01 26 00 - Contract Modifications.pdf

PDF 217 KB Posted

Attached to
Skytop Lodge Sewage Treatment Plant Improvements Project – Contract : 2026-01- Project Number 005153. 0436
Solicitation number
Not on record
Issued by
Monroe County, Pennsylvania

About this file

This is a Contract Modification Procedures specification document for the Skytop Lodge Sewage Treatment Plant Improvements Project (Contract 2026-01, Project Number 005153.0436) in Pennsylvania. The project involves construction of sewage treatment plant upgrades, including installation of an Influent Screening System, Equalization Tank, Chemical Feed System, two Clarifier Tanks, a Post Aeration Tank, UV Disinfection System, and associated work. Bids are due on Friday, September 18, 2026 at 10:00 AM local time through PennBid, with a pre-bid conference scheduled for August 25, 2026 at 10:30 AM at the Skytop Lodge STP facility in Canadensis, Pennsylvania. Bidding documents are available through the designated PennBid website, which will be updated periodically with addenda and other relevant information.

The specification document establishes procedures for contract modifications, including processes for change orders, work change directives, proposal requests, and requests for interpretation. Contractors must identify an authorized representative to receive change documents and must submit estimates within 10 days of receiving proposal requests. Change orders require owner approval and engineer issuance, with contractors responsible for maintaining detailed records and updated schedules reflecting any authorized modifications. Bid security must be provided in the form of a certified check or bid bond in an amount not less than 10%. All questions regarding the bidding documents must be submitted through PennBid in accordance with the Instructions to Bidders.

View the file

Other files

File Type Posted
33 05 97 - Identification And Signage For Utilities.pdf PDF
26 29 13 - Contactors and Motor Starting Equipment.pdf PDF
26 05 10 - Basic Electrical Materials & Methods.pdf PDF
01 78 36 - Warranties.pdf PDF
26 12 19.01 - Liquid Filled Medium Voltage Pad Mounted Transformers.pdf PDF
01 61 00 - Product Requirements.pdf PDF
03 39 00 - Concrete Curing.pdf PDF
00 01 07 - Seal Page.pdf PDF
01 78 39 - Project Record Documents.pdf PDF
01 29 00 - Payment Procedures.pdf PDF
01 73 00 - Execution Requirements.pdf PDF
43 26 13 - Submersible Sewage Pumps.pdf PDF
33 05 77 Packaged Metering Manhole.pdf PDF
01 10 00 - Project Summary.pdf PDF
26 05 73 - Power System Study and Testing.pdf PDF
00 65 19.16 - Affidavit of Release of Liens.pdf PDF
02 41 19.13 - SELECTIVE BUILDING DEMOLITION.pdf PDF
33 05 05.36 - Vacuum Testing.pdf PDF
40 05 51 - Common Requirements For Process Valves.pdf PDF
01 26 13 - Requests for Interpretation.pdf PDF
00 73 36 - Equal Employment Opportunity Requirements.pdf PDF
40 05 62 - Plug Valves.pdf PDF
26 24 16 - Panelboards.pdf PDF
00 45 36 EEO Certificate.pdf PDF
46 66 16 - Trojan Open Channel UV Disinfection System.pdf PDF
00 72 00 - General Conditions 2018.pdf PDF
40 23 23 - Potable Water Process Piping.pdf PDF
31 23 19 - Dewatering.pdf PDF
40 95 34 a- IOList Table.pdf PDF
01 50 00 - Temporary Facilities and Controls.pdf PDF
00 31 32 - Geotechnical Data.pdf PDF
01 57 28 - Temporary Flow Control.pdf PDF
31 05 16 - Aggregate for Earthwork.pdf PDF
00 65 19.23 - Notice of Acceptability of Work.pdf PDF
00 60 00 - Project Forms.pdf PDF
01 22 00 - Unit Prices.pdf PDF
06 10 00 - Rough Carpentry.pdf PDF
40 05 53 - Identification For Process Piping.pdf PDF
06 17 53 - Shop-Fabricated Wood Trusses.pdf PDF
00 45 19 Non Collusion Affidavit.pdf PDF
40 05 23 - Stainless Steel Process Pipe And Tubing.pdf PDF
26 05 33.16 - Boxes.pdf PDF
26 05 29 - Electrical Supports, Anchors and Fasteners.pdf PDF
41 22 23.16 - Portable Hoists.pdf PDF
26 32 13 - Packaged Engine Generator Systems.pdf PDF
31 23 16.13 - Trenching.pdf PDF
01 33 00 - Submittal Procedures.pdf PDF
46 43 21 Packaged Wastewater Treatment Plant Equipment.pdf PDF
13 34 00 - Pre-engineered Post Frame Structures.pdf PDF
01 41 26 - Permit Requirements.pdf PDF
Show 40 more

