION

A. The Contractor(s) will, at all times throughout the Work, cooperate fully with the Owner in maintaining all necessary utility services to the public.

B. The Work involves modifications to and the demolition of existing facilities and structures which must be completed in sequence with one another due to the physical requirements of the Work or the need to maintain operations of existing facility.

C. Should the Contractor's operations damage any existing facilities and render them unavailable for continued use prior to the scheduled time for their removal, the Contractor will take immediate action to furnish, install, and place into operation alternate equivalent facilities. Should only minor repairs be required to the existing facilities, the Contractor shall immediately make such necessary repairs and restore the existing facilities to full service. All costs for such repairs or additional costs for operation of alternate facilities for a period of time longer than planned will be paid for by the Contractor.

D. The nature, location, capacity, and type of facilities proposed for maintaining continuity of Owner operations will at all times are subject to the approval of the Engineer.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION

3.1 ALTERATION PROCEDURES

A. Entire facility will be occupied for normal operations during progress of construction.

Cooperate with Owner in scheduling operations to minimize conflict and to permit continuous usage:

1. Perform Work not to interfere with operations of occupied areas.

2. Keep utility and service outages to a minimum and perform only after written approval of Owner.

3. Clean Owner-occupied areas daily. Clean spillage, overspray, and heavy collection of dust in Owner-occupied areas immediately.

B. Materials: As specified in product Sections; match existing products with new products for patching and extending Work.

C. Employ skilled and experienced installer to perform alteration and renovation Work.

D. Cut, move, or remove items as necessary for access to alterations and renovation Work.

Replace and restore at completion. Comply with Section 01 73 00 - Execution Requirements

Herbert, Rowland & Grubic, Inc. 01 31 13 - 3 005153.0436

E. Remove unsuitable material not marked for salvage, including rotted wood, corroded metals, and deteriorated masonry and concrete. Replace materials as specified for finished Work.

F. Remove debris and abandoned items from area and from concealed spaces.

G. Prepare surface and remove surface finishes to permit installation of new Work and finishes.

H. Close openings in exterior surfaces to protect existing Work from weather and extremes of temperature and humidity.

I. Remove, cut, and patch Work to minimize damage and to permit restoring products and finishes to original or specified condition.

J. Refinish existing visible surfaces to remain in renovated rooms and spaces, to specified condition for each material, with neat transition to adjacent finishes.

K. Where new Work abuts or aligns with existing Work, provide smooth and even transition.

Patch Work to match existing adjacent Work in texture and appearance.

L. When finished surfaces are cut so that smooth transition with new Work is not possible, terminate existing surface along straight line at natural line of division and submit recommendation to Engineer for review.

M. Where change of plane of 1/4 inch or more occurs, request instructions from Engineer.

N. Trim existing doors to clear new floor finish. Refinish trim to original or specified condition.

O. Patch or replace portions of existing surfaces that are damaged, lifted, discolored, or showing other imperfections.

P. Finish surfaces as specified in individual product Sections.

END OF SECTION