Latest 50 of 157 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

01 26 00 – CONTRACT MODIFICATION PROCEDURES

Herbert, Rowland & Grubic, Inc. 01 26 00 - 1 005153.0436

SECTION 01 26 00 - CONTRACT MODIFICATION PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. Section Includes:

1. Change procedures.

B. Related Sections:

1. Document 00 60 00 - Project Forms.

2. Document 00 63 13 - RFI Form.

3. Document 00 63 49 - Work Change Directive Form.

4. Document 00 63 63 - Change Order Form.

5. Section 01 26 13 – Requests for Interpretation.

1.2 CHANGE PROCEDURES

A. Submittals: Submit name of individual who is authorized to receive change documents and is responsible for informing others in Contractor's employ or Subcontractors of changes to the Work.

B. Carefully study and compare Contract Documents before proceeding with fabrication and installation of Work. Promptly advise Engineer of any error, inconsistency, omission, or apparent discrepancy.

C. Requests for Interpretation (RFI) and Clarifications: Allot time in construction scheduling for liaison with Engineer; establish procedures for handling queries and clarifications:

1. Refer to Section 01 26 13 - Requests for Interpretation.

2. Engineer may respond with a direct answer on the Request for Interpretation form, Field Order, or Proposal Request.

1.3 MINOR CHANGES IN THE WORK

A. Engineer will advise of minor changes in the Work not involving adjustment to Contract Price or Contract Time by issuing supplemental instructions on Field Order.

1.4 PROPOSAL REQUESTS

A. Owner-Initiated Proposal Requests: Engineer may issue Proposal Request including a detailed description of proposed change with supplementary or revised Drawings and Specifications with the period of time during which the requested price will be considered valid:

1. Proposal Requests issued by Engineer are not instructions either to stop work in progress or to execute the proposed change.

2. Contractor will prepare and submit estimate within 10 days:

a. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.

Herbert, Rowland & Grubic, Inc. 01 26 00 - 2 005153.0436

b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

c. Include costs of labor and equipment directly attributable to the change.

d. Include an updated Construction Schedule that indicates the effect of the change.

B. Contractor may propose changes by submitting a Change Proposal to Engineer, describing proposed change and its full effect on the Work. Include a statement describing reason for the change and the effect on Contract Price and Contract Time with full documentation and a statement describing effect on the Work by separate or other Contractors:

1. Notice: Comply with General Conditions where latent or changed conditions require modifications to the Contract.

2. Include quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made.

3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.

4. Include costs of labor and equipment directly attributable to the change.

5. Include an updated Construction Schedule that indicates the effect of the change.

C. Document requested substitutions according to Section 01 25 00 - Substitution Procedures.

1.5 CHANGE ORDER PROCEDURES

A. On Owner's approval of a Proposal Request, Engineer will issue a Change Order for execution by Owner and Contractor:

1. Change Order Forms: Document 00 63 63 - Change Order Form.

B. Stipulated Price Change Order: Based on Proposal Request and Contractor's price quotation or Contractor's request for Change Order as approved by Engineer.

C. Unit Price Change Order: For Contract unit prices and quantities, the Change Order will be executed on a fixed unit price basis. For unit costs or quantities of units of that which are not predetermined, execute Work under Work Directive Change.

D. Correlation of Contractor Submittals:

1. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as separate line item and adjust Contract Price.

2. Promptly revise Progress Schedules to reflect change in Contract Time, adjust times for other items of Work affected by the change, and resubmit.

3. Promptly enter changes in Record Documents.

1.6 WORK CHANGE DIRECTIVE

A. Engineer may issue directive, on Work Change Directive signed by Owner, instructing Contractor to proceed with change in the Work, for subsequent inclusion in a Change Order. Document will describe changes in the Work and designate method of determining any change in Contract Price or Contract Time. Promptly execute change.

Herbert, Rowland & Grubic, Inc. 01 26 00 - 3 005153.0436

B. Maintain detailed records of Work done on time and material basis. Provide full information required for evaluation of proposed changes and to substantiate costs for changes in the Work.

PART 2 - PRODUCTS - Not Used.

PART 3 - EXECUTION - Not Used.

END OF SECTION